The sections below outline how to collect data and perform analyses for each Travel Delay and Reliability measurement.
Existing Volume-to-Capacity Ratio
The volume-to-capacity ratio (V/C) is the ratio of the flow rate to the theoretical maximum capacity and as described in this Guidebook is measured using daily volumes and capacities for a higher-level evaluation of the degree of utilization for a corridor. A V/C over 1 indicates a location is over capacity. It should be noted that because this is a high-level analysis, a V/C below 1 does not necessarily indicate that a corridor is under capacity, and may have other operational issues such as weaving, merging, etc., which may be understood through qualitative input from corridor users, or in more complex studies may require more detailed modeling efforts.
Data
The data needed to document the volume-to-capacity ratio includes the following, with instructions included below:
- Annual Average Daily Traffic (AADT). Obtain the most recent daily vehicle volumes for each segment of the corridor using MnDOT’s Transportation Data Management System. (Note that the same AADT data is also requested in Step 2.)
- Capacity. Determine the capacity of the corridor by segment or intersection using the Highway Capacity Manual, published by the Transportation Research Board (TRB).
Documentation
Summarize corridor V/C using a table (or tables) that documents V/C by segment and/or intersection as applicable.
Future Volume-to-Capacity Ratio
The future V/C ratio estimates future V/C using forecasted volumes.
Data
The data needed to document the volume-to-capacity ratio includes the following, with instructions included below:
- Forecast AADT. Forecasted volumes can be calculated or obtained using some or all these sources:
- MnESAL Traffic Forecasting Tool on MnDOT’s Traffic Forecasting webpage
- Regional travel demand model or other local agency forecasts, if available
- Coordination with appropriate MnDOT point of contact for the project (usually the district traffic engineer)
- Coordination with MnDOT’s Section Director for Traffic Forecasting & Analysis (TFA) - contact information available here
- Capacity. Utilize the same capacity identified above. There may be some exceptions to this, such as if the future “no build” condition will include known capacity changes within the corridor outside of what is being studied in this corridor plan.
Documentation
Summarize corridor V/C using a table that documents V/C by segment.
Vehicle Miles Traveled
The existing vehicle miles traveled (VMT) metric will serve as a baseline to understand existing usage and provide information for Step 4.
Data
The data needed to document the volume-to-capacity ratio includes AADT (described above) and corridor length, which should be known at this point in the evaluation. Multiplying the AADT and corridor length in miles will provide a VMT.
- Traffic Volumes. See above for obtaining AADT and use only values where the AADT Code is from an actual seasonally adjusted count (see the superscript code in the application).
- Segment Lengths. For each AADT segment, document the length. If only a portion of the AADT segment is included in the corridor, document that portion.
The equations below describe how to calculate VMT using AADT and segment lengths. To convert AADT by segment to VMT, use Equation 1. Use Equation 2 to calculate total VMT that is the sum of all segments.
VMTx=AADT(SL*PL)
Where:
AADT = AADT of segment
SL = Segment length used for traffic forecast
PL = Portion of length of segment within the corridor bounds (i.e., if a SL is fully encompassed within the corridor the value = 1; if only a portion of the SL is within the corridor bounds, then the project value will be between 0-1 representing the portion of the project length from the point of the last segment to the end of the project limits)
VMT corridor=VMTa+VMTb+VMTd+VMTc+...
Where:
VMTX = Average Daily VMT output from each segment, with different sub-letters for each corresponding segment
VMTcorridor= Total Average Daily VMT forecasted in the affected area
Documentation
Create a table documenting corridor VMT.
Corridor Segment Number |
TFA Location ID |
Segment Length (miles) |
Current Average Annual Daily Traffic (AADT) |
1 |
|
|
|
2 |
|
|
|
3 |
|
|
|
4 |
|
|
|
Vehicle Travel Delay
According to MnDOT’s Traffic Engineering Manual (TEM), delay is defined as an interruption of normal travel involving a slowing or stopping. It is the difference between interrupted and uninterrupted travel times.
Data
ClearGuide, a traffic analysis tool developed by Iteris, is recommended as the primary, or initial, method for assessing vehicle travel delay in a corridor. ClearGuide allows MnDOT staff and consultants to access, analyze, and interpret traffic performance data across the state. MnDOT staff and consultants interested in using ClearGuide can request access through their MnDOT point of contact or apply online; access to ClearGuide requires MnDOT authorization. ClearGuide is only available for use on projects involving MnDOT roadways.
If there are more detailed traffic analysis needs, such as if the corridor study will contribute to an Intersection Control Evaluation (ICE) or other reasons mentioned in the table above, analysts can utilize other software, but guidance for that level of detail is not included here. Refer to the TEM linked above for more information on more detailed analysis methods and resources, such as Highway Capacity Model (HCM) and Highway Capacity Software (HCS), Synchro/SimTraffic, or Vissim, if determined to be appropriate for the corridor plan.
ClearGuide can be accessed at this link: https://mndot.iteris-clearguide.com/. Users not familiar with ClearGuide may need additional guidance for using this tool. Contact MnDOT’s RTMC for assistance, training, or more information.
Documentation
Summarize vehicle delay using tables, graphs, maps, or narratives as appropriate. Identify areas of concern.
Vehicle Travel Time Reliability
Similar to the Vehicle Travel Delay measurement above, the guidebook focuses on a high-level analysis of existing conditions using ClearGuide. If there are more detailed traffic analysis needs, refer to the TEM linked above for more information on other analysis methods and resources, such as HCS, Synchro/SimTraffic, or Vissim.
Data
Obtain vehicle travel time reliability information using ClearGuide (detail above).
Documentation
Summarize vehicle delay using tables, graphs, maps, or narratives as appropriate. Identify areas of concern.
Truck Travel Time Reliability
MnDOT routinely collects truck data using in-ground sensors and other tools. That data is used to calculate reliability through a Truck Travel Time Reliability Index (TTTRI), which is a federally defined measure calculated by the ratio between the 95th percentile travel times (slow vehicles) and 50th percentile (average truck travel times). A higher TTTRI represents conditions where truck travel time reliability is a concern.
Data
MnDOT publishes a Freight Bottleneck Report that includes a statewide map identifying the TTTRI for state highways. The report is updated every two years; use the most recent version available.
Documentation
Document the TTTRI for the corridor using the published map or table.
TSMO focuses on improved highway operations by improving safety, efficiency, and reliability through the use of technology or improved operational procedures. Examples of TSMO strategies include the following:
- Traffic Management Systems
- Traffic signal timing and coordination
- Transit advantages
- Special event management
- Managed lanes
- Road weather management
Data
Information from in-place ITS devised state-wide is available from MnDOT’s RTMC. Aerial imagery also may show TSMO related infrastructure, such as ramp meters, dynamic signage, cameras at signals, and high-occupancy vehicle lanes. Information on other TSMO strategies or activities should be gathered from MnDOT and local agency staff. MnDOT’s TSMO webpage will have the latest TSMO resources and contact information.
Documentation
Using aerial imagery, input from the MnDOT project team, identify any TSMO strategies or activities in use on the corridor. Existing TSMO strategies and infrastructure can typically be described using a narrative. If there are multiple tools in use along a corridor, or they are implemented at key locations but not others, a map may provide more complete documentation.
The sections below outline how to collect data and perform analyses for each freight and intermodal measurement.
Highway Freight Routes and Tonnage
According to the Minnesota State Freight Plan, nearly two thirds of all freight moved in the state is carried by truck. Trucks play a crucial role in connecting shippers with other transportation modes.
Data
Freight-related maps are available on the “Maps & Data” tab of MnDOT's Freight Webpage. Relevant maps for this topic include the following:
- Oversize/Overweight Superload Corridors
- Twin Trailer Network
- Truck Freight Tonnage
- Weigh Stations in Minnesota
Documentation
Identify any freight-related characteristics of the corridor, as described in the resources above, using a map or table. Relevant information includes inclusion of the corridor in Minnesota Twin Trailer Network, allowed tonnage, and restrictions related to height, width, or safety on Oversize/Overweight (OSOW) Superload Corridors. Also note if truck parking and weigh station facilities are present in the corridor.
Rail Crossings
At-grade rail crossings may impact a highway corridor either directly (the railroad crosses the highway at grade) or indirectly (the railroad crosses an intersecting roadway at grade in proximity to the highway and causes backups on the highway). It is important to understand these characteristics as they can impact safety and mobility along the corridor. Coordinate with the designated MnDOT Railroad Project Manager for the region if any work is planned along railroad corridors or near railroad at-grade crossings. Contacts for the railroad project management staff is available here.
Data
Information on public rail crossings in the state can be accessed using the Minnesota Rail Viewer Application. More detailed information is available as the map is zoomed in. If there are rail crossings present along the corridor, the crossing type icon can be clicked to access information for documentation.
Documentation
Document the following information in narrative, table, or map format:
- Date that you contacted the Railroad Project Manager assigned to your region
- Rail crossing location(s) and type(s)
- Rail route network name
- Information from the USDOT Crossing Inventory Form (including, but not limited to, estimated train movement counts, type and count of tracks, speed of train at crossing, detection and signals, control devices, signs, activated warning devices, illumination, and crossing angle)
- Summary of any incidents included in a USDOT Accident/Incident Report
- Description of characteristics based on aerial imagery or visual references linked in mapping application
Other Freight and Intermodal Characteristics
This measure can capture any additional characteristics for the corridor related to freight and intermodal features such as rail, airport or other transfer stations and ports and waterways, including freight generators, intermodal connectors, intermodal yards, airports, port facilities, and warehouses. (Airports are described in more detail as a subtopic in Section 3.7 Critical Connections: Other Topics.) Intermodal Freight Terminals can be identified using the Intermodal Terminals in Minnesota map on the “Maps & Data” tab of MnDOT's Freight Webpage. If there are truck-rail container intermodal facilities, seaport facilities, airport facilities on or near the corridor, or if the corridor is a key connection to any of these facilities, document them here. Any other relevant freight characteristics such as nearby truck stops or other hubs for freight traffic and parking can be documented here.