Orange barrels on a highway

MnROAD

Minnesota's Cold Weather Road Research Facility

Home | Test Cells | Data & Instrumentation | Projects | Reports | About Us | Contact Us

Current and Past Construction Reports and Research

 

2011 Construction

MnROAD 2011 Reconstruction and Repair of PCC Mainline Cells 5, 6, 63, & 96

Four test cells on the MnROAD Mainline were in need of reconstruction or substantial repairs
in 2011. This opportunity allowed us to enhance the research program at MnROAD by

evaluating and demonstrating the following materials and methods:

 

Also, a thin (5") unbonded concrete overaly using a non- woven geotextile interlayer was
constructed on half a cell, and, repairs were made on a thin whitetopping cell to evaluate
best practices to maintain concrete overlays.

 

Stabilized Full Depth Reclamation on Cell 28

With budgets being stretched and local sources of pavement materials being depleted,

reconstruction of low volume roadways is becoming difficult for local agencies to fund.

Cheaper methods, such as the use of gravel material, have been adopted to try and

alleviate these costs.

 

The construction on Cell 28 explored alternative methods of paving that are both renewable

and relatively inexpensive in overall costs. The plan attempted to utilize in situ materials of

the previous Cell 28 construction to repave the cell in a sustainable manner using 100%

of the existing materials. The cell consisted of 100% recycled pavement that has no

transportation costs, material costs, and relatively inexpensive operating costs providing for

a better quality road. This cell has the potential to serve as a model for maintaining thousands

of low volume road miles.

 

2011 Engineer's Weekly Updates

 

 


 

 

2010 Construction

Sensor Placement

Three new test cells were constructed on the Mainline to investigate the design,

construction, and performance aspects of composite pavements. Construction

began in mid-April and was completed by the end of May.

 

 


 

 

2008 Construction

Reconstruction began in April 2008 and was completed in November. Over 20

test cells were either reconstructed or rehabilitated with asphalt or concrete surfacing.

MnROAD staff installed over 1400 sensors in the various pavement layers during construction.

 

 


 

 

Reconstruction

2007 Construction

MnROAD reconstruction on the Low Volume Road in 2007 included fly ash stabilized

full depth reclamation, polyphosphoric acid modified asphalt, and two new cells to

evaluate the impact of implements of husbandry vehicles on low volume roadways.

 

Two Cells on the mainline were diamond ground with an innovative grind for quiet pavements

 

 


 

2007 Construction

 

2006 Construction

In 2006 Cell 1, 27, and 28 were reconstructed by MnROAD. There were three significant

aspects of research behind the test cell reconstruction: field validation of Geocomposite

Capillary Barrier Drain (GCBD) for limiting moisture changes in pavements, Intelligent

Compaction (IC) research performed on the unbound base and subgrade layers, and

accelerated testing of PG 52-34 binder to support a Local Road Research Board (LRRB)

project. These reports document the previous pavement condition, pavement structural

and mixture designs, instrumentation plan, field construction activities, material sampling,

and laboratory test results.

 

Pervious concrete helps to divert polluted and excess water from local water sources.

In 2006 MnROAD and its partners collaborated on a pervious concrete sidewalk project

to help study how to effectively use pervious concrete to best limit negative environmental

factors.

 

 


 

Pervious Sidewalk Construction

 

2005 Construction

In 2005, MnROAD continued to study the effectiveness of pervious concrete in its test cells.

MnROAD was researching the pervious concrete's inherent sustainability during the varying

environmental factors that come with each season especially safety during the winter seasons.

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 

2004 Construction

2004 marked several different construction and research projects for MnROAD. Cells

60- 63 were constructed using whitetopping technique to replace earlier whitetopping

cells constructed in 1997. The report below contains the relevant information about the

reconstruction and the

data attained through the seven years research.

 

Mesabi Hard Rock aggregate began to be tested during 2004 resulting in several reports

and studies. The purpose of the research was to see the utilization possibility of a new

and Minnesota based resource.

 

Cell 26 was reconstructed to replace a test cell that had failed prematurely.

 

 


 

Culvert Construction

 

2000 Construction

 

Several DOT's from around the US have considered the use of thermoplastic piping to

inlay within pavement. This report describes the development and implementation of

field tests conducted for this project, extends the findings of the field tests, and makes

recommendations for design and installation of thermoplastic pipe under shallow cover

and highway live loads.

 

The purpose of the report below is to document the forensic investigation and to record

observations and conclusions as to the construction, historical performance and subsequent

deterioration of Cell 26

 

This report describes the results for physical characteristics of new PCC test cells 32,

52, and 53.The report also summarizes the results of various material tests performed

during and immediately following the construction of the test cells.

 

 


 

 

1999 Construction

This paper's purpose is to provide an update on the pavement condition of MnROAD's

three low volume road (LVR) SuperPave test cells constructed in 1999 with different

asphalt binders. These cells were built to field validate the current low temperature

performance grading (PG) system currently being used at MnDOT and many other

agencies around the world.

 

 


 

 

1997 Construction

This report presents the results of the research project to investigate the design and

performance of thin and ultra-thin whitetopping.

 

 


 

 

1996 Construction

This report focuses on the second construction phase of the Minnesota Road Research

facility (MnROAD) and evaluates three typical, locally available, surfacing aggregates

along with a rollover section from the initial phase for performance.

 

 


 

 

1990- 1993 Construction

 

These are initial reports released by MnROAD during its original construction.

 

2007 Constructio