DCP Final Checklist

Information and Resources

Final Package to be submitted to Metro State Aid

 

  1. Final DCP Payment request--- See following online guide to requesting final payment: DCP Payment Guide

 

  1. Overrun Form  (If project needs additional federal funds encumbered.) Download form

 

  1. Copy of final voucher (Fully signed by Local Agency and Contractor and must contain language certifying that work was completed in accordance with plans and specifications.
    • Contractor must certify, on a separate page, or under a separate block of text, that they are accepting full and final payment and will make no further claims. If this language is not on the final voucher, a stand alone document needs to be completed and signed by the Contractor. Contractor Certification form Please note--even if the stand alone form is used, the final voucher itself must still contain the signatures of both the Local Agency and the Contractor.

 

  1. Copies of all Change Orders, Work Orders, and Supplemental Agreements

 

  • It is helpful if these are approved for funding by Metro State Aid in advance of submitting your final package.

 

  1. Overrun/Underrun Report--Used to report major overrun/underrun of contract quantities Download sample

 

  1. Materials Exception Summary Download form Forms located under "Project Certification"

 

Please attach the following:

  • List of Testers---include name, Mn/DOT Certification #, type of tests performed Download form
  • Memo from Mn/DOT Bituminous Office listing any exceptions on file, or stating there are no exceptions. Download form
  • Memo from Mn/DOT Concrete Office listing any exceptions on file, or stating there are no exceptions. Download form
  • Copies of documents showing reductions to unit price and/or penalties
  • If Mn/DOT did not provide Quality Assurance on the project, please provide documentation showing Quality Assurance was completed by others.
  • Other documentation that affects exceptions noted on your form.

For projects with no materials, send in anyway and write “NA” on it. 

 Materials Information Packet

 7.Final Inspection Report (signed by Mn/DOT engineer and project engineer and showing any problems as resolved) If project has not been inspected, call Jim Deeny at 651-234-7762 to schedule a final inspection. Download Form 

 

8.  Cost Distribution Spreadsheet  This spreadsheet needs to show all contract items by cost group and must match the the total shown for each group on the Final DCP payment submittal.

 

9.      State Aid Payment Request (if requesting state aid funds for local match or other state aid eligible costs.) Download form - ( Choose Payment Request Form under "General Forms)

 

10.      Backsheet Item Costs (if final voucher shows any costs for extra items not supported by a contract change document, supporting documentation is needed.) Examples include the following:

  • Worksheets showing calculations for Fuel Escalation costs.
  • Worksheets showing calculations for Bituminous Incentive/Disincentives.
  • Items added and paid for by Special Provisions—such as additional traffic control. Include a copy of the page from your Special Provisions or cite the MnDOT Spec Book entry that applies
  • Other—include an explanation of why the item was added as a backsheet.  

 

 

 

DCP Final Checklist

Final documentation for federal aid projects should be submitted when the final payment voucher is accepted by the contractor.

List of items on the left shows the required documentation to be sent to Metro State Aid. It can be sent in as one unit, or piecemeal.

We prefer to review and approve contract change documents before final payment is made to contractor.

Final inspection should be ordered towards the end of the project when the contractor is still on site.

Materials Exception Summary needs to be submitted after the end of the project, but ideally before final payment is made to the contractor.

Full list of other required documentation to finalize project sent to other offices and/or retained for your files:

http://www.dot.state.mn.us/stateaid/projectdelivery/pdp/dcp/dcp-checklist.pdf