Traffic impacts

Hwy 97 in Forest Lake project location map.
All traffic impacts are tentative and weather dependent.
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
Road closures
5 a.m. Mon, June 2 through fall 2025
- Hwy 97 both directions from Hornsby Ave. to Falcon Ave. is closed
- Eastbound detour: Northbound I-35 to eastbound Hwy 8 to southbound Hwy 61
- Westbound detour: Northbound Hwy 61 to westbound Hwy 8 to southbound I-35
- Southbound I-35 to eastbound Hwy 97 detour: Southbound I-35 to Broadway Ave. to northbound I-35 to eastbound Hwy 8 to southbound Hwy 61
Project visualization
Check out a video visualization of what the finished project area is anticipated to look like.
About this project
Starting in June 2025, Hwy 97 will be reconstructed between I-35 and Hwy 61 to improve traffic flow and safety. Turn lanes will be added at specific intersections along the highway and a single-lane roundabout at Fenway Avenue also will be constructed. A raised median will be added to divide east and westbound traffic on the two-lane roadway. The median will also serve as an accessible pedestrian crossing. A new multi-use trail will be constructed along the south side of Hwy 97 to provide a safer space for pedestrians and bicyclists, as well as a connection to the Hardwood Creek Regional Trail.
Summary of work
- Reconstruct roadway and add raised medians
- Add turnlanes at specific intersections
- Build a single-lane roundabout
- Construct multi-use trail
- Upgrade pedestrian accessibility
- Repair/replace drainage
Project timeline
Consstruction will be done in two stages, with one half of the road under construction each year.
- Stage 1 (2025): Hornsby St. to Falcon Ave. Construction Monday, June 2 to late fall
- Stage 2 (2026): Falcon Ave. to Forest Rd.