National Highway System pavement projects

MnDOT District 8

Scoring criteria for national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on network designation, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What's been selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2021

Total Score Route Description  High Level Cost Estimate for Planning Purposes  Year Planned (FY) Comments
83 US71 Rural reconstruction from Highway 23 to Willmar Bypass and additional locations on Highway 71  $25,000,000 2028
79 MN23 Medium mill and overlay from Highway 75 (Pipestone) to north of Highway 91 (Russel)  $13,400,000 2024
79 US71 Reclaim and overlay from Redwood County Road 115 (Sanborn) to Highway 68  $8,800,000 2027
78 MN23 Major concrete rehabilitation from north of Highway 91 (Russel) to Highway 19 (Marshall)  $20,400,000 2029
77 US71 Major CPR and diamond grinding from US212 to MN7  $4,800,000 Not selected Project not selected due to the previous fix being a minor CPR in 2018; it is expected that the average life of those repair are approx. 15 years. This project will be reconsidered approx. 2033
77 US212 Major concrete rehabilitation from Highway 23 (Granite Falls) to east of Highway 23  $8,600,000 Not Selected The district is currently prioritizing other concrete segments that have not yet received a rehabilitation
75 MN15 Thin mill and overlay from Highway 212 (Brownton) to Hutchinson  $3,200,000 Not Selected Candidate for Preventative Maintenance work in 2024
75 US14 Medium overlay and cold in inplace recycling from Lake Benton to Lincoln/Lyon County Line  $5,200,000 2027
75 US12 Major concrete pavement rehabilitation from Darwin to Cokato  $10,700,000 2024
75 US212 Medium overlay from Renville County road 16 to Renville County Road 7  $3,700,000 2030
74 US71 Major CPR and diamond grinding from  Cottonwood/Redwood County line to 120th St   $900,000 Not selected Project not selected due to short length (2 miles); this pavement section continues south into District 7. This project will be selected when District 7 schedules a project.
73 MN7 and MN22 Major concrete rehabilitation on Highway 7 from Hutchinson to Silver Lake, and on Highway 22 from McLeod County road 25 to  Highway 7 (Hutchinson Bypass)  $6,200,000 2027
73 MN19 and US71 Major rehabilitation on MN19 from Qualit Dr to Centennial Dr and on US71 from Hwy 19 to Renville County Road 19  $3,000,000 2031
72 US59 Cold in place recycling and medium overlay from Highway 14 to Lyon County Road 6 (Marshall)  $5,800,000 2028
71 MN15 Medium overlay from Hutchinson to Highway 12 (Dassel)  $6,400,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
71 US71 Reclaim and overlay from Highway 68 to Redwood Falls  $6,800,000 2029
71 US12 Medium overlay from Kerkhoven to Pennock  $3,800,000 Not Selected Candidate for preventive maintenance work in 2025
70 MN15 Reclaim and overlay from Highway 12 (Dassel) to Meeker/Stearns County Line  $8,400,000 2023 This section has been prioritized because maintenance patching is losing effectiveness.
70 US14 Medium mill and overlay from Highway 23 to Tracy  $9,400,000 2028
70 MN23 Thin mill and overlay Highway 19 (Marshall) to Lyon County Road 33  $1,200,000 2028 This section has been prioritized because a thin mill and overlay will improve performance.
69 US59 Medium overlay Highway 30 (Slayton) to north junction of Highway 30  $3,000,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
69 US212 Minor concrete pavement rehab and diamond grinding from Olivia to Bird Island  $1,000,000 Not Selected District anticipates pavement conditions will not deteriorate as fast as the model predicts
68 US14 Thin mill and overlay from South Dakota/Minnesota State line to US75  $1,400,000 2029  
67 MN23 Medium mill and overlay from Rock/Pipestone County Line (Jasper) to HIghway30 (Pipestone)   $5,700,000 Not Selected
67 US71 Medium mill and overlay from Highway 19 (Morton) to Olivia  $7,500,000 Not Selected
65 US14 Medium overlay and cold in place recycling from Revere to Redwood/Brown County Line  $6,300,000 Not Selected
64 MN7 Reclaim and overlay from Highway 40 (Milan) to Montevideo  $11,100,000 Not Selected
58 MN15 Reclaim and overlay from MN19 to US212  $4,600,000 Not selected  
56 US71 Concrete reconstruction from Highway 23 to Willmar Bypass  $7,900,000 Not Selected
53 US59 Reconstruction from Highway 68 (Marshall) to Lyon County Road 33  $8,900,000 Not Selected
48 US71 Cold in place recycling and medium overlay from MN7 to MN23  $2,500,000 Not selected  
46 US212 Minor CPR and diamond grinding from MN22 to Morningside Dr  $1,400,000 Not selected  
45 US212 Unbonded overlay from Morningside Dr to MN5  $12,400,000 Not selected  
44 US212 Minor CPR and diamond grinding from US75 to .5 miles west of MN29 (excluding Dawson)  $3,400,000 Not selected  
43 MN22 Cold in place recycling and medium overlay from Cedar Ave to McLeod County Road 115  $2,600,000 Not selected  
40 MN22 Concrete reconstruction from Glencoe to Hutchinson  $50,600,000 Not Selected
40 US12 Thin overlay from Highway 22 to Highway 24 (Litchfield)  $200,000 Not Selected
39 US12 Concrete reconstruction from Highway 71 to Kandiyohi/Meeker County Line  $58,300,000 Not Selected
37 MN15 Thin overlay from Meeker County Road 18 to south of US12  $200,000 Not selected  
37 US71 Thin overlay from Kandiyohi County Road 93 to MN23  $100,000 Not selected  
37 US59 Thin overlay from Nobles/Murray County Line to Highway 62 (Fulda)  $400,000 Not Selected
36 US71 Thin overlay from Quality Drive (Redwood Falls) to Highway 71 and additional locations on Highway 71  $1,300,000 Not Selected
36 US12 Thin mill and overlay from 25th St. SE (Willmar) to Highway 71  $400,000 Not Selected
35 MN7 Thin overlay from the end of bridge 8518 to Carver County Road 33  $100,000 Not selected  
33 MN23 Major CPR and diamond grinding from .1 mile south of MN7 to .3 miles north of MN7  $200,000 Not selected  
31 US14 Thin overlay from Redwood  County Road 7 to Main St   $100,000 Not selected  
30 US59 Thin overlay from .6 miles south of MN62 to MN62  $100,000 Not selected  
20 US212 Thin overlay eastbound from west of Highway 5 to Highway 5  $100,000 Not Selected
12 US59 Thin overlay from Murray County Road 6 to 1st St  $100,000 Not selected  
8 MN15 Minot CPR and diamond grinding from north of High Dr/County Road 15 to north of High Drive  $100,000 Not selected  
8 MN7 Thin mill and overlay on Highway 7 & Highway 25 Roundabout  $100,000 Not Selected
8 US71 Thin overlay on Highway 71 & Highway 7 Roundabout  $100,000 Not Selected
7 MN15 Thin overlay on Highway 19 (Winthrop) to north of Highway 19  $100,000 Not Selected
6 MN7 Thin overlay from Swift Chippewa County Line to MN40  $500,000 Not selected  
6 MN7 Minor concrete pavement rehab and diamond grinding at the intersection of Highway 23 & Highway 7 (Clara City) - approx. 1000 feet on each leg  $300,000 Not Selected