Increasing the transparency of how we select highway construction projects

Urban non-freeway/non-expressway pavement projects

MnDOT District 8

Scoring criteria for urban non-freeway, non-expressway pavement projects. Out of 100 possible points, 25 points are based on the timing of the improvement, 25 points are based on cracking, rutting and patching, 10 points are based on traffic volume, 10 points are based on compliance with the Americans with Disability Act, 10 points are based on active transportation and transit, 10 points are based on other infrastructure needs, 5 points are based on the condition of local utilities under the road, and 5 points are based on whether the project will benefit an environmental justice population.

Learn more about how MnDOT evaluates and selects urban pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. MnDOT scores and prioritizes urban non-freeway/non-expressway pavement projects separately from the normal pavement scoring process, because of their complexity, utilities and other infrastructure and level of required local coordination and public involvement. In many instances, these roads function both as state highways and as city streets. These pavement projects can be on either National Highway System or non-NHS.

Freeways have full access control (no driveways, signals or at-grade intersections). Expressways have partial access control (limited or no driveways, few and widely spaced intersections, and may include some grade separated crossings). Both are high speed roads designed to facilitate longer trips.

For the purposes of this scoring category, MnDOT uses a flexible, context-based definition of urban. This includes areas with medium-to-high density adjacent development with small to medium setbacks, and in some instances no setback. This includes both residential, industrial and commercial areas. In some instances, the urban context may cover less than a quarter mile.

Urban pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What’s been selected?

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2020

Total Score Community Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
88 Litchfield US12 Medium mill and overlay Highway 22 to Meeker County Road 34 (Litchfield) $700,000 2023  
84 Marshall MN19 Concrete reconstruction from 2nd St. to Minnesota St. (Marshall) $5,700,000 2025  
84 Willmar US12 Medium mill and overlay from 11th St. W. to 6th St. E. (Willmar) $2,000,000 2027  
79 Marshall US59 Reconstruction from Highway 23 to the  junction of Highway 68/Highway 19 (Marshall) $7,800,000 Not selected A nearby section of roadway is programmed for reconstruction. Waiting to avoid multiple years of detours.
76 Marshall MN19 Concrete reconstruction from Minnesota St. to Highway 23 (Marshall) $13,600,000 Not selected A nearby section of roadway is programmed for reconstruction. Waiting to avoid multiple years of detours.
75 Marshall MN19 Concrete reconstruction from Lyon County Road 7 to 2nd St. (Marshall) $8,000,000 Not selected A nearby section of roadway is programmed for reconstruction. Waiting to avoid multiple years of detours.
73 Pipestone US75 Reconstruction from Highway 30 to 4th St N (Pipestone) $4,500,000 Not selected This segment was rehabilitated in 2018
73 Glencoe MN22 Medium mill and overlay from Highway 212 to Cedar Ave (Glencoe) $600,000 2023  
72 Pipestone MN30 Reconstruction from 4th Ave. W. to Highway 75 (Pipestone) $11,400,000 Not selected This segment was rehabilitated in 2017
71 Clara City MN23 Medium mill and overlay Highway 7 to Bridge number 12012 (Clara City) $400,000 Not selected This segment was rehabilitated in 2017
69 Morton MN19 Reconstruction from Centennial Dr. to Brook Dr. (Morton) $1,900,000 Not selected This segment was rehabilitated in 2016
69 Canby US75 Reconstruction  from near St Olaf Ave S to Yellow Medicine County Road 3 (Canby) $8,700,000 Not selected This segment was rehabilitated in 2016
69 Olivia US212 Reconstruction from the west junction of Highway 71/320th sty to the East junction of Highway 71/13th St (Olivia) $11,200,000 Not selected This segment was rehabilitated in 2014
66 Ivanhoe MN19 Medium mill and overlay from Rebecca St. to Lincoln County Road 5 (Ivanhoe) $300,000 2029 Coordinated with a NHS pavement project 
66 New London MN9 Thick mill and overlay from Highway 23 to 1st Ave SE (New London) $700,000 Not selected  
66 Hutchinson MN15 Reconstruction from 5th Ave to High Drive in Hutchinson $1,300,000 Not selected  
66 Montevideo US212 Medium mill and overlay from Yellow Medicine/Chippewa County Line to Hwy 29 in Montevideo $200,000 Not selected  
65 Renville US212 Reconstruction from Renville County Road 6 to 5th St E (Renville) $6,500,000 Not selected  
65 Clarkfield MN67 Reconstruction Highway 59 to 6th St. (Clarkfield) $2,700,000 2024 Selected prior to policy (In 2019-2028 CHIP)
64 Litchfield US12 Resurfacing from Hwy 24 to 4th St in Litchfield $500,000 Not selected  
63 Litchfield MN22 Concrete reconstruction from Pleasure Dr. to Highway 12 (Litchfield) $5,200,000 Not selected  
63 Madison US75 Medium mill and overlay from Highway 40 to 8th St and Highway 40 from Highway 75 to Western Ave (Madison) $2,000,000 2023 This section has been prioritized because the pavement will be 17 years old
63 Lake Benton US14 Reconstruction from South Valley St to Highway 14 and from near the Railroad tracks to Jesse St  $5,500,000 2027 The District has been coordinating with the City to replace their utilities. 
62 Tracy US14 Medium mill and overlay from Lyon County Road 28 to 4th St. E. (Tracy) $700,000 2028 Coordinated with a Non-NHS pavement project
62 Grove City US 12 Reconstruction from west junction Hwy 4 to east junction Hwy 4 Grove City $1,400,000 Not selected  
62 Danube US212 Reconstruction from Freedom St to 2nd St in Danube $2,600,000 Not selected  
61 Redwood Falls US71 Reconstruction from 11th St to Quality Dr $11,000,000 Not selected  
61 Granite Falls US212 Reconstruction from 17th St to Hwy 23 in Granite Falls $3,700,000 Not selected  
60 Montevideo MN7 Thin mill and overlay from Highway 29 to 28th St $1,000,000 2026 Due to a rapid drop in pavement quality, the district is planning a thin mill and overlay in 2026 to extend the current lifespan of this segment.
59 Fairfax MN19 Reconstruction from 1st St to Highway 4 (Fairfax) $4,000,000 Not selected  
57 Dawson US212 Reconstruction from Highway 119 to Lac qui Parle County 39 (Dawson) $7,700,000 Not selected  
55 Redwood Falls MN67 Reconstruction on Highway 71 to Veda Dr. (Redwood Falls) $7,700,000 Not selected  
53 Hutchinson MN15 Thin mill and overlay from 5th Ave. to McLeod County Road 15 (Hutchinson) $200,000 Not selected  
46 Hutchinson MN7 Major concrete pavement rehab and diamond grinding Buff St. to Technology Dr. (Hutchinson) $1,300,000 Not selected  
38 Hendricks MN271 Thin mill and overlay from Railroad St. to Henderson St. (Hendricks) $200,000 Not selected  
37 Walnut Grove US14 Reconstruction from 8th St to 6th St in Walnut Grove $3,700,000 Not selected  
35 Olivia US212 Resurfacing from Hwy [@Description]71 to Renville County Road 14 in Olivia $200,000 Not selected  
28 Redwood Falls MN19 Resurfacing from Minnesota St to Sunrise Blvd in Redwood falls $400,000 Not selected  
28 Bird Island  US212 Resurfacing from 10th St to 1st St in Bird Island  $200,000 Not selected  
25 Eden Valley MN22 Thin mill and overlay Highway 55 to Meeker/Stearns County Line (Eden Valley) $100,000 Not selected  
21 Marshall MN68 Resurfacing from Hwy 59 to Hwy 19 in Marshall $200,000 Not selected  
20 Iona MN267 Thin mill and overlay from Murray County Road 4 to Ireland Ave. (Iona) $100,000 Not selected  
16 Cosmos MN4 Thin mill and overlay from Southern Cross Ave. to Northern Cross Ave. (Cosmos) $400,000 Not selected  
16 Eden Valley MN22 Thin mill and overlay from Hwy 55 to Meeker/Stearns County Line in Eden Valley $100,000 Not selected  