Traffic impacts

I-494 between East Bush Lake Road in Edina and 12th Avenue North in Richfield project location map

I-494 Edina to Richfield project location map.

View full-size map

All traffic impacts are tentative and weather dependent. Local access to all businesses and residences will be maintained throughout construction. The Knox Ave. Park and Ride lot is permanently closed.

Current

Lane closures

7 p.m. Mon, March 4 through 6 a.m. Fri, March 8, 7 p.m. through 6 a.m. nightly
  • NB I-35W is reduced to one lane between 90th St. and 76th St.
  • SB I-35W is reduced to one lane between 66th St. and I-494

Ramp closures

8 p.m. Mon, March 4 through 5 a.m. Tue, March 5
  • The ramp from WB I-494 to SB I-35W is closed
8:30 p.m. Mon, March 4 through 5 a.m. Fri, March 8; 8:30 p.m. to 5 a.m. nightly
  • The ramp from 82nd St. to NB I-35W is closed

Upcoming

Information about upcoming traffic impacts will be posted as details become available. Motorists can expect several weekend, nighttime, and directional closures along I-494 and I-35W. Ramps and loops will be closed at various times for construction. There will also be lane and road closures on local roadways near I-494.

Road closures

5 a.m. Mon, March 18
  • Permanent closure of 78th St. north of I-494 between Portland Ave. and Chicago Ave.
  • Permanent closure of Clover Dr. between 80th ½ St. and Dupont Ave.
Early April through late summer
  • American Blvd. is closed to through traffic in both directions between Hwy 100 and France Ave.
Early April through late May
  • 78th St./Girard Ave. is closed in both directions beginning just before the Shops at Lyndale

Ramp closures

10 p.m. Thu, March 7 through 5 a.m. Thu, March 8
  • The ramp from EB I-494 to NB I-35W is closed
10 p.m. Sun, March 17 through mid-April

About this project

We are constructing E-ZPass lanes on I-494 from Hwy 100 to I-35W in each direction and adding a new ramp at the I-35W and I-494 interchange. We are also replacing the bridges crossing over I-494 at Portland Ave., Nicollet Ave., and 12th Ave., and adding a new pedestrian bridge at Chicago Ave. that crosses over I-494 to provide an additional pedestrian and bicycle connection across I-494.

When work is completed, the E-ZPass lanes and the new ramp at the I-35W and I-494 interchange will address congestion on the interstate. The new bridges at Portland, Nicollet, and 12th Ave. will accommodate future traffic levels, provide wider, accessible sidewalks, new bike lanes, and upgrades to some transit stations. We will be removing access to I-494 from Nicollet Ave. and 12th Ave., but will provide full access to I-494 from Portland Ave.

This is the first of four construction projects that are part of the I-494: Airport to Hwy 169 vision.

Summary of work

  • Add EZ-Pass lane on I-494 in both directions from Hwy 100 to I-35W
  • Modify interchanges along I-494 at Penn Ave., I-35W, Nicollet Ave., Portland Ave., and 12th Ave. and at I-35W/82nd St.
  • Reconstruct and repair pavement on I-494 and local roads
  • Reconfigure I-35W/I-494 interchange
  • Replace bridges at Nicollet Ave., Portland Ave., 12th Ave., and I-494 over I-35W
  • Repair bridges at France Ave. and Penn Ave.
  • Construct new pedestrian bridge near Chicago Ave. over I-494
  • Construct noise and retaining walls
  • Relocate or adjust multiple public and private utilities
  • Connect walking path and concrete bike path along Portland Ave.
  • Replace lighting, signage, and dynamic message boards
  • Improve ramps, sidewalks, and signals at multiple intersections