About this project
Summary of MnDOT work

- MnDOT is reconstructing Highway 19/College Drive from 700 ft west of Marlene St through the intersection of Bruce Street in the City of Marshall.
- The City of Marshall is replacing sanitary sewer and water main utilities.
- A single-lane roundabout will be constructed at the intersection of Highway 19/College Drive, Country Club Drive, and South 2nd Street.
- An EV Charging Station will be installed in the Avera parking lot.
- Sidewalk improvements will be made along the project area to improve accessibility.
- Several traffic control changes throughout the route will be made to enhance safety.
- A bike lane will be striped from Marlene St. to just west of Fairgrounds Rd.
- Trees will be replanted in the fall of 2026(PDF). Tree selections can be viewed here(PDF), please note, these are subject to change.
Project update: June 25, 2026
Work zone: Main Street to Liberty Park Bridge
- Concrete paving is complete at the Redwood Street crossing.
- ADA components continue to be poured at the intersections.
- Concrete sidewalk installation continues.
- Landscape work is scheduled to begin.
Work zone: Main Street / East College Drive intersection (Highways 19, 59 and 68)
- This intersection will be opening Friday, June 26. Crews will be on site early to start the process. Please continue to look for workers in this area as they remove the detour signage.
- Permanent pavement markings (crosswalks, turn arrows, etc.) have been installed.
- Concrete paving is complete.
- Bituminous paving is complete.
- Signal system installation is nearly complete.
Work zone: Bruce Street / Highway 19 intersection
- Water main installation is nearly complete.
- Grading of the roadway is complete.
- Storm sewer installation is complete.
- Surveying for curb and gutter placement and the signal system underground work has been completed.
Work zone: Legion Field Bridge to Main Street
- Crews worked on boulevard maintenance.
Work planned for next week
All work is weather-permitting
Main Street to Liberty Park Bridge
- Landscaping work will continue.
- ADA component installation continues at intersections.
- Concrete sidewalk installation continues.
- Streetlight support poles are scheduled to begin installation.
Bruce Street/ Highway 19 intersection
- Concrete curb and gutter installation will begin.
- Concrete paving will begin.
- Work will start on the signal system underground work.
- Watermain installation is scheduled for completion.
Legion Field Bridge to Main Street on Highway 19 (Year 1 project area)
- Maintenance work will continue.
Liberty Park Bridge to Bruce Street on Highway 19
- High Street to Hill Street is the active zone.
- Sanitary sewer work will be completed.
- Watermain installation will begin.
- Liberty Park Bridge to Bruce Street
- North 3rd Street to Park Avenue is open.
- High Street to Hill Street at Highway 19 is closed.
- Hill Street crossing is open.
- Minnesota Street is open at Highway 19 to access local businesses.
- The Bruce Street / East College Drive intersection is closed.
- Main Street to Liberty Park Bridge on Highway 19 is closed.
- Traffic must use the detour on Lyon County Road 7 and Highway 23.
- West Lyon Street is open at Highway 19.
- Alleys between West Lyon Street and West Redwood Street, and between West Redwood Street and West Marshall Street are closed at Highway 19.
- West Redwood Street and West Marshall Street are closed to through traffic at Highway 19.
- Highway 19 is open to local traffic at Minnesota Street.
- Businesses within the work zone remain open.
- Addison public parking lot is open.
- Please watch for pedestrians.
Traffic access and impacts
2025: Stages 1-4
2026: Stages 5-7


