MnDOT District 8

Scoring criteria for non-national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on the potential to transfer jurisdiction of the road to a city or county, and 5 points are based on the miles covered by the project.

Learn more about how MnDOT evaluates and selects pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What's been selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2021

Total Score Route Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
85 MN4 Reclaim and overlay from Highway 19 (Fairfax) to Highway 12 (Hector)  $9,200,000 2026
85 MN68 Reclaim and overlay from Canby to Minneota  $13,000,000 2031
83 MN24 Medium overlay Highway 12 (Litchfield) to Highway 15  $8,800,000 Not Selected This section has not been selected because it is a thin whitetopping test section (4-inch bonded concrete overlay in 2015). District will continue to monitor performance for research purposes.
81 MN30 Thin mill and overlay from Minnesota / South Dakota State Line to 8th Ave (Pipestone)  $1,200,000 2029  
81 US75 Cold in place recycling and medium overlay from Yellow Medicine County Road 3 (Canby) to 0.4 mi. S. of US 212  $4,000,000 Not selected Project was not selected due to fiscal constraints in 2030 (no new non-NHS projects were added in FY 2030)
81 US75 Medium overlay from Murray County Road 3 to Hwy212  $4,000,000 Not Selected Not a district priority. Will continue to monitor pavement performance. 
80 MN271 Reclaim and overlay from Highway 19 to Minnesota/South Dakota State Line  $4,900,000 2022
80 US75 Medium overlay from Pipestone Creek to Lake Benton  $5,400,000 2028
78 MN30 Reclaim and overlay from  US 59 to Murray/Cottonwood Co. Line  $4,900,000 2026  
78 MN40 Medium mill and overlay from Highway 59 (Milan) to Highway 29  $4,000,000 2026
78 MN22 Medium overlay from Hutchinson to Highway 7  $3,300,000 Not Selected Candidate for reconstruction in 2034
75 US59 Reclaim and overlay from 15th Ave. (Clarkfield) to US 212  $3,800,000 Not selected  
75 MN22 Thin overlay from US 12 to Fredericks Ave. (Eden Valley)  $1,100,000 2027  
75 MN19 Reclaim and overlay from Ivanhoe to Lincoln County Road 5  $13,900,000 2030
75 US59 Reclaim and overlay from 15th Ave to west junction of Hwy212  $3,800,000 Not Selected  
74 MN68 Reclaim and overlay from US 71 to 0.2 mi. W. of MN 67 (Morgan)  $3,900,000 Not selected  
74 MN68 Reclaim and overlay from Hwy71 to Hwy 57 in Morgan   $3,900,000 Not Selected  
74 MN40 Reclaim and overlay Old Highway 277 to Kandiyohi County Road 5 (Willmar)  $12,700,000 2029
74 MN55 Medium overlay from Stearns/Meeker County Line to Eden Valley  $3,000,000 Not Selected Candidate for preventive maintenance in 2024
73 MN30 Cold in place recycling and medium overlay from US 75 to Ravine St. (Lake Wilson)  $4,300,000 Not selected  
73 MN30 Medium overlay from Hwy75 to Ravine St in Lake Wilson  $4,300,000 Not Selected  
71 MN67 Thin mill and overlay from MN 23 to Upper Sioux Agency State Park  $1,000,000 2028 Project was selected because a thin mill & overlay is a low cost treatment with a large performance benefit for this segment (as indicated by low levels of cracking)
71 MN119 Medium mill and overlay from Highway 212 (Dawson) to Highway 40  $2,700,000 Not Selected Candidate for preventive maintenance in 2021
69 MN4 Reclaim and overlay from Hector to Cosmos  $10,100,000 Not Selected Candidate for preventive maintenance in 2021
67 MN68 Thin mill and overlay from from CR 6 (Wabasso) to US 71   $1,100,000 2029 Project was selected because a thin mill & overlay is a low cost treatment with a large performance benefit for this segment (as indicated by low levels of cracking)
67 MN68 Thin mill and overlay from Redwood County Road 6 in Wabasso to south junction with Hwy71  $1,100,000 2029 Project was selected because a thin mill & overlay is a low cost treatment with a large performance benefit for this segment (as indicated by low levels of cracking)
65 MN40 Medium mill from Highway 119 to Highway 59 (Milan)  $3,600,000 2025 Coordinated with other projects
65 MN68 Reclaim and overlay from Redwood County Road 3 (Morgan) to Redwood/Brown County Line  $3,100,000 Not Selected Candidate for reconstruction in 2030
65 MN7 Reclaim and overlay Highway 71 to Highway 4 (Cosmos)  $13,000,000 Not Selected
65 MN7 Reclaim and overlay from Highway 4 (Cosmos) to Highway 22  $7,400,000 Not Selected Candidate for preventive maintenance in 2025
64 MN4 Reclaim and overlay from Cosmos to  Meeker County Road 23  $5,400,000 2022 This section has been prioritized due to maintenance patching losing effectiveness because of the level of deterioration. 
64 MN267 Reclaim and overlay from Iona to Highway 30  $4,000,000 Not Selected
63 MN68 Reclaim and overlay from South Dakota/Minnesota State Line to Canby  $6,400,000 Not Selected
62 MN29 Reclaim and overlay from Airport Ave (Montevideo) to MN 40  $3,700,000 Not selected  
62 MN29 Medium mill and overlay from west junction of Highway 40 to east junction Highway 40 and additional locations on Highway 40  $5,200,000 2024 Coordinated with projects on Highway 40
62 MN67 Reclaim and overlay from Redwood Falls to Fergus Ave. (Morgan)  $8,600,000 Not Selected
62 MN29 Reclaim and overlay from Airport Trail to Hwy 40  $3,700,000 Not Selected  
61 MN274 Reclaim and overlay from Wood Lake to Highway 23  $6,500,000 Not Selected
59 MN67 Reclaim and overlay from Travers Ln. to Highway 19  $12,300,000 Not Selected
58 MN67 Reclaim and overlay from US 75 to US 59 (Clarkfield)  $7,200,000 Not selected  
58 MN68 Reclaim and overlay Highway 71 to Redwood County Road 3 (Morgan)  $7,700,000 Not Selected
58 MN67 Reclaim and overlay from Hwy 75 to Hwy59 near Clarkfield  $7,200,000 Not Selected  
54 US59 Reclaim and overlay from Yellow Medicine County Road 3 to Clarkfield  $4,100,000 Not Selected
42 MN22 Thin overlay from 0.1 mi. E. of MN 7 to 0.2 mi. W. of MN 7  $100,000 Not selected  
42 MN22 Thin overlay from .1 miles east of Hwy 7 to .2 miles west of Hwy 7  $100,000 Not Selected  
40 MN67 Thin mill and overlay Highway 23 (Granite Falls) to Travers Ln.   $2,100,000 Not Selected
39 MN269 Thin overlay from South Dakota/Minnesota State Line to Highway 23 (Jasper)  $600,000 Not Selected
37 MN9 Thin overlay from Kandiyohi County Road 7 (Sunberg) to Kandiyohi / Swift Co. Line  $100,000 Not selected  
37 MN9 Thin overlay from Kandiyohi County Road 7 to Kandiyohi/Swift County line  $100,000 Not Selected  
36 US75 Thin overlay from 4th St. N. (Pipestone) to Pipestone County Road 22  $100,000 Not Selected
32 MN29 Thin overlay from MN 40 to Chippewa / Swift Co. Line  $400,000 Not selected  
32 MN29 Thin overlay from Hwy 40 to Chippewa/Swift County Line  $400,000 Not Selected  
31 MN68 Thin overlay on from Highway 19 to Redwood County Road 32 (Milroy)  $700,000 Not Selected
29 MN19 Thin overlay from Reference point 3 to Reference point 4  $200,000 Not selected  
29 MN19 Thin overlay from Reference pt 003 to Reference pt 004  $200,000 Not Selected  
6 MN22 Thin overlay from Sibley / McLeod Co. Line to US 212  $200,000 Not selected  
6 MN330 Thin overlay from Highway 14 to University of Minnesota SW Research and Outreach Center  $500,000 Not Selected
6 MN22 Thin overlay from Sibley/McLeod County line to Hwy212  $200,000 Not Selected  
3 MN104 Thin mill and overlay Highway 9 to Kandiyohi/Pope County Line  $1,400,000 Not Selected