Hwy 52 Southbound Improvements

Zumbrota to Cannon Falls

Construction schedule

Some of the items may move in time periods or change as design work continues.

2021

  • Constructed various Hwy 52 median crossover lanes to direct traffic off or onto the northbound or southbound lanes during future construction work.
  • Constructed Hwy 60 West overpass bridge replacement at Zumbrota.
  • Replaced northbound Hwy 52 bridge at Hwy 60 east interchange south of Zumbrota.

2022 (Construction started April 21)

  • Rebuild Hwy 52 southbound from (4,000 feet north) Goodhue Co. Rd. 9 to Goodhue Co. Rd. 50.
  • Build a new interchange at the intersection of Hwy 57/Goodhue Co. Rd. 8 and Hwy 52.
  • Replace the southbound bridge over Hwy 52 for Hwy 60 East.
  • Build Goodhue Co. Rd. 14 connection, frontage roads and cul de sacs.

2023

  • Replace the Hwy 52 southbound bridge over the Zumbro River.
  • Repair the Hwy 52 northbound bridge over the Zumbro River.
  • Reconstruct Hwy 52 southbound from Goodhue Co. Rd. 24 in Cannon Falls to (4,000 feet) north of Co. Rd. 9.
  • Reconstruct Hwy 52 southbound from Co. Rd. 50 to 1.3 miles north of Goodhue Co. Rd. 7.
  • Construct frontage roads and cul de sacs.
  • Construct noise wall along northbound Hwy 52 south of Hwy 58 interchange at Zumbrota.