Minnesota Department of Transportation

511 Travel Info

Bridges and Structures

Design, construction and maintenance resources

Do It Right! Lessons from the field not to be repeated

Rehab work

Rehab work
  • Don’t allow the contractor to use over 60 pound jackhammers when removing the deck over the beams — or the beams may get damaged!
Rehab work
  • These concrete beams were supposed to be left in place, and a new deck poured on top of them.
  • The contractor thought they could just repair them with the deck pour.
  • We had to make the contractor provide new beams, so a large delay was incurred.
Rehab work

Haste makes waste

  • These beams were supposed to be reused after the deck was removed. There is no way to repair this much damage to prestressed concrete beams.
Rehab work
  • The DNR would rather we don’t attempt to neutralize the effects of acid rain with the liberal application of concrete dust!
Rehab work
  • We now require the concrete saws to have a stream of water be directed at the area being cut, and the milling to be performed in such a manner as to prevent visible dust to be liberated.
Rehab work
  • Try not to remove more concrete than is shown in the plan.
  • Quite a bit of sound concrete was removed and a lot of rebar was damaged because of the speed at which this joint was removed.
Rehab work
  • Remove only what was called to be removed in the Plans.
  • In this case, the barrier dowels were cut off to make it easier to replace the Expansion joint.
  • What will hold the barrier on the deck now?
Rehab work
  • Try to remove only what is shown in the plans, as long as the in-place concrete is sound.
  • Don’t cut epoxy coated reinforcement with a torch!
  • All damage to portions of the structure to remain in place that is due to the contractor's operations shall be repaired at the contractor’s expense.
Rehab work
  • What happens if the barrier takes a hit at this location now?
Rehab work
  • Try to prevent damage to sound concrete when performing repairs!
  • Sure, maybe they saved some time removing the expansion joint with a backhoe-mounted hammer . . . but how much time will they need to spend repairing the damage?
  • And how much damage will not get repaired?
Rehab work

Shotcrete Repairs

  • Shotcrete is thirsty! Make sure that all repairs area are cleaned and saturated 24 hours prior to shotcreting, and re‐wetted prior to shooting.
  • And . . . make sure that it gets a full three-day wet cure.
Rehab work
  • Form new top flange monolithically with new expansion joint.
  • This repair does not meet the criteria for beam repair, as only spalls less than 3 inches deep are permitted to be poured with the deck. Obtain Bridge Office approval for exceptions!
Rehab work
  • Form top flange monolithically with expansion joint to repair damage to top flange of beam (removal of entire portion on left side of web). Excess damage caused!