Value Engineering

 

Federal regulations

Per 23 CFR Part 627: Value Engineering, under § 627.5 b

Applicable projects requiring a VE analysis shall include the following:

  1. Each project located on the National Highway System (NHS) (as specified in 23 U.S.C. 103) with an estimated total project cost of $50 million or more that utilizes Federal-aid highway funding;
  2. Each bridge project located on the NHS with an estimated total project cost of $40 million or more that utilizes Federal-aid highway funding;
  3. Any major project (as defined in 23 U.S.C. 106(h)), located on or off of the NHS, that utilizes Federal-aid highway funding in any contract or phase comprising the major project;
  4. Any project where a VE analysis has not been conducted and a change is made to the project's scope or design between the final design and the construction letting which results in an increase in the project's total cost exceeding the thresholds identified in paragraphs (b)(1), (2) or (3) of this section; and
  5. Any other project FHWA determines to be appropriate that utilizes Federal-aid highway program funding.