About this project
MnDOT is planning a resurfacing project for Highway 4, from Highway 212 in Hector to Highway 19 in Fairfax. The primary goal of this project is to improve the safety and pavement conditions of the highway. Additionally, several culverts along the route will be repaired and replaced as part of the project to enhance infrastructure and ensure long-term durability.
Schedule Update
Originally planned for 2027, the Highway 4 resurfacing project has been moved up one year and will now be constructed in 2026.
Traffic impacts
During construction, the detour route will include Highway 212, County Road 16, and Highway 19 and is expected to last the full construction season.
Project Update: July 16, 2026
- The contractor finished culvert work, and installing geotextile which is used to improve performance, drainage, stability, and environmental protection.
- Crews have started paving and will continue into next week.