About this project
Traffic impacts
Work started on I-35 northbound and southbound Aug. 24 and is expected to be completed early October. Work is scheduled to begin end of September on Highway 14 and will be completed late October.
- Single lane closure in each direction during the resurfacing work on I-35 and Highway 14
Short-term ramp closures will occur and motorists will be detoured. It is anticipated that ramp closures will last several hours to a few days. Closures will be shown on 511mn.org.
- Highway 14 eastbound off-ramp closure to Highway 218
Detour: From Highway 14 eastbound, take County Road 45 exit and go south. Go east on County Road 60 which intersects with Highway 218. - Highway 14 eastbound on-ramp closure from County Road 45
Detour: Continue north on County Road 45 and take exit to Highway 14 westbound. Take exit at I-35 and then take exit to Highway 14 eastbound. - Highway 14 westbound off-ramp closure to County Road 45
Detour: Continue west on Highway 14. Take exit at I-35 and then take exit to Highway 14 eastbound. Take County Road 45 exit. - Highway 14 eastbound off-ramp closure to County Road 45
Detour: Continue east on Highway 14. Take exit to Highway 218, go north and take exit to Highway 14 westbound. Take exit to County Road 45. - Highway 14 westbound on-ramp closure from County Road 45
Detour: Go south on County Road 45 and take the Highway 14 eastbound exit. Take exit to Highway 218, go north and take exit to Highway 14 westbound. - Highway 14 eastbound on-ramp closure from Highway 218
Detour: Go north on Highway 218 and take the Highway 14 westbound exit. Take the County Road 45 exit and then exit to Highway 14 eastbound.
Summary of work
I-35 northbound and southbound lanes will be resurfaced from Highway 14 to Straight River Rest Area. Work is scheduled to begin Aug. 24, and it's expected to be completed mid-October.
Highway 14 eastbound and westbound lanes will be resurfaced from I-35 to Highway 218. Work is tentatively scheduled to begin early October. It is anticipated that it will be completed by early November.