Current traffic impacts

Work zone on Highway 114. Culvert locations shown on map are approximate.
- Highway 114 between Lowry and Interstate 94 closed to thru-traffic until October.
- Local traffic only: If you have destination on Hwy 114, you are permitted to enter the work zone to get there. Remember you are in an active work zone, please travel with caution and obey all signage and barriers.
- When culvert replacements start, weather permitting, crews will begin on the south end, working north.
- Residential access is maintained, but areas where culverts are being replaced may be impassable at times and you may need to use an alternate route around the work site.
- Work at each culvert site may take 1-3 days to complete.
- Watch for loose gravel, large equipment and workers throughout the entire work zone
- Thru-traffic detour: I-94, Highway 29 and Highway 55 until October
- Highway 27 remains open to cross traffic
Stay informed
Sign up for project email updates so you can stay up-to-date on the project's schedule, construction progress, traffic changes and more during construction!