Minnesota Department of Transportation

511 Travel Info

Interstate 94 westbound

Evansville to Grant/Otter Tail county line

Current traffic impacts

  • Traffic is currently head-to-head through the project area. Please travel with care.
  • Starting June 23 until August: Westbound off-ramp at Exit 82 near Evansville closed to all travelers to allow crews to reconstruct the deceleration lane and pave westbound I-94 near the ramp.
    • Detour: Use Exit 90 near Brandon and follow the alternate route toward Evansville and/or Highway 79.

Project details

Map shows work zone for I-94 westbound concrete resurfacing project from the Grant/Otter Tail County line to Highway 79 near Evansville
Project map for westbound I-94 resurfacing west of Evansville

In 2026, the Minnesota Department of Transportation will resurface the westbound lanes on Interstate 94 from Highway 79 near Evansville to the Grant/Otter Tail county line (approximately near the County Road 26 overpass).

Key project elements

  • Concrete overlay
  • Minor bridge work
  • Replace guardrail
  • Line culverts