Future work, traffic plans
The Wadena project will take three construction seasons to complete from June 2025 to August 2027.
Work by year map

MnDOT will improve these areas on Hwy 10, 29 and 71. Select map to enlarge.
Schedule at a glance
All information is tentative and subject to change by contractor or MnDOT.
Dates |
Map color |
Construct |
Impacts |
April-August 2027 |
Dark blue |
Hwy 10 - east of Co. Rd. 20 to Oink Joint Rd.
|
Hwy 10 Open one lane, each way
|
April-late October 2026 |
Cyan COMPLETE |
2026 work areas map
Hwy 10
Hwy 71 south of Hwy 10
Hwy 29
|
Complete |
June-November 2025 |
Orange COMPLETE |
2025 work areas map (PNG)
|
Complete |