Central Minnesota

2026 work

These roadwork projects on state highways will have traffic impacts, but will be led, constructed and communicated by the city, township or county. Check 511mn.org for current impacts on these projects.

Improve access and safety

Stearns County to realign the intersection at Hwy 4 and Stearns Co. Rd. 32, replace culverts, add lighting and resurface the roadway. Google map of location

  • Construct: July 13-early October
  • Impacts: Lane or shoulder closures on Hwy 4; changes to local access; detour for those on Co. Rd. 32
  • Estimated cost: $1 million
  • Led by: Stearns County
    Project work map
    Stearns Co. Rd. 32 closed to/from Co. Rd. 32. Follow road signs for access north or south of Lake Henry

Improve access and traffic flow

Wright County to construct a roundabout at Hwy 12 and Co. Rd. 14/Dague Ave. in Delano.

Improve access and traffic flow

Wright County to construct a roundabout at Hwy 24 and Co. Rd. 7. The project will be coordinated with MnDOT's interchange reconstruction project on Hwy 24 at I-94 in Clearwater.

  • Construct: Aug. 10 to late November 2026
  • Impacts: Narrow lanes with no shoulders on Hwy 24; local access changes on Co. Rd. 7
  • Estimated cost: TBD
  • Led by: Wright County. Visit the City of Clearwater's website for project information, updates and links to project newsletters.

Improve access and traffic flow

Wright County to construct a roundabout at Hwy 25 and Co. Rd. 113. The project will be coordinated with MnDOT's 2026 roadwork project on Hwy 25 from Buffalo to Monticello.

  • Construct: July-late fall 2026
  • Impacts: Lane or shoulder closure on Hwy 25; local access changes to 14th St. NE
  • Estimated cost: $2.5 million
  • Led by: Wright County

Wright County to improve access at interchange

Construct roundabouts at the I-94 interchange on/off ramps and Co. Rd. 137. I-94 impacts will be coordinated with MnDOT's I-94 Albertville to Monticello Gap project.

  • Construct: 2026
  • Impacts: Lane closures, changes to access, follow directional signs
  • Estimated cost: $5.8 million
  • Led by: Wright County
Project location
Wright County Co. Rd. 137 project location map of two-year project on Co. Rd. 137 in Albertville and Otsego. Select map for larger image (PNG). Map by Wright County.

Sherburne County to construct new interchange 2025-2026

Construct new interchange at Hwy 169 and Co. Rd. 4 (Freemont Ave.) in Zimmerman.

  • Construct: August 2025-November 2026
    • 2025 complete: Prepare for construction and reconstruct local roads
    • Spring - fall 2026: Construct interchange
  • Impacts: Lane closures, changes to access on Hwy 169 and local roads in Zimmerman.
  • Led by: Sherburne County
Project location
Sherburne County to construct a new interchange at Zimmerman at Hwy 169 and Co. Rd. 4 in 2025-2026. Hwy 169 impacts at future interchange in 2026. Select work map image (JPG) to enlarge. Image by Sherburne County.

Landscape roundabout area

Add plantings to establish turf and beautify the area at the roundabout on Hwy 169 and Red Oak Dr. Google map of location

  • Construct: 2026
  • Impacts: Minimal shoulder closures
  • Estimated cost: $2.5 million
  • Led by: City of Aitkin

Studies, future plans

These projects are on state highways but are led and communicated by the city, township or county (State Aid, partnerships or specific grant funds). For more specific details visit the leading agency on the project.

Project study to improve the intersection

Sherburne County is leading a planning and development study to improve the intersection of Hwy 10 and Co. Rd.11 in Becker Township. This intersection is a critical connection for commuters, freight, emergency responders, and regional travel. Today this intersection is often congested and has a history of frequent crashes due to heavy trafic and train crossings on the adjacent rail line.