Know before you go: check 511mn.org
Upcoming
Overnight's week of Mon, Nov. 16
Heads up! Crews will deliver and place beams for the new Hwy 24 bridge to span I-94. The work will occur each overnight between 8 p.m. and 5 a.m. starting Mon evening, Nov. 16 through Thu morning, Nov. 19.
- Both directions of I-94 will be reduced to one-lane and use the Hwy 24 on/off ramps to go around the closed work site. Expect to slow down or stop. Use alternate routes to avoid delays.
- Hwy 24 bridge closed at I-94, follow detour signs
- Note: More details to be shared once confirmed
Current work zone
Off-road work and shoulder closures to occur year-round. Primary work in 2026 is to widen and prepare work areas for 2027 construction.
Hwy 24
Open in both directions
- Expect narrow lanes with no shoulders, reduced speeds, lane shifts and slow moving vehicles entering and exiting work areas, flaggers and stop-and-go traffic
- Access may change at times, follow signs
- Access to businesses open and maintained
I-94
Open in both directions
- Expect narrow lanes/no shoulders, lane shifts and reduced speeds. Crews at work along the interstate
- Single-lane closures at off-peak hours
- Exit/entrance ramps open with no shoulders
Wright County roundabout project
Co. Rd. 7 and Hwy 24
Aug. 17-late November
- Hwy 24 open with no shoulders
- Co. Rd. 7 open with no shoulders
- Intersection access:
- Left-turn closed: SB Hwy 24 to EB Co. Rd. 7- use detour (Google maps)
- Left-turn closed: WB Co. Rd. 7 to SB Hwy 24 - use detour (Google maps)
- City of Clearwater and Wright County project updates and contacts