Current
- Periodic lane or shoulder closures as crews prepare the work zone.
Detour begins Mon, April 22
Aitkin to Hassman
Late April to mid-October
Reconstruct and close Hwy 169/210 between Aitkin Co. Rd. 12 and Hwy 210, includes underground pipes.
- Detour through McGregor: Co. Rd. 12 (400th Ave.) Aitkin, Hwy 47, Co. Rd. 4 (Dam Lake St.), Hwy 65 McGregor, Hwy 210
All traffic impacts are tentative and weather dependent.
Local impacts
Access will be open and maintained to those who live, work or visit those along the work zone; however expect changes.
Future drainage work
Hard closures will be necessary to replace drainage structures beneath Hwy 169. Overall crews will work south west to north east. More schedule details to come. Map of locations:
a. Pipe south of Co. Rd. 12/83
b. Pipe north of Co. Rd. 12/83
c. Box bridge between Co. Rd. 12/83 and 390th St.
d. Pipe between 390th St.and 365th St.
e. Box bridge north of 370th Ln.
f. Pipe north of 370th Ln.
g. Box bridge south of Co. Rd. 54/56
h. Box bridge south of Co. Rd. 54/56
i. Pipe between 395th St and Rice River