Hwy 2 - Warba Resurfacing Project

Itasca

Traffic Impacts

Tree removal will start on November 30, weather dependent. Travelers can expect single lane traffic controlled by flaggers and shoulder closures during work hours.

Construction will begin in spring 2027. A detour will be required for a portion of the project.

About this project

A rendering of the Hwy 2 Warba project.

Click image for full-size image

Summary of work

Highway 2 in Warba from 0.1 miles west of Highway 73 to 0.26 miles west of Highway 74 in Itasca County. The project involves 0.8 miles of mill and overlay, ADA improvements, bike and pedestrian improvements and traffic calming elements. It also includes redecking the bridge over the Swan River.

View a layout of the project (PDF)

Public meeting

MnDOT hosted a public meeting on March 28, 2024, to give an update on the Highway 2 road construction project through Warba. For those unable to attend, the presentation is below.