Project Stages
Stage 2A - Early May to Late July: Minnesota Pollution Control Agency Dig Site Work and 3rd Avenue West to Broadway
Stage 2C - Early May to Late June: 8th Avenue West to 3rd Avenue West (Lake/South Side)
Stage 2B - Late June to Early September: 8th Ave W to 3rd Ave W (Inland/North Side)
Stage 2D - Early to Late September: 8th Avenue West to 3rd Avenue West bumpouts and finishing work
2021 project stage map. The green dot represents the MPCA dig site location. Click to enlarge. 2021 project detours by stage. The truck detour will remain during all of construction. Click to enlarge.
About this project
Project animation
Construction staging
Summary of work
- Reconstruct and resurface Hwy 61 through Grand Marais, improve accessibility, replace box culverts