Construction begins August 3. Work includes resurfacing 17 miles of road, including shoulders and turn lanes, repairing drainage pipes and other road improvements.
The project will require a detour for through traffic on Highway 6 starting on Aug. 3 to allow replacement of 3 culvert pipes. The posted route is via Cty Rd 1 Emily, Co. Rd. 3 (Grove St.), Hwy 169 Waukenabo to Hwy 200 Hill City, back to Hwy 6 Remer. The current schedule for road work during the detour and replacing the culverts on Highway 6 is as follows:
- Replace culvert near mile post 55, south of Remer from August 3-5.
- Replace culvert near mile post 40, about 2 miles north of Outing from August 6-7
- Replace culvert near mile post 39.5, about 1.5 miles north of Outing, August 10-12
Exact dates may change depending upon how long construction takes at each pipe location. Culvert work will take no longer than 12 calendar days total.
Motorists traveling along Highway 6 can expect flagging operations and a pilot car where repaving is occurring. Work will also occur at Cty Rd 7 to realign and improve access, but the intersection will remain open to traffic. Through traffic can follow the detour route to avoid traffic impacts. Paving is expected to last through late August.
Work is expected to be complete in September.
Click image for full-size image
About this project
Click image for full-size image
MnDOT will resurface and improve Hwy 6 from the Roosevelt Lake bridge, just north of Cass Co. Rd. 58, in Outing and Hwy 200 in Remer in 2026. Project requires a detour to replace underground pipes.
Summary of work
- Resurface 17 miles of road, includes shoulders and turn lanes
- Replace or repair drainage pipes, includes ditches
- Realign and improve access at Cass Co. Rd. 7
- Upgrade guardrail, includes Roosevelt Lake bridge
- Install road markings and mumble strips