Project selection

Increasing the transparency of how we select highway construction projects

Specialty and competitive programs

Safety rest areas

Scoring criteria for safety rest area projects. Out of 100 possible points, 35 points are based on condition, 25 points are based on long-range objectives, 15 points are based on compliance with the Americans with Disabilities Act, 10 points are based on usage, 10 points are based on coordination and synergy with other work, and 5 points are based on network designation.

MnDOT's Safety Rest Area Program funds construction, repair and rehabilitation of rest areas and waysides. Rest areas support commercial freight movements, serve as a countermeasure to drowsy driving, and promote state and regional tourism as well as providing convenient time-saving services for travelers.
MnDOT focuses investment in rest area projects that:

  • Eliminate an unsafe highway shoulder stop
  • Occur at a critical location for commercial trucks
  • Occur at a strategic location for promoting the state and state tourism
  • Provide another safety function
  • Are situated at the desired 50-60 mile spacing on the Rest Area Service Network as a countermeasure to drowsy driving and for other highway safety purposes

MnDOT Rest Area Program identifies capital investment candidate projects based on the physical condition of rest area buildings and pavements, accessibility and building code compliance, partnership potential and availability of alternative funding sources.
MnDOT Districts also identify rest area capital investment projects. These typically focus on the physical condition of rest area vehicular pavements and ramps. These projects typically use one-time funding.

What’s been selected?

Related links

How the projects scored

The construction costs shown on this list represent a rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2021

Score  Route Location Year planned (FY) Construction cost estimate for planning purposes Comment
100 I-94 Hansel Lake *** 2027 $4,000,000 New Fergus Falls rest area (Lake Iverson & Hansel Lake replacement)
80 I-35 Beroun Vicinity * Not Selected Unknown A new rest area is needed in the Beroun vicinity to meet program spacing objectives on southbound I-35. A location has yet to be determined.
80 I-94 Lake Iverson (E.B.) *** 2027 $4,000,000 Lake Iverson was demolished due to flooding and needs to be developed in a new location. A new Fergus Falls rest area will replace Lake Iverson & Hansel Lake
72 I-94 Burgen Lake (W.B.) 2024 $8,000,000 Building rehabilitation and expansion, vehicular pavement rehab/reconstruction, and truck parking expansion
67 I-90 Adrian (E.B.) ** Not Selected Unknown Possible future conversion to truck-only rest area. 
62 I-90 Adrian (W.B.) ** Not Selected Unknown Possible future conversion to truck-only rest area. 
55 I-94 St. Croix Transportation Information Center (W.B.) 2023 $6,100,000
42 US2 Fishers Landing Transportation Information Center  Not Selected Unknown On Hold.  Full reconstruction needed.  BSS unable to deliver.
42 I-35 Forest Lake (S.B.) Not Selected Unknown District roofing, storefront and restroom improvement project.  Maintenance project.
32 US2 Oak Lake 2023 Unknown
30 MN60 Wantonwan River  Not Selected Unknown FY21 funding shifted to Thompson Hill Pavements 
27 I-35 Thompson Hill Transportation Information C+E4enter  (S.B.) Not Selected Pavement reconstructed in 2021
27 I-90 Beaver Creek TIC (E.B.) Not Selected Unknown
27 US10 Central Minnesota Transportation Information Center Not Selected Unknown
25 US169 Minnesota Valley Not Selected Unknown
25 I-35 Albert Lea TIC (NB) Not Selected Unknown
25 I-90/US61 Dresbach TIC (W.B.) Not Selected Unknown
25 I-94 Elm Creek (E.B.) 2024 Unknown Site ADA improvements
22 US169 Rum River Not Selected Unknown
20 I-94 Enfield (E.B.) Not Selected Unknown
20 I-94 Fuller Lake (W.B.) Not Selected
20 I-94 Moorhead Transportation information center (E.B.) Not Selected Unknown
15 I-94 Big Spunk Lake (E.B.) Not Selected Unknown
15 I-90 Blue Earth (W.B.) Not Selected Unknown
15 MN371 Brainerd Lakes Area Welcome Center Not Selected Unknown
15 US2 Cass Lake Not Selected Unknown
15 I-90 Enterprise (E.B.) Not Selected Unknown
15 I-35 Goose Creek (N.B.) Not Selected Unknown
15 MN61 Gooseberry Falls Not Selected Unknown
15 MN61 Grand Portage Visitor Center Not Selected Unknown
15 I-94 Lake Latoka (E.B.) Not Selected Unknown
15 I-90 Marion (W.B.) Not Selected Unknown
15 I-94 Middle Spunk Lake (W.B.) Not Selected Unknown
15 I-35 New Market (S.B.) Not Selected Unknown
15 I-35 Straight River (S.B.) Not Selected Unknown Pavement reconstructed in 2021
15 I-35 Heath Creek (N.B.) Not Selected Unknown Pavement reconstructed in 2021
15 I-35 Straight River (N.B.) Not Selected Unknown
15 MN60 Worthington Transportation Information Center Not Selected Unknown
12 US53 Anchor Lake Not Selected Pavement reconstructed in 2021
12 US10 Frazee Not Selected Unknown
10 I-90 Blue Earth (E.B.) Not Selected Unknown
10 I-35 Culkin (N.B.) Not Selected Unknown
10 US10 Daytonport Not Selected
10 I-90 Highforest (E.B.) Not Selected
10 I-90 Oakland Woods (W.B.) Not Selected Pavement reconstructed in 2021
10 MN61 Tettegouche Not Selected Unknown
5 I-90 Clear Lake (E.B.) ** Not Selected
5 I-90 Des Moines River (W.B.) ** Not Selected
5 I-90 Hayward (E.B.) Not Selected Pavement reconstructed in 2020
5 I-35 General Andrews (S.B.) Not Selected Unknown
5 I-35 Kettle River (N.B.) Not Selected Unknown
5 US61 Lake Pepin Not Selected Unknown

Notes
* A rest area is needed in the Beroun vicinity to meet program spacing objectives on southbound I-35. This is on hold until after existing rest areas brought into good condition and ADA compliant.
** The Adrian rest areas are in very poor physical condition and need replaced however, by reconstructing the Des Moines River and Clear Lake rest areas the Adrians could be demolished. This would allow MnDOT to accomplish the objective of consolidating rest areas.
*** Lake Iverson was demolished due to flooding and needs to be developed in a new location.