Increasing the transparency of how we select highway construction projects

Non-National Highway System pavement projects

MnDOT Metro District

How the projects scored in 2020

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2020

Score Route Description High level construction cost estimate for planning purposes Year Planned (FY) Comments
90 MN 13 Medium mill and overlay from I-35W to Yankee Doodle Road $6,370,000 Not Selected Not  district priority. Will continue to monitor pavement performance
83 MN 5 Medium mill and overlay from Carver County Road 17 to Hennepin County Road 4 $3,260,000 Not Selected Not  district priority. Will continue to monitor pavement performance
83 MN 97 Thin mill and overlay from Roundabout to Hwy 95 $11,450,000 2028  
82 MN 19 Medium mill and overlay from Red Wing Ave to LeSueur/Scott County Line $220,000 Not Selected Not  district priority. Will continue to monitor pavement performance
81 MN 5 Medium mill and overlay from Fuller Rd to Wooddale Ave $710,000 Not Selected Not  district priority. Will continue to monitor pavement performance
81 MN 5 Medium mill and overlay from County Road 4 to Fuller Rd $580,000 Not Selected Not  district priority. Will continue to monitor pavement performance
80 US 10 Medium mill and overlay from .2 miles north of I-694 to I-694 $470,000 Not Selected Not  district priority. Will continue to monitor pavement performance
79 MN 62 Medium mill and overlay from I-35E to Hwy 52 $3,420,000 Not Selected Recent rehabilitation completed
79 MN 13 Medium mill and overlay from Senneca Rd to Yankee Doodle Rd $620,000 Not Selected Not  district priority. Will continue to monitor pavement performance
78 MN 25 Medium mill and overlay from White sty to State St $60,000 Not Selected Not  district priority. Will continue to monitor pavement performance
77 MN 13 Medium mill and overlay from County Road 42 to Connelly Pkwy $790,000 Not Selected Not  district priority. Will continue to monitor pavement performance
77 US 61 Medium mill and overlay from Roselawn Ave to Hwy 36 $1,090,000 Not Selected Not  district priority. Will continue to monitor pavement performance
77 US 61 Medium mill and overlay from I-694 to White Bear Ave $2,480,000 Not Selected Not  district priority. Will continue to monitor pavement performance
77 MN 19 Thin mill and overlay from LeSueur/Scott County Line to Scott/Rice County Line $3,330,000 2027  
77 MN 282 Major rehabilitation from Hwy 21 to Hwy 13 $1,170,000 2021
76 MN 5 Major rehabilitation from Sibley/Carver County line to 142nd St $460,000 2021
75 MN 47 Medium mill and overlay from 27th Ave to 35th Ave $1,080,000 Not Selected Not  district priority. Will continue to monitor pavement performance
75 MN 120 Medium mill and overlay from Ridge Dr to 4th St in Oakdale $1,410,000 2026  
75 US 10 Thin mill and overlay from Hwy 61 to Saint Croix River bridge $460,000 2027 Poor ride quality requires resurfacing.
75 MN 149 Major rehabilitation from Hwy 55 to I-494 $320,000 2028
74 MN 3 Reconstruction from Amana trail to south of Upper 55th Ave  $6,110,000 2029  
74 MN 97 Medium mill and overlay from east of Everton Ave to Hwy 61 Roundabout $30,000 2024
74 MN 41 Medium mill and overlay from Engler Rd to Pioneer Tr $520,000 Not Selected Not  district priority. Will continue to monitor pavement performance
73 MN 47 Reclaim and overlay from 153rd Ave to Cree St $15,560,000 2027
73 MN 95 Reclaim and overlay from Chisago County road 14 to Sunrise river $10,630,000 2028  
73 MN 95 Reconstruction from Oakview Ave to Chisago County Rd 14 $6,900,000 2028  
73 MN 97 Medium mill and overlay from US61 Roundabout to end of US61 Roundabout $40,000 2024
72 US 61 Medium mill and overlay from Hwy 36 to I-694 $1,690,000 Not Selected Not  district priority. Will continue to monitor pavement performance
72 MN 95 Medium mill and overlay from Bailey Rd to 70th St $730,000 Not Selected Recent rehabilitation completed
71 MN 3 Medium mill and overlay from 190th to Dakota County Road 58 $610,000 Not Selected Newer roundabout completed 
71 MN 13 Medium mill and overlay from .4 miles west of Dakota Ave to .2 miles east of Dakota Ave $600,000 Not Selected Not  district priority. Will continue to monitor pavement performance
71 MN 13 Medium mil and overlay from Yankee Doodle Rd to I-494 $380,000 Not Selected Not  district priority. Will continue to monitor pavement performance
71 US 61 Medium mill and overlay from Hwy 96 to .8 miles north $400,000 Not Selected Recent rehabilitation completed
71 MN 252 Major rehabilitation from 85th to Hwy 610 $440,000 2025 Corridors of commerce
70 MN 101 Medium mill and overlay from Carver County Road 61 to Carver County Road 14 $280,000 Not Selected Not  district priority. Will continue to monitor pavement performance
70 MN 3 Medium mill and overlay from Upper 55th St to Robert St $790,000 2029 Selected prior to policy (in 2019-2028 CHIP)
70 MN 3 Medium mill and overlay from Railroad crossing to Chesterfield. $260,000 Not Selected Not  district priority. Will continue to monitor pavement performance
70 MN 25 Medium mill and overlay from Scott County line to Sibley County Road 14 $500,000 Not Selected Not  district priority. Will continue to monitor pavement performance
70 MN 25 Medium mill and overlay from Sibley County Road 14 to Hwy 5 $3,020,000 Not Selected Not  district priority. Will continue to monitor pavement performance
70 MN 95 Medium mill and overlay from Hwy 36 to north of 56th St N $940,000 Not Selected Not  district priority. Will continue to monitor pavement performance
69 MN 5 Medium mill and overlay from Birch St to Scandia Rd $930,000 Not Selected Not  district priority. Will continue to monitor pavement performance
69 MN 47 Major rehabilitation from Central Ave to Broadway St $730,000 2024
69 MN 13 Major reconstruction from I-494 to Hwy 55 $5,250,000 2026  
69 MN 50 Medium mill and overlay from Hwy 52 to Hwy 60 $5,630,000 2026  
69 US 61 Medium mill and overlay from Hwy 97 to north of Washington County Road 2 $7,600,000 2030 RQI is predicted to fall into the poor category before 2030.
69 US 61 Medium mill and overlay from Frenchman Rd to Trailer Park Entrance $180,000 Not Selected  
69 US 61 Medium mill and overlay from Forest Lake Circle to south of 250th St N $310,000 Not Selected  
69 MN 284 Reclaim and overlay from Hwy 212 to Elm Creek Rd $5,760,000 2026 Selected prior to policy (in 2019-2028 CHIP)
69 MN 21 Medium mill and overlay from south of Old Hwy 169 to Mill St $120,000 2027  
68 MN 21 Medium mill and overlay from 230th St to Meadow Wood Court $570,000 Not Selected  
67 US 61 Medium mill and overlay from 250th St N $330,000 Not Selected  
67 US 61 Medium mill and overlay from Chisago County Road 31/32 to 267th St in Wyoming $70,000 Not Selected  
67 MN 19 Medium mill and overlay from Scott County Road 143 to 11th ave SW $90,000 Not Selected  
67 MN 95 Medium mill and overlay from north of Commercial Ave to Hwy 36 $440,000 Not Selected  
66 MN 97 Medium mill and overlay from I-35W to Hwy 61 $500,000 2024  
65 MN 47 Medium mill and overlay from Broadway St to 27th Ave NE $1,270,000 Not Selected  
65 MN 3 Medium mill and overlay from 145th St to Hwy 149 $5,760,000 2026 Selected prior to policy (in 2019-2028 CHIP)
65 MN 13 Medium mill and overlay from I-35E to Hwy 13 $480,000 Not Selected  
65 MN 95 Medium mill and overlay from .25 miles South of Valley Creek to .25 miles north of Valley Creek $100,000 Not Selected  
65 MN 149 Medium mill and overlay from Hwy 3 to Albano Tr $100,000 Not Selected  
64 MN 13 Medium mill and overlay from 2nd St to U-35E $360,000 Not Selected  
63 MN 5 Medium mill and overlay from .2 miles east of Carver County Road1 0 to .2 miles west of Carver County Road 10 $90,000 Not Selected  
63 MN 121 Medium mill and overlay from Pedestrian Bridge to 58th St $1,230,000 2025 Selected prior to policy (in 2019-2028 CHIP)
63 MN 95 Medium mill and overlay from Vista Road to Chisago County Road 16 $180,000 Not Selected  
63 MN 96 Medium mill and overlay from Hwy 61 to Hwy 95 $15,350,000 2030 RQI currently in the poor to fair range.
62 MN 19 Medium mill and overlay from 11th Ave SW to 5th Ave SW $90,000 Not Selected  
62 MN 95 Medium mill and overlay from .7 miles north of I-94 to I-94 $360,000 Not Selected  
62 MN 95 Medium mill and overlay from I-94 to Valley Creek $300,000 Not Selected  
62 MN 41 Medium mill and overlay from Pioneer Tr to Hwy 5 $440,000 2023 Selected prior to policy (in 2019-2022 STIP)
62 MN 41 Medium mill and overlay from Hwy 5 to Hwy 7 $530,000 Not Selected  
61 MN 5 Medium mill and overlay from Hwy 25 to .1 miles north $20,000 Not Selected  
61 MN 25 Medium mill and overlay from Hwy 5 to Hwy 7 $1,320,000 2021 Selected prior to policy (in 2019-2022 STIP)
60 MN 13 Reclaim and overlay form Eagle Creek to Scott  County Road 42 $5,360,000 2030 RQI currently in the poor to fair range.
60 MN 95 Reclaim and overlay from Hwy 8 to Hwy 97 $19,580,000 2029 Selected prior to policy (in 2019-2028 CHIP)
59 MN 25 Thin mill and overlay from Hwy 212 to Hwy 5 $2,820,000 2026 Selected prior to policy (in 2019-2028 CHIP)
59 US 61 Major rehabilitation from 267th St to I35 $80,000 2021 Selected prior to policy (in 2019-2022 STIP)
58 MN 3 Medium mill and overlay from Ann Marie Tr to Amana Tr $50,000 Not Selected  
57 MN 25 Medium mill and overlay from .2 miles south of Hwy 7 to Hwy 7 $50,000 Not Selected  
56 MN 95 Medium mill and overlay from Chestnut St to north of Commercial Ave $210,000 Not Selected  
55 MN 101 Medium mill and overlay from Hwy 5 to Town Line Rd $2,180,000 2026 Selected prior to policy (in 2019-2028 CHIP)
55 MN 3 Medium mill and overlay from Ann Marie Trail to Amana Trail $170,000 Not Selected  
54 MN 13 Medium mill and overlay from Hwy 55 to 2nd St  $460,000 Not Selected  
50 MN 5 Thin mill and overlay from Carver County Road 11 to Hwy 41 $4,900,000 2029 Selected prior to policy (in 2019-2028 CHIP)
48 MN 51 Thin mill and overlay from Hwy 36 to Grey Fox Rd $5,760,000 2026 Longitudinal joint distresses need fixing; not necessarily associated with poor ride. Other area needs included.
46 MN 20 Thin mill and overlay from Hwy 19 to Hwy 50 $6,620,000 2028 Selected prior to policy (in 2019-2028 CHIP)
44 MN 62 Thin mill and overlay from Mendota to I35E $1,250,000 2025 Predicted RQI does not match on the ground conditions. Poor condition requires resurfacing.
43 MN 25 Medium mill and overlay from Hwy 7 to White St $1,120,000 Not Selected
42 MN 3 Thin mill and overlay from Rice/Dakota County line to Hwy 50 $8,740,000 2028 Thin mill and overlay selected for preventive maintenance.
41 US 10 Medium mill and overlay from I35W to north of I494/694 $970,000 Not Selected  
41 MN 95 Thin mill and overlay from Isanti trail to west of Falcon Ave $1,520,000 2028 Poor ride requires resurfacing. Coordinating with locals.
40 MN 56 Thin mill and overlay from Goodhue/Dakota County line to Hwy 50 $4,390,000 2027 Thin mill and overlay selected for preventive maintenance.
38 MN 95 Medium mill and overlay from old County Road 15 to south of Hudson Rd D $440,000 Not Selected  
37 MN 95 Medium mill and overlay from .7 miles north of I-94 to I-94 $350,000 Not Selected  
34 MN 5 Major rehabilitation from 142nd St to Hwy 212 $140,000 2021 Selected prior to policy (in 2019-2022 STIP)
34 MN 47 Thin mill and overlay from 40th Ave to Hwy 10 $15,790,000 2030 RQI predictions do not match conditions on the ground. Requires resurfacing. Other area and local needs included.
34 MN 13 Medium mill and overlay from Hwy 19 to 1.5 miles north of Hwy 19 $1,530,000 Not Selected  
32 US 61 Medium mill and overlay from south of 170th st to .1 miles north of 170th $60,000 Not Selected Recent roundabout completed 
30 MN 101 Medium mill and overlay from Carver County Road 14 to Kiowa Tr $1,070,000 Not Selected
29 MN 101 Medium mill and overlay from Kiowa Tr to Lyman Blvd $170,000 Not Selected
28 MN 95 Reclaim and overlay from Isanti/Chisago County line to north of 392nd st $1,380,000 2028 Poor ride quality requires resurfacing. Coordinating with locals.
26 MN 95 Medium mill and overlay from Valley Crk to Jct Bailey $480,000 Not Selected  
26 MN 95 Medium mill and overlay from 70th St to Hwy 61 $1,250,000 Not Selected  
19 MN 55 Thin mill and overlay from Hwy 100 to Lyndale Ave $2,020,000 Not Selected RQI predictions do not match conditions on the ground. Requires resurfacing. Other functional and local needs included.
19 MN 47 Thin mill and overlay from Cree St to Anoka/Isanti County line $3,320,000 2025 Pavement is rough but surface work is secondary. Project driven by safety.
13 MN 95 Thin mill and overlay from Hwy 97 to north of Commercial Ave $17,710,000 2029 RQI prediction does not match conditions on the ground. Poor ride requires resurfacing.
9 MN 47 Thin mill and overlay from Industry ave to 153rd $2,130,000 2027 Thin mill and overlay selected for preventive maintenance.
4 MN 244 Thin mill and overlay from Ash St to Hwy 96 $1,050,000 2025 Notoriously poor riding urban section. Requires resurfacing. Other functional area and local needs included.