Non-National Highway System culverts
MnDOT District 8
How the projects scored in 2019
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
Score | Bridge | Route | Key intersection or closest landmark | Work Type | Year planned (FY) | High level construction cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
72 | 8323 | MN 68 | Stream south of 170th St in Porter | Replace | 2020 | $500,000 | |
70 | L3624 | MN 56 | Tributary to Split Rock Creek | Replace | Not Selected | $200,000 | |
67 | 8518 | MN 7 | Stream near New Germany | Replace | 2025 | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
57 | 1686 | US14 | Stream near Lake Benton | Replace | 2025 | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
56 | 8373 | US 75 | Stream near Canby | Replace | 2025 | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
56 | 8172 | MN 30 | Ditch south of Casey Jones Trail | Replace | 2027 | $150,000 | Selected prior to policy (in 2019-2028 CHIP) |
56 | 8737 | MN 21 | Yellow Medicine River | Replace | 2023 | $200,000 | Selected prior to policy (in 2019-2028 CHIP); being replaced with culverts 826 and 8736 |
48 | 8887 | US 59 | Irrigation ditch near Green Valley | Replace | 2021 | $200,000 | Selected prior to policy (in 2019-2022 STIP) |
47 | 6320 | MN 7 | Ditch north of 70th St near Granite Falls | Replace | Not Selected | $200,000 | |
46 | 91681 | MN 40 | Irrigation ditch near Raymond | Replace | 2020 | $200,000 | Selected prior to policy (in 2019-2022 STIP) |
46 | 8716 | MN 30 | Ditch south of Casey Jones Trail | Replace | 2027 | $150,000 | Selected prior to policy (in 2019-2028 CHIP) |
46 | 826 | MN 19 | Yellow Medicine River | Replace | 2023 | $200,000 | Selected prior to policy (in 2019-2028 CHIP); being replaced with culverts 8736 and 8737 |
46 | 8736 | MN 20 | Yellow Medicine River | Replace | 2023 | $200,000 | Selected prior to policy (in 2019-2028 CHIP); being replaced with culverts 826 and 8737 |