Project selection

Increasing the transparency of how we select highway construction projects

Non-National Highway System pavement projects

MnDOT District 3

How the projects scored in 2019

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2019

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
89 MN27 Reclaim and overlay from 9th St to 127th Ave $11,000,000 2029  
87 MN95 Reclaim and overlay from Isanti County Highway 15 to County Road 14 $8,700,000 Not Selected Not a current district priority, continue to monitor pavement performance
86 MN55 Medium mill and overlay from Pope/Stearns County line to Stearns/Kandiyohi County line $7,300,000 Not Selected Not a current district priority, continue to monitor pavement performance
85 MN95 Medium mill and overlay from Mille Lacs County line to Mille Lacs County Highway 15 $5,700,000 2028
84 MN95 Medium mill and overlay from Isanti County Highway 2 to Isanti/Chisago County line $3,900,000 2028
84 MN25 Medium mill and overlay from Crow Wing County line to Highway 210 $5,400,000 2029
83 MN47 Reclaim and overlay from Highway 23 to Highway 27 $17,000,000 Not Selected Not a current district priority, continue to monitor pavement performance
82 MN25 Medium mill and overlay from Skunk River Bridge to Crow Wing County line $8,200,000 2025
82 MN55 Medium mill and overlay from Stearns/Kandiyohi County Line to County Rd 181 $4,600,000 Not Selected Not a current district priority, continue to monitor pavement performance
80 MN238 Medium mill and overlay from 3rd Ave to Highway 27 $10,700,000 2024
80 MN107 Medium mill and overlay from Highway 65 to Isanti/Kanabec County Line $1,500,000 2025
80 MN65 Reclaim and overlay Isanti County Highway 30 to Wren Way $10,000,000 2026
80 MN4 Reclaim and overlay from Highway 55 to I-94 $19,000,000 Not Selected Not a current district priority, continue to monitor pavement performance
80 MN27 Reclaim and overlay from Todd County Highway 51 to Highway 71 $9,300,000 Not Selected Not a current district priority, continue to monitor pavement performance
78 MN95 Medium mill and overlay from Highway 23 to Mille Lacs County Line $6,000,000 2028
77 MN115 Medium mill and overlay from Highway 10 to Camp Ripley Entrance $2,600,000 2024
77 MN27 Medium mill and overlay from Highway 25 to Highway 169 $12,000,000 Not Selected Not a current district priority, continue to monitor pavement performance
75 MN29 Medium mill and overlay from Highway 71 to Jefferson St $300,000 Not Selected
74 MN87 Medium mill and overlay from Highway 64 to Highway 371 $5,800,000 Not Selected
73 MN28 Medium mill and overlay from Highway 71 to Highway 27 $11,000,000 2027 Selected prior to policy (in 2019-2028 CHIP)
73 MN55 Reclaim and overlay from Meeker/Stearns County line to Highway 24 $11,000,000 Not Selected
72 MN6 Reclaim and overlay from Cass/Itaska County line to Highway 2 $7,800,000 Not Selected  
70 MN25 Medium mill and overlay from Highway 23 to 115th Ave $300,000 Not Selected
70 MN237 Medium mill and overlay from Stearns County Highway 30 to I-94 $1,500,000 Not Selected  
69 MN200 Medium mill and overlay from Hubbard/Cass County line to Highway 371 $1,200,000 2024 Selected prior to policy (in 2019-2028 CHIP)
69 MN22 Thin mill and overlay from Hutchenson Ave to Highway 23 $2,500,000 2026 Selected prior to policy (in 2019-2028 CHIP)
69 MN6 Medium mill and overlay from Highway 210 to Mississippi River bridge $2,400,000 Not Selected  
69 MN301 Reclaim and overlay from Highway 10 to Stearns County Highway 8 $800,000 Not Selected
66 MN47 Medium mill and overlay from Anoka/Isanti County line to Highway 95 $6,000,000 2029 Selected prior to policy (in 2019-2028 CHIP)
64 MN238 Medium mill and overlay from Walnut Ave to 3rd Ave $1,500,000 2026 Selected prior to policy (in 2019-2028 CHIP)
62 MN18 Medium mill and overlay from Highway 169 to Highway 47 $5,200,000 2024 Selected prior to policy (in 2019-2028 CHIP)
61 MN107 Medium mill and overlay from Isanti/Kanabec County line to junction with Highway 23 $6,100,000 2027 Selected prior to policy (in 2019-2028 CHIP)
56 MN70 Reclaim and overlay from Highway 65 to Highway 107 $5,000,000 2025 Selected prior to policy (in 2019-2028 CHIP)
54 MN241 Minor concrete pavement rehabilitation/diamond grinding from Wright County Highway 19 to I-94 $2,200,000 Not Selected
53 MN287 Medium mill and overlay from 9th St to Highway 71 $900,000 2025 Selected prior to policy (in 2019-2028 CHIP)
53 MN87 Reclaim and overlay from Highway 371 to Highway 84 $5,900,000 Not Selected  
50 MN25 Medium mill and overlay from 1st st to Highway 55 $500,000 Not Selected  
46 MN25 Reclaim and overlay from Highway 12 to Reference point 207 $5,000,000 Not Selected  
45 MN64 Thin mill and overlay from Highway 210 to Highway 87 $9,800,000 2028 Selected prior to policy (in 2019-2028 CHIP)
42 MN200 Medium mill and overlay from Highway 371 to Highway 84 $8,000,000 Not Selected
41 MN27 Medium mill and overlay from Highway 10 to Highway 25 $5,500,000 Not Selected
37 MN6 Medium mill and overlay from 6 miles north of Mississippi River Bridge to North end of Roosevelt Lake bridge $7,100,000 Not Selected  
37 MN6 Medium mill and overlay from Highway 18 to Highway 210 $4,800,000 Not Selected
35 MN47 Medium mill and overlay from Highway 27 to Mille Lacs/Aitkin County line $4,200,000 Not Selected
34 MN6 Medium mill and overlay from Roosevelt Lake Bridge to Highway 200 $6,700,000 2026 Selected prior to policy (in 2019-2028 CHIP)
31 MN200 Medium mill and overlay from Highway 6 to Cass/Aitkin County line $400,000 Not Selected
25 MN24 Medium mill and overlay from Highway 55 to Poplar ave $400,000 Not Selected