I-94 standalone noise wall in St. Paul project area map.
Click map for larger version.
Crews constructed a new noise wall between Fairview Ave. and Prior Ave. on eastbound I-94 in St. Paul.
Summary of work
Constructed new wood plank and concrete post noise barrier
Removed trees
Schedule
Complete: August 2021 through June 2022
Location
EB I-94 between Fairview Ave. and Prior Ave. in St. Paul
Benefits
Reduce noise levels
Cost
$950,000
I-35E in Eagan
I-35E standalone noise wall in Eagan project area map.
Click map for larger version.
Previous noise levels exceeded state/federal noise standards. This area previously ranked 6th in the MnDOT Metro 2016 Noise Abatement Study. The city of Eagan provided a resolution of support for this project and committed to a 10% cost share. A public meeting and voting process was held in September 2017.
Summary of work
Constructed new 3,500 ft. long, 20 ft. tall concrete noise barrier