Minnesota Department of Transportation

511 Travel Info

Hwy 75

Pipestone

About this project

Hwy 75 in Pipestone
Hwy 75 project in Pipestone. Click to enlarge.

 

Current traffic impacts

  • MnDOT project will be completed under traffic using alternating lane closures
  • Reminder - driving over, through or around any barricade is a violation of Minnesota Statute 160.2715.

Project updates

  • Curb and gutter pours completed. 
  • ADA work continues and should be completed on June 18. 
  • Draining and milling completed. 
  • Paving, sign installation and pavement markings next week. 
  • Anticipated completion date of June 22. 

Summary of work

  • Resurfacing of Hwy 75 from the south intersection of Hwy 23 to Hwy 75/Hwy 23 in Pipestone
  • Construction of continuous two way center left turn lane
  • Update pedestrian crossings along project area to meet Americans with Disabilities (ADA) standards

Contractor

City of Pipestone project

  • The city of Pipestone is conducting utility work on Hwy 75
  • For questions on the utility project, please contact the city of Pipestone at 507-825-3324
  • Duininck Inc. is the contractor on the project