Summary of work

MnDOT work

  • Resurface Hwy 71 from just south of Viking Drive to the Hwy 212 intersection
  • Upgrade existing sidewalk, ramps and adjacent driveways to current Americans with Disabilities Act standards
  • Add new sidewalk to create connections with existing sidewalk
  • Replace portions of existing concrete curb and gutter and underground storm pipe from Ash Avenue to Hwy 212 to improve drainage during rainfall events
  • Regrade ditches and replace several culverts from Viking Drive to Ash Avenue to improve drainage
  • Add a bypass lane at Viking Drive (southbound)

City of Olivia work

  • Add flashing pedestrian crossing at Chestnut Avenue
  • Construct trail from Chestnut Avenue to Viking Drive

Traffic impacts

  • Hwy 71 will be open to two-way traffic during most of construction
  • Drivers can expecte temporary lane and shoulder closures, along with other minor traffic impacts
  • Pedestrians will encounter temporary sidewalk and ramp closures
  • A detour will be in place for about one month during construction; it is currently scheduled for August 8 through September 9; see detour map above
  • Everyone is encouraged to allow extra travel time and watch for traffic sign instructions and flagging crews
  • Homes and businesses along the project route will remain accessible

Project update

August 5, 2022

  • Work continues with removals of old materials and grading new sidewalks
  • Crews are working under traffic - please use caution in the work zone
  • Beginning Monday, August 8, the road will close and the detour posted above will be in place