Construction updates
Construction updates/access information will be provided throughout the project. Continue to check back for future updates.
May 1, 2026
- Crews are working Main Street to Luverne Street on sanitarty sewer, water mains, and storm sewer
- Crews are working from Cardinal Drive to Elm Street on storm sewer and water mains
Access
- To cross Highway 75 use Dodge Street or Adams Avenue
- Coming from the north, use James Street - open to residence south to Cashin Drive/North Fairview Drive
The City of Luverne will be giving notice for water outages or temporary water line installation.