Hwy 19 New Prague Downtown Reconstruction

New Prague

About this project

Summary of work

Reconstruction of Hwy 19 through downtown New Prague from the intersection of Highway 13/21 to 7th Ave. SE

I-494 Ramp Closures
Highway 19 map. Click for larger view.
  • Partnership with the City of New Prague and MnDOT to reconstruct approximately one mile of roadway through the historic downtown portion of the City.
  • Replace aging and deteriorating infrastructure
    • Municipal underground utilities (sanitary sewer and watermain)
    • Stormwater drainage systems
    • Roadway pavement and sidewalks
    • Intersection improvements proposed at First Avenue and Columbus Avenue with mini-roundabouts (to view mini-roundabouts located in St. James Minnesota visit https://youtu.be/eZUVUq5fFMw )

Traffic impacts

Construction detour concepts outlined here

Coordination items

  • City of New Prague Main Street website
  • Public involvement and stakeholder input
  • Local business impacts
  • Historic downtown
  • Topographic surveys/review of existing buildings
  • Railroad crossing
  • Right of Way and temporary construction easements
  • Construction staging and business access
  • Streetscaping & landscaping
  • Dožínky Festival – New Prague’s annual fall festival

Cost

  • $10-13 million based on planning estimates
  • Cost share estimates for the City of New Prague and MnDOT will be refined as the project is further developed