I-94/Hwy 75 interchange reconstruction

Moorhead

Project details

Current I-94/Hwy 75 work zone
Moorhead interchange area construction map

The Minnesota Department of Transportation is reconstructing the intersection of I-94 and Hwy 75/8th Street. In addition, auxiliary lanes (an additional lane in each direction) are being added on I-94 between Hwy 75/8th Street and 20th Street.

For the most up-to-date information on this project, sign up for project email alerts through the "Connect with us" section to the right or click here for the latest news.

What will it look like when it's complete? Click here for a simulation.

Current Traffic Impacts

  • I-94 work from Stage 1 continues
    • Intemittent work possible on I-94 (Auxiliary lanes are open)
  • Stage 2 began June 6. (Traffic Impact Overview Map / Traffic simulation AM / Traffic simulation PM / Detour)
  • Stage 2 traffic impacts
    • I-94 remains open, Hwy 75 is closed over I-94
    • East ramps on Hwy 75 to/from I-94 close for reconstruction
    • West ramps on Hwy 75 to/from I-94 remain open
    • Detours around the Hwy 75/8th St. work zone
    • The intersection of Hwy 75/8th St. and 30th Avenue is open for east-west traffic and for southbound traffic exiting the eastbound I-94 ramp
    • Northbound Hwy 75/8th St. is closed at 32nd Ave. All remaining traffic must turn left onto 32nd Ave.
    • Starting approx. July 11, the east side of the Hwy 75/8th Street intersection with 30th Avenue will close. Traffic will not be able to go east-west across Hwy 75 in this area. Nor will vehicle be able to turn left from southbound Hwy 75/8th Street to eastbound 30th Avenue.
    • For more details, check out the weekly update page

Construction Staging

The project will be constructed in four major stages over the 2016 construction season. Some minor cleanup may be completed in 2017. A PDF project handout with maps and summaries is available by clicking here.

Detours

Detour map - From early June to mid- to late-August, Hwy 75/8th St. traffic will detour to 40th Ave S, 20th St S and 12th Ave S. The 34th St. interchange will be used for some traffic movements.

Stage 1 (Late April to mid June)


Planned Work (Work Plan Map)

  • I-94 auxiliary lane construction (an additional lane in each direction) between Hwy 75/8th St. and 20th St.
  • Improvements to Hwy 75/8th St. between 22nd Ave. S. and 24th Ave. S.
  • Improvements to Hwy 75/8th St. between 30th Ave. S and 35th Ave. S./Belsly Blvd

Traffic Impacts (Traffic Impact Map)

  • I-94 and Hwy 75/8th St. will remain open
  • Shoulder closures and overnight lane closures on I-94 between Hwy 75/8th St. and 20th St.
  • Lane closures/traffic shifts on Hwy 75/8th St. between 22nd Ave S and 24th Ave S (Delays likely)
  • Lane closures/traffic shifts on Hwy 75/8th St. between 30th Ave S and 35th Ave S/Belsly Blvd (Delays likely)

Stage 2 (June 6 to early July)


Planned Work (Work Plan Map)

  • Reconstruction of the east side I-94 ramps (westbound off-ramp & eastbound on-ramp)
  • Reconstruction of the east side of Hwy 75 between 24th Ave. and 30th Ave.

Traffic Impacts (Traffic Impact Map / Traffic simulation AM / Traffic simulation PM / Detour)

  • I-94 remains open, Hwy 75 will close over I-94
  • East ramps between I-94 and Hwy 75 closed for reconstruction
  • West ramps between I-94 and Hwy 75 remain open (but traffic cannot cross the bridges)
  • East side of the Hwy 75/8th St. intersection with 30th Ave will close for two weeks

Stage 3A (Approx. early July to late July)


Planned Work (Work Plan Map)

  • Reconstruction of the eastbound I-94 off-ramp (southwest corner)
  • Reconstruction of the west side of Hwy 75 between 24th Ave. and 30th Ave.

Traffic Impacts (Traffic Impact Map / Traffic simulation AM / Traffic simulation PM / Detour)

  • I-94 remains open, Hwy 75 remains closed over I-94
  • Southwest off ramp from I-94 east to Hwy 75 closed for reconstruction
  • Northwest on ramp from Hwy 75 to I-94 west remains open
  • East ramps between I-94 and Hwy 75 re-open (but traffic cannot cross the bridges)
  • West side of the Hwy 75/8th St. intersection with 30th Ave will close for two weeks

Stage 3B (Approx. late July to mid/late August)


Planned Work (Work Plan Map)

  • Reconstruction of the westbound I-94 on-ramp (northwest corner)
  • Continued reconstruction of the west side of Hwy 75 between 24th Ave. and 30th Ave.

Traffic Impacts (Traffic Impact Map / Traffic simulation AM / Traffic simulation PM / Detour)

  • I-94 remains open, Hwy 75 remains closed over I-94
  • Northwest on ramp from Hwy 75 to I-94 westbound closed for reconstruction
  • Southwest off ramp from I-94 east to Hwy 75 re-opens
  • East ramps between I-94 and Hwy 75 remain open (but traffic cannot cross the bridges)

Stage 4 (mid/late August to October)


Planned Work (Work Plan Map)

  • Complete work on Hwy 75/8th St.
  • Seeding, cleanup

Traffic Impacts (Traffic Impact Map)

  • I-94 and Hwy 75/8th St. will be open
  • Lane closures on Hwy 75/8th St. (locations may change during this phase)

Cost estimate

  • $13.6 million

Preferred alternative

MnDOT has selected a preferred interchange alternative, the Diverging Diamond Interchange (DDI) alternative. (Click here for 9MB PDF of the layout.) The DDI best addressed the project purpose and need as well as stakeholder input. A simulation of projected 2035 traffic volumes flowing through the DDI can be viewed at at this link (77MB MP4) or a low-resolution version can be viewed here (17 MB WMV).