Status as of Sept. 17, 2025:

  • Crews are finishing up centerline culvert replacements. These areas remain gravel so please travel with caution.
  • Paving scheduled to start the week of Oct. 6, weather permitting.

Traffic impacts

  • Lane closures
  • Flaggers

Project details

In 2025, the Minnesota Department of Transportation will resurface Highway 210 from the junction at Highway 29 to just west of Highway 71 in Hewitt. The work is scheduled to begin Aug. 14, weather permitting.

Key project elements

  • Grading
  • Mill and overlay (resurfacing)
  • Culvert work