Hwy 10, 29 and 71—Wadena

Wadena and Otter Tail counties

Future work, traffic plans

The Wadena project will take three construction seasons to complete from June 2025 to August 2027.

Work by year map

Map of work areas for each year.
MnDOT will improve these areas on Hwy 10, 29 and 71. Select map to enlarge.

Schedule at a glance

All information is tentative and subject to change by contractor or MnDOT.

Dates

Map color

Construct

Impacts

June-November 2025

2025 work areas map (PNG)

Hwy 10 - Work west of Hwy 71

  • Excavate and build up road materials, replace pipes, construct new west segments of road, entrances, half of the Co. Rd. 92 roundabout and the north access to Co. Rd. 75
  • Off-road work along Hwy 10 in east limints near Oink Joint Rd. Construct road bases for future WB lanes and road connections

Hwy 71

Reconstruct Birch Ave. N to Elm Ave. N

  • Reconstruct road and install underground storm sewer and other city utilities
  • Remove pedestrian tunnel at old hospital
  • Update or install sidewalk

Resurface Elm Ave. N to north of Alfred St.

  • Underground structures
  • Center left-turn lane to Alfred St.
  • Sidewalk/trail to Juniper Ave.

Construct SB Hwy 71 turn-lane access to NB Hwy 10

  • Construct turn-lane, widen corner, relocate signal, reconstruct sidewalk along southwest side of Hwy 71/10

Visit the home page for current 2025 work and traffic impacts

April-early November 2026

  2026 work areas map

Hwy 10 - west of Hwy 71

  • Complete work: excavate and build-up road materials, replace pipes, construct road, medians and entrances, includes J-turn at Co. Rd. 75 and roundabout at hospital

Hwy 10 - east of Hwy 71

  • Excavate and build-up road materials, construct segments of road, entrances and half of roundabout at Harry Rich Rd., includes pipe bridges at Union Creek and Whiskey Creek

Hwy 71 - south of Hwy 10

Franklin to Aldrich Av. S

  • Resurface and update the road
  • Update or install sidewalks
  • Storm sewer work
  • Update or replace signals at Hwy 29, Bryant Ave. S, Aldrich Ave.

Hwy 29
Hwy 71 to west limits of Wadena

  • Resurface road,
  • Update/add sidewalk
  • Storm sewer work

Hwy 10, Hwy 71, Hwy 29

Open one lane each way:

  • Narrow lanes, lane shifts, flaggers
  • Access maintained and open to businesses and residents along the project; however expect changes and gravel surfaces

Tentative detours used at times:

Hwy 10

  • Hwy 10 closed between Co. Rd. 4 and Harry Rich Dr. to excavate deep and replace poor soils and install Union Creek pipe (about five weeks)
  • Hwy 10 closed between Co. Rd. 4 in Wadena and Oink Joint Rd. to replace Whiskey Creek pipe and other underground work. (about six weeks)
  • Co. Rd. 75 access closed south of Hwy 10 to reconstruct connection and complete J-turn. (about three weeks )

April-August 2027

2027 work areas map

Hwy 10 - east of Co. Rd. 20 to Oink Joint Rd.

  • Complete work: construct road, medians and entrances, includes roundabout at Harry Rich Rd.
  • Restripe urban portion to four lane from Co. Rd. 20 to Co. Rd. 4
  • Wrap up entire project

Hwy 10

Open one lane, each way

  • Narrow lanes, lane shifts, flaggers
  • No detours at this time