Minnesota Department of Transportation

511 Travel Info

Hwy 169—Aitkin to north of Hassman

Aitkin County

Current

  • Periodic lane or shoulder closures as crews prepare the work zone.

Detour begins Mon, April 22

Aitkin to Hassman

Late April to mid-October
Detour Aitkin to Hassman
Current work zone April 22. Select map to enlarge

Reconstruct and close Hwy 169/210 between Aitkin Co. Rd. 12 and Hwy 210, includes underground pipes.

All traffic impacts are tentative and weather dependent.

Traffic plan

The project requires segments of road closures with detours along with shoulder or lane closures with flaggers. Access will be open and maintained to those who live, work or visit those along the highway; however, expect changes.

Schedule at a glance

Information is tentative and subject to change. Detours will overlap at times.

Segment Construct Impacts
Aitkin to Hassman Late April to mid-October Detour through McGregor
Aitkin Mid-May to mid-July Detour in town
Hassman Late July to early September Detour through Palisade

Detours, work segments into three - one 2023 detour and two in 2024
2024 detour plans. Select map to enlarge

Aitkin to Hassman

Late April to mid-October
Detour in Aitkin via Hwy 169, Hwy 47 and Co. Rd. 12
Close-up of detour in Aitkin. Select map to enlarge

Reconstruct and close Hwy 169/210 between Aitkin Co. Rd. 12 and Hwy 210, includes underground pipes.

Aitkin

Mid-May to mid-July

Reconstruct and close Hwy 169/210 between the Ripple River bridge and Aitkin Co. Rd. 12.

  • Detour in Aitkin: Hwy 169 (Minnesota Ave.), Hwy 47 (Fourth St. SE), Co. Rd. 12 (400th Ave.)
  • Access will be maintained and open to businesses. Follow signs.

Hassman

Late July to early September

Reconstruct and close the Hwy 169 and 210 intersection for up to five weeks.

About this project

Project location map
Project location map.Select map to enlarge

MnDOT will reconstruct the road and widen shoulders from the Ripple River in Aitkin to the Mississippi River north of Hassman, Aitkin County.

Summary of work

  • Reconstruct 11 miles of road surface with a stronger, concrete overlay material
  • Widen the shoulders (eight-feet paved and two-feet gravel), lengthen turn lanes and improve road access
  • Add center turn lane through the city of Aitkin to Co. Rd. 12/83 (400th Ave.)
  • Repair or replace drainage infrastructure
  • Replace bridge

The Hwy 169 project will use an unbonded concrete overlay to repair and strengthen the road surface. The process consists of three layers.

Existing concrete layer

First, cracks and other imperfections are patched before the interlayer is placed over the existing surface

Interlayer

The interlayer serves as a bond breaker to prevent cracks on the existing concrete layer from transferring to the new concrete layer. This is called “reflective cracking”. Specially-designed fabric or up to an inch of asphalt may be used for this layer

New concrete layer

Seven to ten inches of new concrete is poured over the interlayer

The Hwy 169 project will use an unbonded concrete overlay to repair and strengthen the road surface. The process consists of three layers.

Existing concrete layer

First, cracks and other imperfections are patched before the interlayer is placed over the existing surface

Interlayer

The interlayer serves as a bond breaker to prevent cracks on the existing concrete layer from transferring to the new concrete layer. This is called “reflective cracking”. Specially-designed fabric or up to an inch of asphalt may be used for this layer

New concrete layer

Seven to ten inches of new concrete is poured over the interlayer
Informational graphic of an unbonded concrete overlay. Select image to enlarge