Hwy 135

Biwabik Main Street

Traffic impacts

Landscaping work will start on May 15 and is expected to last through July 15. Motorists can expect shoulder closures.

Highway repair work will take place later this summer.

About this project

A map of the Hwy 135 Biwabik detour route

Project work zone. Click to enlarge.

Summary of work

Highway reconstruction including:

  • New pavement
  • Curb and gutter
  • Sidewalk
  • City water main replacement
  • Storm sewer replacement
  • Sanitary sewer replacement

Work Schedule

  • 2020 Construction – May to September, all work except from 1st Avenue to 6th Avenue
  • 2021 Construction – May to October, remaining work between 1st Avenue to 6th Avenue

Complete Streets

MnDOT’s Complete Streets philosophy is being used to better accommodate all users of the corridor. As a part of the philosophy, highway lane and parking widths will be narrowed for traffic calming purposes and to make additional space available for other uses.