Construction

2020 construction season

Route (Hwy or Interstate) Description Begin Date End Date Total Construction Cost 2020 Construction Cost MnDOT District
1 Upgrade existing DWP railroad signal system at Hwy 1 near Cook 8/11/2019 2/11/2020 $124,000 $113,000 1
1 Replace culvert on Hwy 1 west of Thief River Falls 6/1/2020 10/30/2020 $350,000 $350,000 2
1 Replace Hwy 1 Stony River bridge and grade approaches near CR 2 8/12/2020 8/12/2020 $1,956,000 $1,886,000 1
1 Resurface and pedestrian improvements on Hwy 1 and Hwy 75 in Warren, and Hwy 75 in Argyle 7/7/2020 10/6/2020 $3,899,000 $3,689,000 2
1 Reconstruct Hwy 1 between Hwy 89 and Red Lake 5/1/2020 10/30/2020 $5,140,000 $5,400,000 2
1 Resurface Hwy 1 between Hwy 219 and Pennington CR 18 in Thief River Falls 8/17/2020 10/9/2020 $6,690,000 $6,400,000 2
1 Construct 3 roundabouts on Hwy 1 between Hwy 59 and Kinney Ave in Thief River Falls with frontage road and multi-use trail 6/1/2020 10/30/2020 $8,100,000 $6,680,000 2
1 Resurface Hwy 1 from Hwy 65 to Hwy 53, and on Hwy 73 from Hwy 1 to Hwy 53; repair bridge 7/13/2020 10/30/2020 $9,100,000 $4,300,000 1
2 Resurface Hwy 2 east of Crookston 6/1/2020 7/17/2020 $970,000 $1,000,000 2
2 Resurface Hwy 2 and construct multi-use trail in Bagley 6/8/2020 8/31/2020 $2,650,000 $2,326,000 2
2 Construct multi-use trail near Bena 7/6/2020 9/30/2020 $2,726,000 $2,726,000 2
2 Resurface Hwy 2 westbound lanes between Hwy 32 and Polk CR 44 near Marcoux Corner 7/6/2020 8/28/2020 $3,460,000 $3,300,000 2
2 Resurface Hwy 2 between Bena and Ball Club 7/13/2020 9/4/2020 $6,210,000 $5,800,000 2
3 Repair bridge on Hwy 3/Robert St at Mississippi River and railroad to .7 miles southeast of I-35E and I-94 in Saint Paul 7/10/2020 9/15/2020 $2,300,000 $1,402,000 Metro
3 Close Hwy 3 access, construct 4 left-turn lanes and a roundabout from 209th St in Farmington to Township Rd 58/170th St in Empire Township 7/1/2020 11/1/2020 $3,789,000 $3,789,000 Metro
5 Remove signal at Hwy 5/Albion Ave in Saint Paul, and realign Lexington Pkwy at Elway St with new signal and ADA work 6/1/2020 11/20/2020 $336,000 $336,000 Metro
5 Resurface Hwy 5 from 5th St in Green Isle to Hwy 212 7/10/2020 10/30/2020 $3,700,000 $3,500,000 7
5 Resurface Hwy 5 between I-494 and the south end of the Hwy 5 Mississippi River Bridge, repair 12 bridges on Hwy 5, repair ramps and install cable median barrier 4/15/2020 10/31/2020 $25,974,000 $25,974,000 Metro
6 Replace culvert on Hwy 6 at Little Too Much Lake near Talmoon 7/13/2020 9/28/2020 $653,000 $633,000 2
6 Resurface Hwy 6 between Talmoon and Itasca CR 136 7/13/2020 9/28/2020 $2,953,000 $2,833,000 2
6 Urban reconstruct on Hwy 6 and Hwy 2 in Deer River, replace culvert north of Deer River  5/18/2020 10/12/2020 $5,244,000 $5,124,000 2
7 Repair drainage and correct slope on Hwy 7 from east of Merrywood Dr in Minnetrista to east of Smithtown Rd, and at Hawks Pointe Ln in Victoria 9/8/2020 10/8/2020 $1,750,000 $1,750,000 Metro
8 Install fiber optic cables and cameras on Hwy 8 from I-35 in Forest Lake to Akerson St in Lindstrom 9/14/2020 6/1/2021 $1,035,000 $1,035,000 Metro
8 Construct roundabout at Hwy 8/CR 26/Pleasant Valley Rd 5/1/2020 8/31/2020 $2,928,000 $2,900,000 Metro
9 Districtwide shouldering, District 4 8/17/2020 12/18/2021 $500,000 $500,000 4
10 Repair road and bridges, and update accessibility (ADA) on Hwy 10 between the east ramp at Foley Blvd and Hwy 65 in Blaine, and on Hwy 47 from Anoka CR 10 to the east junction of Hwy 10 in Coon Rapids 9/14/2020 10/31/2020 $2,200,000 $2,169,000 Metro
10 Reconstruct Hwy 10 from 3rd St NW to 2nd St NE in Wadena; includes sidewalks, accesses, signals, railroad crossings and underground utility upgrades 5/15/2020 10/15/2020 $8,989,000 $4,345,000 3
10 Repair Hwy 10 pavement and reconstruct shoulder on EB lanes in Glyndon 7/13/2020 8/14/2020 $394,000 $394,000 4
10 Install signal and related safety improvements at Hwy 10/CR 54 and Hwy 10/Kris St in Detroit Lakes 7/6/2020 8/31/2020 $2,889,000 $2,700,000 4
11 Reconstruct Hwy 53 from Crescent Dr to 4th St, and Hwy 11 from Hwy 71 to Hwy 53 in International Falls  7/6/2020 7/1/2022 $14,125,000 $6,000,000 1
12 Resurface Hwy 12 from Zephyr Ave in Montrose to north of Bridge Ave in Delano 8/11/2020 11/21/2020 $3,338,000 $3,100,000 3
12 Resurface Reardon Ave SW to west of Sunset Ave. to 7th St. SE in Cokato, upgrade pedestrian accessibility 5/15/2020 8/15/2020 $3,615,000 $3,476,344 3
12 Reconstruct Hwy 12 in downtown Litchfield. 3/30/2020 8/1/2020 $10,981,000 $4,097,550 8
12 Realign Hwy 12 and reconstruct Hwy 40 including two new bridges to facilitate a railroad bypass on the west side of Willmar. 7/8/2019 11/30/2021 $33,980,000 $16,634,000 8
13 Replace Hwy 13 sign and panels between Silver Bell Rd in Eagan and Washburn Ave in Burnsville  4/15/2020 6/1/2020 $370,000 $370,000 Metro
13 Replace Hwy 13 tall overhead lighting at Hwy 77 in Eagan  4/1/2020 7/15/2020 $1,798,000 $1,797,000 Metro
14 Landscape along Hwy 14 Broadway St to Hwy 21 in New Ulm 4/1/2020 7/31/2020 $22,000 $21,000 7
14 Improve Hwy 14/W Central St intersection in Springfield 6/1/2020 9/1/2020 $500,000 $500,000 7
14 Install traffic management system equipment on Hwy 14 from I-35 to 0.6 miles east of Steele CR 43 6/1/2020 9/19/2020 $698,000 $500,000 6
14 Replace Hwy 14  box culvert in Chester, east of Rochester 5/5/2020 10/15/2020 $720,000 $610,000 6
14 Repair slopes and stabilize embankment areas at several locations on Hwy 59 and Hwy 14 in Redwood, Lyon and Murray counties. 7/1/2020 9/30/2020 $910,900 $910,900 8
14 Construct new 4-lane, 13-mile alignment of Hwy 14  from Steele CR 43 to Hwy 56 north in Dodge County 10/21/2019 8/1/2022 $105,956,000 $45,023,000 6
15 Repair drainage on Hwy 15 from Cottonwood Street to 5th North St in New Ulm 6/15/2020 9/30/2020 $93,000 $89,000 7
15 Reconstruct Hwy 15 through downtown Hutchinson. Resurface Hwy 15 from CR 115 to 5th Ave SE, upgrade sidewalks and ramps, replace signal at Hwy 15 & S Grade Rd. 4/13/2020 11/1/2020 $11,585,000 $11,585,000 8
18 Replace Hwy 18 bridge over Portage Creek with box culvert west of Hwy 6 7/1/2020 10/16/2020 $778,000 $750,000 3
19 Repair slope and stabilize embankment on Hwy 19 east of Morton.  4/1/2020 4/30/2020 $800,000 $800,000 8
19 Resurface Hwy 19 and Hwy 59 in the Marshall area. 7/1/2020 11/1/2020 $2,500,000 $2,500,000 8
19 Reconstruct Hwy 19 in New Prague from Hwy 21 to 7th Ave SE; replace underground utilities, sidewalks, lighting and landscaping; resurface Hwy 19 from 5th Ave NW to Hwy 21  4/1/2020 11/1/2020 $11,909,000 $10,909,000 7
21 Replace Hwy 21 bridge over the rail line at Helena Blvd and over Union Pacific Railroad; reconstruct pavement; bike/ped trail; repair soil erosion; and construct drainage structure and storm sewer pipe in Jordan 3/2/2020 10/26/2020 $7,462,000 $7,433,000 Metro
22 Resurface 19 miles of Hwy 111/22 from Hwy 99 in Nicollet to 280th St in Gaylord; add turn lanes, new snow fence, rural intersection lighting; improve underground pipes and utilities 5/8/2020 10/3/2020 $14,616,000 $13,466,000 7
23 Construct 134th Ave W from Hwy 23 to 4th St in Duluth 8/17/2020 11/27/2020 $230,000 $230,000 1
23 Replace Hwy 23 bridge over  Nemadji River, 1.6 miles north of CR 8 in Carlton County 3/23/2020 6/1/2021 $3,101,000 $2,750,000 1
23 Replace Hwy 23 bridge at Deer Creek 9.5 miles northeast of the south Carlton County line 7/16/2019 10/30/2020 $4,048,000 $2,910,000 1
23 Resurface Hwy 23 from Cottonwood to Hwy 212/Hwy 23 in Granite Falls and construct left-turn lanes at the intersection of Hw 23/Lyon CR 9 and Hwy 23/Lyon CR 10. 5/4/2020 11/1/2020 $37,173,000 $37,173,294 8
24 Reconstruct Hwy 24 from Hwy 55 to Poplar Ave in Annandale, includes updates to pedestrian sidewalks and replace underground city utilities 4/15/2020 8/15/2020 $5,118,000 $4,982,000 3
25 Install overhead intersection lighting on Hwy 210 east of Brainerd on Crow Wing CR 12 and Hwy 25 in Monticello, Wright County 8/11/2020 9/24/2020 $130,000 $125,000 3
25 Resurface Hwy 25, add right turn lane, improve sidewalk accessibility, extend trail and repair drainage from 0.1 miles south of Carver CR 30 in Mayer to State St in Watertown 6/8/2020 9/7/2020 $6,080,000 $5,846,000 Metro
28 Replace bridge spanning stream 2.6 mi west of Hwy 71 near Sauk Centre 7/15/2020 8/15/2020 $898,000 $863,000 3
28 Resurface Hwy 28 from Chokio to Morris; replace 3 box culverts 7/6/2020 9/1/2020 $7,105,000 $6,640,000 4
28 Complete streets reconstruction on Hwy 28, Hwy 29, Hwy 114 in Starbuck, includes multi-use trail and pedestrian accessibility improvements 5/18/2020 10/17/2020 $8,132,000 $7,600,000 4
28 Replace Hwy 28 culvert in Browns Valley; local-led project TBD TBD $186,000 $186,000 4
29 Replace bridge over N Parkway Dr on Hwy 29 in Montevideo. 3/16/2020 11/1/2020 $1,574,163 $1,574,163 8
29 Complete streets reconstruction on Hwy 28, Hwy 29, Hwy 114 in Starbuck, includes multi-use trail and pedestrian accessibility improvements 5/18/2020 10/17/2020 $8,132,000 $7,600,000 4
30 Resurface Hwy 30 from Cottonwood CR 7 to Hwy 71 7/6/2020 10/6/2020 $5,630,000 $5,200,000 8
30 Resurface Hwy 30 from Hwy 22 to New Richland; replace 2 bridges 5/1/2020 10/2/2020 $9,970,000 $9,050,000 7
32 Resurface 7 miles of Hwy 32 between Thief River Falls and St. Hilaire. Replace culvert, make pedestrian improvements in St. Hilaire, construct roundabout at Hwy 32/Pennington CR 16/CR 8 south of Thief River Falls. 5/18/2020 10/1/2020 $4,189,000 $4,189,000 2
I 35 Early steel for signal system in advance of Lake Avenue bridge repair in Duluth 4/20/2020 11/27/2020 $47,000 $43,000 1
I 35 Early steel for bridge expansion joints in advance of Lake Avenue bridge repair in Duluth 4/20/2020 11/27/2020 $79,000 $73,000 1
I 35 Repair I-35 Carlton weigh station near Cloquet 3/9/2020 10/4/2020 $1,538,000 $1,466,000 1
I 35 Reconstruct Straight River Rest Area parking lot on southbound I-35  5/27/2019 10/30/2020 $2,131,000 $1,775,000 6
I 35 Reconstruct Heath Creek Rest Area parking lot on I-35 northbound 5/27/2019 10/30/2020 $2,838,000 $2,376,000 6
I 35 Resurface Lake Avenue bridge over I-35 in Duluth; ADA improvements 4/6/2020 11/27/2020 $3,112,000 $2,071,000 1
I 35 Repair I-35 concrete pavement and stormwater drainage from Chisago CR 9 to Chisago/Pine County line 4/15/2019 9/1/2020 $22,452,000 $9,209,000 Metro
I 35E Preserve landscaping on I-35E from north intersection of Wheelock Pkwy in Saint Paul to Little Canada Rd in Little Canada 7/1/2019 9/30/2020 $90,000 $90,000 Metro
I 35E Preserve landscaping on I-35E from University Ave to southern intersection of Wheelock Pkwy in Saint Paul 7/1/2019 6/30/2020 $90,000 $90,000 Metro
I 35E Preserve landscaping on I-35E from north intersection of Wheelock Pkwy in Saint Paul to Little Canada Rd in Little Canada  1/1/2020 9/30/2021 $90,000 $90,000 Metro
I 35E Preserve landscaping  on I-35E from University Ave to the southern intersection of Wheelock Pkwy in Saint Paul 7/1/2020 6/30/2021 $90,000 $90,000 Metro
I 35E Install new temporary signals at the I-35E/CR J ramp in Lino Lakes 7/15/2020 9/30/2020 $300,000 $300,000 Metro
I 35E Install I-35E cable median barrier from Anoka CR J in Lino Lakes to I-35E/I-35W split in Columbus 4/13/2020 5/29/2020 $964,000 $964,000 Metro
I 35W Landscape on I-35W under 5th St pedestrian bridge in Mpls 9/15/2020 7/1/2023 $94,000 $54,000 Metro
I 35W Construct stormwater holding cavern system on northbound I-35W from 42nd St to 0.1 mile south of 40th St in Mpls 8/1/2019 7/1/2023 $65,688,000 $20,000,000 Metro
I 35W Replace I-35W bridge over Minnesota River from Black Dog Rd in Burnsville to 106th St in Bloomington 6/13/2018 9/15/2021 $115,160,000 $26,344,000 Metro
I 35W Replace pavement and construct MnPASS Express Lanes—one lane in each direction—in the middle of existing I-35W; repair 17 bridges and replace 5 bridges between CR C in Roseville and CR 17/Lexington Ave. in Blaine. 4/1/2019 9/2/2021 $200,675,000 $109,000,000 Metro
I 35W Construct MnPASS lane; reconstruct road; build transit station, noise and retaining walls and repair or replace bridges on I-35W from 43rd St. to I-94 in Minneapolis and on I-94 from First Ave to Park Ave; Hwy 65 from 24th St. to 15th St. 8/7/2017 10/22/2021 $243,829,844 $50,000,000 Metro
I 35W Repair I-35W pavement and drainage from 0.1 mile north of 76th St to 66th St in Richfield 5/4/2020 6/5/2020 $959,000 $959,000 Metro
36 Replace signals at Hwy 36/Ramsey CR 65 north and south ramps in Maplewood 5/4/2020 7/11/2020 $511,000 $512,000 Metro
37 Resurface Hwy 37 from Hwy 53 to Hwy 135 through Gilbert 7/13/2020 10/29/2021 $6,560,000 $4,500,000 1
40 Replace bridge on Hwy 40 (known as Milan bridge) over Lac qui Parle Lake west of Milan. 5/13/2019 7/1/2020 $7,768,000 $4,044,833 8
42 Repave Hwy 42 from Hwy 247 in Plainview to Hwy 61 near Kellogg 7/13/2020 10/5/2020 $4,614,000 $4,284,000 6
47 Reconstruct 22 miles of Hwy 47, improve road access and update drainage between Hwy 27/47 in Isle and Hwy 23 in Ogilvie. Replace two bridges near Ann Lake. 7/15/2020 11/15/2020 $15,338,000 $14,713,975 3
52 Repair and protect Hwy 52 bridge pier foundations in Oronoco  7/6/2020 10/1/2020 $330,000 $250,000 6
53 Hwy 53 in International Falls. Early steel for signal and light poles in advance of project 3608-48 8/15/2020 11/15/2020 $114,000 $104,200 1
53 Install Hwy 53 signal light/ADA improvements in City of Virginia 6/1/2020 11/27/2020 $162,000 $141,000 1
53 Install intersection improvements on Hwy 53 at Hwy 1 and CR 115/Ashawa Road near Cook 7/13/2020 9/17/2021 $1,482,000 $1,000,000 1
53 Install Hwy 53 signal light/ADA improvements in City of Virginia 7/6/2020 10/30/2020 $2,284,000 $1,650,000 1
55 Repair Hwy 55 bridge over railroad and Luce Line Trl in Plymouth 4/20/2020 5/22/2020 $649,000 $649,000 Metro
55 Replace Hwy 55 bridge over the Pomme de Terre River near Barrett 6/1/2020 8/7/2020 $1,500,000 $1,500,000 4
56 Repave 7.5 miles of Hwy 56 from Leroy to Taopi 9/7/2020 10/31/2020 $1,709,000 $1,589,000 6
57 Construct Hwy 57/Hwy 60 roundabout in Wanamingo 5/4/2020 7/17/2020 $1,933,000 $1,750,000 6
59 Replace two culverts near Newfolden 7/20/2020 9/25/2020 $1,499,000 $1,449,000 2
61 Reconfigure Hwy 61 median at Sugar Loaf View near Fleet Farm in Winona 5/4/2020 6/12/2020 $320,000 $370,000 6
61 Install high tension cable median barrier on Hwy 61 at various locations from 0.51 miles east of Hwy 316 to 0.23 miles east of Aspen Ave in Red Wing 9/14/2020 10/25/2020 $959,000 $1,130,000 6
61 Repair Hwy 61 Reads Landing overlook, and Lake City concourse  5/15/2020 10/27/2020 $1,252,000 $1,252,000 6
61 Reconstruct Hwy 61 in Lake City from W Elm St to Lakeshore Drive 4/3/2020 10/16/2020 $14,994,000 $14,594,000 6
61 Resurface Hwy 61 from Reservation Bay Rd near Grand Portage to Hwy/Canadian border 7/13/2020 10/1/2021 $16,100,000 $4,500,000 1
61 Resurface and reconstruct 11 miles of Hwy 61 from 1.8 miles north of Cutface Creek to 0.1 miles south of CR 14; replace the box culvert at Fall River in Grand Marais. 12/2/2019 10/29/2021 $20,970,000 $18,691,000 1
63 Replace Red Wing Bridge on Hwy 63 (final year of multi-year project) 5/5/2017 8/20/2020 $66,200,000 $1,002,000 6
65 Repair Hwy 65/3rd Ave bridge over Mississippi River in Mpls 5/4/2020 6/30/2023 $131,014,000 $15,000,000 Metro
68 Repair Hwy 68 slope and culvert near CR 24 3/2/2020 9/1/2020 $850,000 $790,000 7
71 Install truck routes signs on Hwy 71 and Hwy 34 in Park Rapids; install lighting on Hwy 71 at Hubbard CR 28 and RDO plant entrance 5/29/2020 6/30/2020 $35,000 $35,000 2
71 Install gates on BNSF Railroad crossing at Hwy 71/Jefferson St in Wadena 8/11/2019 2/11/2020 $312,000 $300,000 3
71 Replace bridge over Long Prairie River in Long Prairie and resurface 1 mile of Hwy 71 from 2nd Ave to Hope Drive 4/15/2020 6/15/2020 $2,041,000 $1,965,000 3
71 Resurface Hwy 71 from Hwy 60 in Windom to Hwy 30 4/1/2020 10/30/2020 $2,755,000 $2,425,000 7
71 Resurface Hwy 71 from Jackson to Hwy 60 in Windom; replace box culvert at Jackson CR 38 5/4/2020 8/7/2020 $8,857,000 $8,097,000 7
72 Resurface 14 miles of rural Hwy 72 between Lake of the Woods CR 1 and south of the Beltrami County line 5/1/2020 6/12/2020 $2,355,000 $2,275,000 2
72 Replace three culverts on Hwy 72 between Blackduck and Kelliher 8/3/2020 10/30/2020 $2,797,000 $2,677,000 2
72 Replace Hwy 72 International Bridge over Rainy River in Baudette 5/1/2018 9/30/2020 $41,200,000 $15,520,000 2
73 Replace railroad bridge near on Hwy 73, south of Hibbing  Spring 2020 11/30/2020 $1,589,000 $1,590,000 1
74 Realign Hwy 74/CR 26 intersection and resurface CR 26 in Weaver. Project led by Wabasha County. Spring 2020 11/30/2020 $525,000 $525,000 6
74 Replace Hwy 74 bridge over Beaver Creek  north of Winona CR 30 3/9/2020 9/4/2020 $656,000 $500,000 6
75 Replace bridge over Pipestone Creek on Hwy 75 in Pipestone. 6/15/2020 11/1/2020 $1,613,880 $1,613,880 8
75 Replace Hwy 75 bridge over the Mustinka River; resurface from 5th Street in Wheaton to the Mustinka River Bridge 6/15/2020 9/5/2020 $2,568,000 $2,400,000 4
75 Resurface Hwy 75 from north of Hwy 212 to Hwy 7. Upgrade sidewalks and ramps, replace culvert liners, pave shoulders and replace guardrails. The road will  not be resurfaced in Madison. 8/1/2020 Fall 2021 $8,340,000 $8,340,000 8
I 90 Install high tension cable median barrier on I-90 from west of Olmsted CR 10 to east of Hwy 74 9/14/2020 10/20/2020 $685,000 $685,000 6
I 90 Reconstruct and expand Hayward Rest Area parking lot on I-90 eastbound 5/27/2019 10/30/2020 $2,152,000 $1,804,000 6
I 90 Replace rest area on WB I-90 (Des Moines) near Jackson 8/5/2020 11/26/2020 $4,496,000 $4,323,000 6
I 90 Replace rest area on EB I-90 (Clear Lake) near Jackson 8/6/2020 11/29/2020 $4,870,000 $4,684,000 6
I 90 Replace I-90 bridge at Winona CR 12 near Nodine and eastbound I-90 bridge over Dakota Valley Rd west of Dakota 5/15/2020 10/15/2020 $7,130,000 $6,600,000 6
I 90 Repave 10 miles eastbound I-90 from Freeborn CR 46 near Petran to Hwy 105 near Austin 5/4/2020 9/20/2020 $14,800,000 $19,302,000 6
I 90 Replace Hwy 63 bridges over I-90, construct new westbound I-90 off-ramp to southbound Hwy 63, reconstruct I-90 westbound off-ramp to northbound Hwy 63, close current access to Hwy 30, install cable median barrier 3/11/2020 9/11/2020 $16,820,000 $14,338,000 6
I 90 Resurface I-90 from Fairmont to Blue Earth; repair bridges, improve drainage and add interchange lighting 3/11/2019 10/19/2020 $41,841,000 $20,362,000 7
91 Resurface 15 miles of Hwy 91 from the south Adrian city limits to the Noles/Murray County line; improve pedestrian crossings in Adrian, add turn lanes, new rural intersection lighting; improve underground pipes and utilities 5/15/2019 7/24/2020 $9,933,000 $2,650,000 7
91 Resurface Hwy 91 from the Murray/Nobles county line to Russell, replace bridges and repair culverts along project route. Replace bridge over ditch and upgrade sidewalks in Lake Wilson. 7/15/2019 10/7/2020 $18,451,694 $6,100,000 8
 I 94 Reconstruct I-94/494/694 interchange, bridge and ramp in Washington County 12/10/2018 11/30/2020 $30,412,000 $12,241,000 Metro
I 94 Reconstruct ADA bike trail on I-94 at Maple Grove Pkwy and CR 30 in Maple Grove 5/4/2020 6/12/2020 $146,000 $73,000 Metro
I 94 Landscape I-94 from Nicollet Ave in Mpls to Shingle Creek Pkwy in Brooklyn Center 7/27/2020 1/27/2021 $188,000 $188,000 Metro
I 94 Interchange safety revisions on I-94 at Hwy 23 Interchange south of Waite Park 8/15/2019 10/15/2020 $2,103,000 $371,000 3
I 94 Repair 3  I-94 bridges on at the entrance and exit ramps over LRT, 17th Ave south and at Hiawatha bicycle trail in Mpls 4/15/2020 8/1/2020 $2,265,000 $2,200,000 Metro
I 94 Resurface I-94, update traffic management system; ADA and striping from Nicollet Ave in Mpls to Hwy 280 in Saint Paul 7/15/2020 9/15/2020 $4,657,000 $3,908,000 Metro
I 94 Reconstruct I-94/Ramsey CR 53 interchange bridge and approach sections, repave, construct sidewalks, shoulders, and travel lanes, replace MnDOT bridge from .01 miles south of Iglehart Ave to University Ave in Saint Paul 10/15/2019 11/30/2020 01/26/2019 $12,650,000 $12,650,000 Metro
I 94 Install signals for new Dayton Pkwy crossing at I-94 between Brockton Lane and CR 81 in Dayton 5/4/2020 10/31/2021 $21,100,000 $5,000,000 Metro
I 94 Reconstruct I-94 and add lane (EB & WB) from Wright CR 19 in Albertville to the Crow River bridge in St Michael. Replace bridges over Wright CR 19; Hwy 241 6/1/2019 11/1/2021 $66,165,000 $47,495,000 3
I 94 Reconstruct 14 miles of I-94 from west of Hwy 25 in Monticello to Hwy 24 in Clearwater; add lanes, new pavement,  noise wall in Monticello, improve drainage 8/1/2019 11/1/2021 $106,418,000 $63,000,000 3
I 94 Reconstruct eastbound and westbound lanes of I-94 between Fish Lake Rd in Maple Grove and Hwy 101 in Rogers; add lane in both directions between Hwy 610 and Hwy 101, reconstruct rest area parking lot, add digital signage, add 10  truck parking spaces at rest area. 12/2/2019 11/1/2021 $125,858,000 $54,039,000 Metro
I 94 Install snow fence along I-94 and Hwy 34 TBD TBD $1,159,000 $1,158,794 4
95 Resurface Hwy 95, improve sidewalk access and repair drainage from 0.2 miles north of Bayport to 0.1 mile south of I-94 in Lakeland 5/4/2020 10/17/2020 $6,408,000 $6,408,000 Metro
95 Construct  Hwy 95 turn lanes, widen shoulders and resurface from 70th St to Hwy 61 in Cottage Grove 6/10/2019 10/1/2020 $8,939,000 $5,821,000 Metro
97 Repair/replace Hwy 97 drainage infrastructure; construct east and west left turn lane and install lighting at North Shore Trl/Keswick Ave in Forest Lake 4/27/2020 7/7/2020 $1,220,000 $1,173,000 Metro
99 Install left turn lanes on Hwy 99 in LeCenter at Justice Center and East Commerce Drive 6/15/2020 8/21/2020 $200,000 $200,000 7
100 Install fiber optic and modify cabinets at 6 intersections on Hwy 100 4/6/2020 6/3/2020 $148,000 $148,000 Metro
114 Complete streets reconstruction on Hwy 28, Hwy 29, Hwy 114 in Starbuck, includes multi-use trail and pedestrian accessibility improvements 5/18/2020 10/17/2020 $8,132,000 $7,600,000 4
123 Upgrade BNSF railroad crossing on Hwy 123 7/1/2019 12/31/2019 $163,000 $163,000 1
123 Upgrade existing signal system at BNSF railroad crossing on Hwy 123 near Sandstone  8/11/2019 2/11/2020 $188,000 $170,000 1
135 Reconstruct Hwy 135 from CR 715 to Hwy 4 in Biwabik 5/26/2020 9/30/2021 $7,085,000 $2,750,000 1
149 Landscape on Hwy 149 from I-494 to Hwy 5  10/1/2019 6/1/2021 $143,000 $130,000 Metro
169 Landscape along Hwy 169 from Bren Rd to 7th St in Hopkins 4/7/2020 7/15/2020 $100,000 $100,000 Metro
169 Install concrete barrier on Rockford Rd bridge over Hwy 169 in Plymouth 4/20/2020 5/29/2020 $100,000 $100,000 Metro
169 Install left-turn lane at Hwy 169/Hwy 65 intersection in Nashwauk 7/6/2020 9/15/2020 $480,000 $437,000 1
169 Construct 3 reduced conflict intersections on Hwy 169 at Mille Lacs CR 11, CR 12, CR 13 3/13/2020 9/13/2020 $3,577,000 $3,464,000 3
169 Resurface 13 miles of Hwy 169 from Hwy 53 eastward to CR 26; bridge repair  7/13/2020 10/30/2020 $4,429,000 $4,036,000 1
169 Construct folded diamond interchange at Hwy 169/101st Ave, and auxiliary lanes between 101st Ave. and Hwy 610 in Brooklyn Park 4/15/2020 11/25/2020 $13,140,000 $13,139,434 Metro
169 Construct Hwy 169 interchange, 3 bridges and landscape at Chestnut Blvd/Scott CR 78 in Jackson Township 9/1/2018 11/20/2020 $45,500,000 $5,000,000 Metro
172 Resurface Hwy 172 and replace two culverts between Baudette and Wheeler's Point 8/3/2020 10/30/2020 $4,801,000 $4,681,000 2
194 Resurface portions of Hwy 194 in Duluth in advance of Twin Ports Interchange construction 5/4/2020 10/16/2020 $655,000 $600,000 1
200 Historic restoration at roadside parking area in Whipholt 6/8/2020 9/7/2020 $450,000 $450,000 2
200 Reconstruct and raise grade on Hwy 200 east of Laporte, and install new culvert 6/15/2020 9/30/2020 $1,740,000 $1,690,000 2
210 Install overhead intersection lighting on Hwy 210 east of Brainerd on Crow Wing CR 12 and Hwy 25 in Monticello, Wright County 8/11/2020 9/24/2020 $130,000 $125,000 3
210 Repair Hwy 210 culvert  just west of I-94 near Fergus Falls 3/30/2020 5/15/2020 $500,000 $500,000 4
210 Reconstruct Hwy 210 from west of I-94 near Fergus Falls to the Otter Tail/Wilkin County line 5/26/2020 10/2/2020 $14,766,000 $13,800,000 4
212 Replace Hwy 212 signals, extend turn lanes, close access at Morse St, improve ADA and add a pedestrian underpass from Hwy 25 in Norwood Young America to CR 34 in Carver 6/22/2020 6/1/2021 $16,073,236 $15,518,000 Metro
220 Replace bridges on Hwy 220 over the Snake and Tamarac Rivers between Hwy 317 and Hwy 11 6/3/2019 7/24/2020 $3,522,000 $3,362,000 2
246 Install roundabout at Hwy 246/Jefferson Pkwy intersection in Northfield. Project led by city of Northfield. 5/1/2020 10/31/2020 $483,480 $483,480 6
251 Repave 16 miles of Hwy 251 from I-35 in Freeborn County to Hwy 218 in Mower County 5/4/2020 10/30/2020 $6,474,000 $6,500,000 6
280 Replace Hwy 280 lighting from Energy Park Dr in Saint Paul to 0.2 miles north of Como Ave in Lauderdale 8/3/2020 10/17/2020 $323,000 $310,000 Metro
313 Resurface Hwy 313 between Warroad and the Canadian Border 9/8/2020 10/2/2020 $2,180,000 $2,060,000 2
 I 494 Reconstruct I-94/494/694 interchange, bridge and ramp in Washington County 12/10/2018 11/30/2020 $30,412,000 $12,241,000 Metro
I 494 Install accesible pedestrian signal, sidewalk ramps, build sidewalk and concrete repair in Bloomington at I-494 and France Ave 6/8/2020 7/31/2020 $267,000 $240,000 Metro
I 494 Resurface I-494, repair drainage, add and upgrade guardrail from 0.1 miles east of 5th Ave in Saint Paul to I-35E in Mendota Heights 7/8/2019 11/13/2020 $32,314,000 $16,343,000 Metro
610 Replace signs on Hwy 610 from Hwy 169 in Brooklyn Park to Hwy 10 in Coon Rapids 7/13/2020 9/11/2020 $350,000 $350,000 Metro
 I 694 Reconstruct I-94/494/694 interchange, bridge and ramp in Washington County 12/10/2018 11/30/2020 $30,412,000 $12,241,000 Metro
Various Install intersection lighting on Hwy 13 at 3 county roads in Waseca County 10/26/2020 12/31/2020 $87,000 $80,000 7
Various Safety signal upgrades District 1 10/1/2019 6/30/2020 $96,000 $15,000 1
Various Perform bridge preventive maintenance at various locations. 5/1/2020 11/1/2020 $125,000 $125,000 8
Various Seal Coat - various locations District 6 5/1/2020 8/7/2020 $188,000 $188,000 6
Various Improve intersection signing and lighting on 17 intersections districtwide 10/26/2020 12/31/2020 $240,000 $240,000 7
Various Resurface Hwys districtwide 7/1/2020 10/1/2020 $500,000 $500,000 7
Various Replace traffic signs on Hwys districtwide 4/1/2020 8/1/2020 $518,000 $518,000 7
Various Districtwide pavement striping, District 6 5/15/2020 12/18/2021 $520,000 $500,000 6
Various Districtwide culvert improvements, District 4 8/30/2020 2/28/2021 $823,000 $732,676 4
Various Replace signs throughout the district. 7/1/2020 11/1/2020 $1,100,000 $1,100,000 8
Various Districtwide concrete pavement repair, Metro District 4/6/2020 10/1/2021 $1,451,000 $550,000 Metro
Various Pavement rehabilitation District 1 9/2/2019 12/31/2021 $1,507,000 $1,359,000 1
Various Drainage improvements at various Hwy locations District 1 3/2/2019 11/30/2020 $1,720,000 $422,000 1

Location Description Cost Dates
Crookston Renovate interior of main transit facility by enclosing office suites, additional restroom, repair misc exterior steel siding $77,500
(MnDOT share $62,000)
May - Dec 2020
Duluth Install air exchangers, resurface garage roof $2,080,000
(MnDOT share $1,250,000)
May 2019 – Dec 2020
Fairmont Renovate interior of Martin/Faribault County Transit Board building with additional offices $270,000
(MnDOT share $216,000
August 2019 - Dec 2020
Gilbert Install new garage drain grates, repave parking lot $216,600
(MnDOT share $173,280)
January 20 - June 2021
Hermantown Purchase and repair leased transit facility $1,040,000
(MnDOT share $208,500)
May 2019 - Dec 2020
Hermantown Install portable bus wash, garage floor drain repair $33,500
(MnDOT share $26,800)
August 2019 - Dec 2020
Little Falls Construct operation/storage facility $1,080,000
(MnDOT share $864,000)
August 2019 - Dec 2021
Milaca Repair parking lot, insulation facility $31,000
(MnDOT share $24,800)
January 2020 - June 2021
Rochester Install custom engineered system for existing bus wash bay, capable of washing all transit fleet vehicles  $370,000
(MnDOT share $296,000)
May 2019 - Dec 2020
Sandstone Install portable bus wash, roof repair, parking lot pavement $118,500
(MnDOT share $94,800)
January 20 - June 2021
Sleepy Eye Construct bus storage garage addition to existing county facility $108,700
(MnDOT share $86,960)
January 2019 - June 2021
Waite Park Replace operating facility septic service $20,000
(MnDOT share $16,000)
January 2020 - June 2021
Winona Install transit shelters with signage $242,200
(MnDOT share $193,760)
May 2019 - Dec 2020

Location Description Cost Dates
Baudette International Airport Reconstruct South 4300 feet of Runway 12/30 $6,000,000 2020
Cloquet-Carlton County Airport Runway Rehabilitation $1,300,000 2020
Detroit Lakes Municipal Airport Runway Extension $11,400,000 2020-2021
Duluth Sky Harbor Airport Runway Relocation $3,300,000 2020
Eveleth-Virginia Municipal Airport Apron Rehabilitation $1,100,000 2020
Lake Elmo Airport Relocate Runway 14/32 $4,300,000 2020
Moorhead Municipal Airport Runway Rehabilitation $1,600,000 2020
Princeton Municipal Airport Runway Reconstruction $1,600,000 2020
Rochester International Airport Jet Boarding Bridge  $2,500,000 2020
Winsted Municipal Airport Reconstruct Runway 9/27  $2,000,000 2020

Location Description 2020 spend Project Total Dates
Duluth Seaway Port Authority Seaway Office Building $3,000,000 $3,000,000 2020-2021
Red Wing Port Authority Passenger Dock $667,730 $3,068,718 2019-2020
Saint Paul Port Authority Direct Barge-Rail-Truck Transload Facility $1,500,000 $2,598,321 2020-2021
Saint Paul Port Authority Barge Terminal #1 Receiving System $1,000,000 $3,240,000 2020-2021
Saint Paul Port Authority Barge Terminal #1 Fender Replacement $286,450 $286,450 2020
Winona Port Authority 998 Riverview Drive Dock Rehab $200,000 $626,550 2020-2021
Winona Port Authority Stormwater Upgrades $747,900 $747,900 2020

Location Description Project Cost Dates
Askov Replace existing signal system with new gates, flashing lights and constant warning circuitry $185,958
(MnDOT share $92,979)
July 1, 2019 - June 30, 2020
Barnesville Replace existing signal system with new gates, flashing lights and constant warning circuitry $220,916 July 1, 2019 - June 30, 2020
Baxter Replace existing signal system with new gates, flashing lights and constant warning circuitry $400,000
(MnDOT share $320,000)
July 1, 2019 - June 30, 2020
Bloomington Replace existing signal system with new gates, flashing lights and constant warning circuitry $270,465 July 1, 2019 - June 30, 2020
Brooten Install flashing lights and gates and constant warning circuitry $242,187 July 1, 2019 - June 30, 2020
Cambridge Install flashing lights and gates and constant warning circuitry $232,217 July 1, 2019 - June 30, 2020
Cass Lake Replace existing signal system with new gates, flashing lights and constant warning circuitry $220,945
(MnDOT share $220,945)
July 1, 2019 - June 30, 2020
Cotton Install flashing lights and gates and constant warning circuitry $315,511 July 1, 2019 - June 30, 2020
Essig Install flashing lights and gates and constant warning circuitry $238,307 July 1, 2019 - June 30, 2020
Florence Install flashing lights and gates and constant warning circuitry $396,188 July 1, 2019 - June 30, 2020
Forada Install flashing lights and gates and constant warning circuitry $238,400 July 1, 2019 - June 30, 2020
Granite Falls Install flashing lights and gates and constant warning circuitry $186,163 July 1, 2019 - June 30, 2020
Grasston Replace existing signal system with new gates, flashing lights and constant warning circuitry $344,410
(MnDOT share $172,205)
July 1, 2019 - June 30, 2020
Henning Install flashing lights and gates and constant warning circuitry $237,172 July 1, 2019 - June 30, 2020
Janesville Install flashing lights and gates and constant warning circuitry $234,756 July 1, 2019 - June 30, 2020
Lake City Replace existing signal system with new gates, flashing lights and constant warning circuitry $298,374 July 1, 2019 - June 30, 2020
Lewiston Replace existing signal system with new gates, flashing lights and constant warning circuitry $240,000 July 1, 2019 - June 30, 2020
Miltona Install flashing lights and gates and constant warning circuitry $240,335 July 1, 2019 - June 30, 2020
Murdock Install flashing lights and gates and constant warning circuitry $230,000
(MnDOT share $23,000)
July 1, 2019 - June 30, 2020
New Ulm Install flashing lights and gates and constant warning circuitry $234,282 July 1, 2019 - June 30, 2020
Proctor Replace existing signal system with new gates, flashing lights and constant warning circuitry $357,717 July 1, 2019 - June 30, 2020
Renville Replace existing signal system with new gates, flashing lights and constant warning circuitry $214,995 July 1, 2019 - June 30, 2020
Roseville Replace existing signal system with new gates, flashing lights and constant warning circuitry $240,000 July 1, 2019 - June 30, 2020
Saint Paul Replace existing signal system with new gates, flashing lights and constant warning circuitry $269,484 July 1, 2019 - June 30, 2020
Sleepy Eye Install flashing lights and gates and constant warning circuitry $234,125 July 1, 2019 - June 30, 2020
Stanchfield Replace existing signal system with new gates, flashing lights and constant warning circuitry $223,581 July 1, 2019 - June 30, 2020
Verndale Replace existing signal system with new gates, flashing lights and constant warning circuitry $300,000 July 1, 2019 - June 30, 2020
Verndale Replace existing signal system with new gates, flashing lights and constant warning circuitry $320,000 July 1, 2019 - June 30, 2020
Wadena Replace existing signal system with new gates, flashing lights and constant warning circuitry and preemption $652,041
(MnDOT share $647,041)
July 1, 2019 - June 30, 2020
Wadena Install flashing lights and gates and constant warning circuitry $362,746
(MnDOT share $362,041)
July 1, 2019 - June 30, 2020
Wadena Replace existing signal system with new gates, flashing lights and constant warning circuitry $629,730
(MnDOT share $314,865)
July 1, 2019 - June 30, 2020
Waite Park Replace existing signal system with new gates, flashing lights and constant warning circuitry $269,017 July 1, 2019 - June 30, 2020
Warroad Replace existing signal system with new gates, flashing lights and constant warning circuitry $314,140 July 1, 2019 - June 30, 2020
Waseca Replace existing signal system with new gates, flashing lights and constant warning circuitry $295,421 July 1, 2019 - June 30, 2020
Winona Replace existing signal system with new gates, flashing lights and constant warning circuitry $350,983 July 1, 2019 - June 30, 2020
Winona Replace existing signal system with new gates, flashing lights and constant warning circuitry $442,048 July 1, 2019 - June 30, 2020