The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2020

Score Route  Community Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
86 US 169 St Peter Reconstruction from Minnesota Ave frontage road to Jefferson Ave in Saint Peter $1,500,000 2023 Pavement will be addressed as part of intersection improvement at Hwys 22, 169, and 99 on south side of St Peter
85 MN 13 Waseca Reconstruction from 5th St in Waseca to the railroad crossing $3,100,000 Not Selected Monitoring pavement performance; Will require local coordination
84 US 75 Luverne Thick mill and overlay from I-90 to Veterans Drive in Luverne $8,000,000 2025  
82 MN 270 Hills Medium mill and overlay from Railroad overpass to Lincoln County Road 6 in Hills $2,000,000 2030 Part of the Hwy 270 project
81 US 169 Elmore Medium mill and overlay from Jay St to Poulton St in Elmore $1,700,000 2022 Part of the Hwy 169 project from Iowa to Blue Earth
80 MN 15 Fairmont Medium mill and overlay from School St to E 4th St in Fairmont $2,600,000 Not Selected Monitoring performance of recent project
80 US 59 Worthington Reconstruction from 1st St to south of I-90 in Worthington $14,300,000 2027 Coordinating with the City of Worthington on planned reconstruction 
78 MN 19 Gaylord Thick mill and overlay from Spring St to 90 ft NE of Spring St in Gaylord $100,000 2028 Very small segment that will be included with the Hwy 19 from Hwy 15 to Gaylord project
78 MN 19 Winthrop Thick mill and overlay from Brown St to Pleasant Ave in Winthrop $2,500,000 2028 Part of the Hwy 19 from Hwy 15 to Gaylord project
78 MN 22 Wells Reconstruction from 10th St to Hwy 109 in Wells $8,000,000 2026 Coordinating with Wells to I-90 project
76 MN 22 Kiester Medium mill and overlay from Front St to Center St in Kiester $2,500,000 2027 Part of the Hwy 22 project from Iowa to I-90
75 MN 22 Mankato Reconstruction from 120 ft south of Basset Dr to 585 ft north of Basset Dr in Mankato $2,000,000 2030 Small segment that will be part of Hwy 22 project between Hwy 83 and Madison Avenue in Mankato
75 MN 60 Windom Major resurfacing from 6th St to Hwy 71 intersection in Windom $8,500,000 Not Selected Corridor study underway. City monitoring pavement performance. 
73 MN 13 Waseca Reclaim and overlay from 4th Ave NE to northern Waseca City limits $700,000 Not Selected Waiting to coordinate with another project
71 MN 30 Amboy Medium mill and overlay from Stevens St to 4th St in Amboy $400,000 Not Selected Waiting to coordinate with another project
71 MN 99 Le Center Reconstruction from Maple Ave to Cordova Ave in LeCenter $1,600,000 2029 Part of the Hwy 99 project that extends to Hwy 13
71 MN 264 Round Lake Medium mill and overlay from 2nd Ave to north end of Main st in Round Lake $1,900,000 2030 Part of the Hwy 264 project
68 MN 5 Arlington Medium mill and overlay from Baker St to Sheila Dr/2nd ave NW intersection in Arlington $200,000 Not Selected Will be part of a future Hwy 5 project
67 MN 13 Waseca Reconstruction from railroad crossing ro 4th Ave NE in Waseca $1,000,000 Not Selected  
66 MN 91 Ellsworth Medium mill and overlay from 7th Ave to North ave in Ellsworth $300,000 Not Selected Waiting to coordinate with a future Hwy 91 project
66 US 169 St Peter Reconstruction from Chestnut St to Ramsey st in St. Peter $3,500,000 2025 Selected due to extensive pavement deterioration
66 MN 4 Sherburn Medium mill and overlay from Front Street (CR26) to 5th Street in Sherburn $1,500,000 2024 Completing as part of Hwy 4 project north to St James
65 MN 109 Winnebago Medium mill and overlay from Hwy 169 to 4th St in Winnebago $100,000 Not Selected Will be part of a future Hwy 109 project
64 MN 22 New Auburn Thick mill and overlay from 1st St to 5th St in New Auburn $3,600,000 Not Selected Will be part of a future Hwy 22 project
63 MN 19 New Prague Medium mill and overlay from 7th Ave SE to east of the Alton Ave Roundabout in New Prague $200,000 2029 Part of Hwy 19 project from Hwy 169 to east junction of Hwy 13
62 MN 22 Minnesota Lake Medium overlay from 4th Ave to Main st in Minnesota Lake $3,200,000 2023 Part of Hwy 22 Wells to Mapleton project
62 US 71 Jackson Thick mill and overlay from Des Moins River Trail Crossing to Springfield Pkwy in Jackson $100,000 2028 Part of Hwy 71 project from Iowa to I-90
61 MN 263 Ceylon Reconstruction from Clark St to Railroad St in Ceylon $1,500,000 2022 Part of Hwy 263 project
60 MN 30 New Richland Medium mill and overlay from Elm Ave to Hwy 13 $200,000 Not Selected  
60 MN 99 Nicollet Medium mill and overlay from Heidemann Ave to Birch St in Nicollet $300,000 Not Selected  
60 MN 4 Trimont Medium overlay from Chestnut Street to Beech Street in Trimont $1,000,000 2024 Completing as part of Hwy 4 project north to St James
59 MN 15 New Ulm Thin mill and overlay from 20th St to Center St in New Ulm $1,100,000 Not Selected Waiting to coordinate with another project
58 MN 30 Darfur Medium mill and overlay from 2nd st through 1st St in Darfur $2,600,000 Not Selected  
58 US 169 Blue Earth Medium mill and overlay from 10th St to the north side of the Leland Pkwy roundabout in Blue Earth $400,000 Not Selected  
57 MN 60 Madison Lake Reconstruction from 7th St to 1st St in Madison Lake $2,000,000 2021 Reconstruction part of the Hwy 60 from Hwy 14 to Waterville project
56 US 169 Mankato Medium mill and overlay from Webster Ave to Hwy14 in Mankato and North Mankato $2,800,000 2027 Part of Hwy 169 project in Mankato and North Mankato
53 MN 19 New Prague Thick mill and overlay from 6th Ave to 4th Ave in New Prague $100,000 2029 Will be addressed as part of the Hwy 19 project that extends from Hwy 169 to the east junction of Hwy 13
52 MN 13 Montgomery Reconstruction from Milwaukee Ave to Welco Ave to Montgomery $4,200,000 2023 Drainage and saturation issues contributing to the rapid deterioration of the roadway
51 MN 62 Windom Thin mill and overlay from Plum Ave to Hwy 60 in Windom $200,000 Not Selected  
50 MN 60 Lake Crystal Reconstruction from Lilly St to Leclaire St in Lake Crystal $6,800,000 2024 Selected due to extensive pavement deterioration
50 MN 111 Nicollet Thin mill and overlay from Hillview St to 1st St in Nicollet $100,000 Not Selected  
49 MN 22 St Peter Medium mill and overlay from 3rd St to North Sunrise Dr in St Peter $1,000,000 2024 Part of Hwy 22 project between Hwy 169 and Hwy 111
48 MN 5 Gaylord Reconstruction from 1st St to Division St in Gaylord $500,000 Not Selected  
48 MN 60 Worthington Resurfacing from Nobles St to north of the Roundabout at I-90 $2,100,000 Not Selected  
47 MN 15 Truman Medium overlay from south 2nd St to north 2nd St in Truman $2,800,000 Not Selected  
46 US 59 Worthington Reconstruction from 1st to 440 ft to the east in Worthington $1,000,000 2027 Small segment part of larger Hwy 59 reconstruction project in Worthington
46 MN 4 Sleepy Eye Reconstruction from Ellsworth St to north of Allison Pkwy in Sleepy Eye $2,100,000 2027 Hwy 4 concrete repair on both sides of Hwy 14
45 MN 13 New Prague Major Reconstruction from 5th ave to Hwy 19 in New Prague $2,900,000 2029 Part of the Montgomery to Hwy 19 project
45 MN 86 Lakefield Reconstruction from 5th Ave to Funk Ave in Lakefield $3,500,000 2022 Partnering with the city as part of an extensive utility replacement project
43 MN 19 Gibbon Thick overlay from Ash Ave to Ely Ave in Gibbon $3,100,000 Not Selected  
42 US 14 Sleepy Eye Chip seal from 8th Ave to east of 7th Ave in Sleepy Eye  $150,000 Not Selected  
39 US 14 Springfield Medium mill and overlay from Mary Ave to Washington Ave in Springfield $500,000 2022 Selected prior to policy (in 2019-2022 STIP)
39 MN 15 New Ulm Reconstruction from Broadway Ave to German St in New Ulm $500,000 Not Selected  
35 MN 22 Mankato Minor resurfacing from north of Bassett Dr through the Adams St roundabout in Mankato $300,000 Not Selected  
33 MN 91 Adrian Major reconstruction from 4th St to Railroad Crossing in Adrian $200,000 Not Selected  
33 MN 91 Adrian Medium mill and overlay from Railroad Crossing to Pearl St in Adrian $200,000 Not Selected  
31 MN 93 Le Sueur Major reconstruction from Main st to west end of Minnesota River Bridge in LeSueur $100,000 Not Selected  
31 US 169 St Peter Minor resurfacing from Jefferson Ave to Chestnut St in St Peter $400,000 Not Selected  
30 MN 22 Mankato Reconstruction from north side of Adams St Roundabout to Hwy14 $4,800,000 Not Selected  
28 MN 4 St James Reconstruction from 9th Avenue S to 11th Avenue N in Saint James $300,000 Not Selected  
21 MN 22 Gaylord Thin mill and overlay from High Ave to Linden Ave in Gaylord $200,000 Not Selected  
20 MN 22/MN 5/MN 19 Gaylord Minor resurfacing on Hwy/22/5/19 in downtown Gaylord $100,000 Not Selected  
15 MN 22 Gaylord Minor resurfacing from Southview Dr to Commercial St in Gaylord $100,000 Not Selected  
9 MN 99 St Peter Resurfacing from Front St to west end of the Minnesota River Bridge in St Peter $250,000 Not Selected  