Non-National Highway System culverts
MnDOT District 7
How the projects scored in 2020
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2020
Total score | Bridge number | Route | Key Intersection or Closest Landmark | Work Type | Year planned | High Level cost estimate for planning purposes | Comments |
---|---|---|---|---|---|---|---|
65 | 91422 | MN 19 | Under 4th St near Winthrop | Replace | 2021 | $200,000 | Selected prior to policy (in 2019-2022 STIP) |
61 | 8851 | MN 19 | Sand Creek | Replace | 2029 | $300,000 | Selected prior to policy (in 2019-2028 CHIP) |
49 | 4596 | MN 99 | Middle Lake Outlet | Replace | 2021 | $100,000 | Selected prior to policy (in 2019-2022 STIP) |
16 | 8947 | MN 99 | East of Town Lane near LeCenter | Replace | 2027 | $100,000 | Selected prior to policy (in 2019-2028 CHIP) |
11 | 6341 | MN 22 | East Fork Blue Earth River | Replace | 2027 | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
3 | 8852 | MN 4 | Judicial Ditch #30 near Sleepy Eye | Replace | 2022 | $200,000 | Selected prior to policy (in 2019-2022 STIP) |
2 | 8567 | MN 4 | Cedar Run | Replace | 2021 | $200,000 | Selected prior to policy (in 2019-2022 STIP) |
1 | 8814 | MN 4 | Cottonwood River | Replace | 2022 | $200,000 | Selected prior to policy (in 2019-2022 STIP) |