The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2020

Score Route  Description High-Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
83 MN 114 Medium mill and overlay from Hwy 55 to I-94 $2,800,000 2026  
82 MN 27 Thin mill and overlay from E Third St to I-94 $3,100,000 Not selected Not a district priority. Will continue to monitor pavement performance
81 US 75 Medium mill and overlay from 46th Ave S to 30th Ave S $1,300,000 Not selected Not a district priority. Will continue to monitor pavement performance
81 MN 54 Reclaim and overlay from Hwy 27 to Hwy 55 $4,100,000 Not selected Turn Back to Grant County
79 MN 9 Medium mill and overlay from Hwy10 to Clay/Norman County Line $4,900,000 Not selected Not a district priority. Will continue to monitor pavement performance
79 MN 78 Thin mill and overlay from Otter Tail County Road 54 to Hwy 10 $1,400,000 Not selected Not a district priority. Will continue to monitor pavement performance
79 MN 114 Medium mill and overlay from 8th St in Starbuck to Hwy 55 $1,400,000 2024  
78 MN 108 Medium mill and overlay from Hwy 78 to 4th St $2,700,000 2024  
78 MN 113 Medium mill and overlay from Hwy 59 to Hwy 71 $10,100,000 2030  
77 US 75 Thin mill and overlay from 2nd Ave to Clay/Norman County line $3,300,000 Not selected Not a district priority. Will continue to monitor pavement performance
77 MN 104 Thin mill and overlay from Hwy 9 to 8th Ave SE $3,600,000 2025  
76 MN 78 Thin mill and overlay from I-94 to Hwy 210 in Battle Lake $3,600,000 Not selected Not a district priority. Will continue to monitor pavement performance
76 MN 113 Thick Mill and overlay from Norman/Mahnomen County line to Railroad crossing in Wabun $1,500,000 2023  
75 US 75 Medium mill and overlay from Hwy 210 to 220th St $3,500,000 Not selected Not a district priority. Will continue to monitor pavement performance
75 MN 27 Medium mill and overlay from I-94 to Douglas County Road 51/Douglas County Road 82 $600,000 2022  
75 MN 29 Medium mill and overlay from Chippewa River to Outlet Creek/Starbuck $5,100,000 Not selected Not a district priority. Will continue to monitor pavement performance
74 US 75 Medium overlay from County Road 12 to 46th Ave S $300,000 2027  
74 US 75 Medium mill and overlay from Hwy 27 in Wheaton to Railroad crossing north of Hwy 55 $3,600,000 2025  
73 US 75 Medium overlay from Railroad crossing north of Hwy 55 to Hwy 9 $2,100,000 2026  
73 MN 9 Medium mill and overlay from Hwy 210 to 6th St SW in Barnsville $6,400,000 2028  
73 MN 55 Reclaim and overlay from Hwy59 to Grant/Douglas County line $2,500,000 2021  
72 US 75 Medium overlay from Hwy 9 to 6th St in Breckenridge  $1,700,000 Not selected Not a district priority. Will continue to monitor pavement performance
72 US 75 Medium mill and overlay from Traverse County Road 11 (Dumont) to Hwy 27 in Wheaton $1,700,000 Not selected Not a district priority. Will continue to monitor pavement performance
72 MN 27 Medium mill and overlay from Hwy 75 to Grant County Road 11 $4,100,000 2027  
71 US 75 Thin mill and overlay from Hwy 7 to Hwy 12 $1,400,000 Not selected  
71 MN 9 Medium overlay from Chippewa River to Stevens County Road 22 $5,800,000 Not selected  
71 MN 55 Medium mill and overlay from Church St in Wendell to Hwy59 $1,300,000 Not selected  
69 MN 27 Medium mill and overlay from Grant County Road 11 to Hwy 55 $4,200,000 Not selected  
69 MN 108 Medium mill and overlay from Ann Lane in Pelican Rapids to Hwy 78 $5,700,000 2026 Selected prior to policy (in 2019-2028 CHIP)
68 MN 28 Medium overlay from 610th Ave (Chokio) to Lyndale Ave $2,200,000 2021 Selected prior to policy (in 2019-2022 STIP)
68 MN 29 Medium mill and overlay from Hwy 210 to Hwy 71 $3,500,000 Not selected  
66 MN 117 Medium mill and overlay from South Dakota/Minnesota State line to Hwy 27 $500,000 Not selected  
66 MN 200 Medium mill and overlay from Norman/Mahnomen County Line to Hwy59 $1,300,000 Not selected  
65 US 12 Reclaim and overlay from Hwy 75 to Hwy 59 $6,800,000 2021 Selected prior to policy (in 2019-2022 STIP)
64 US 75 Medium mill and overlay from Hwy 28 in Graceville to Traverse County Road 11 in Dumont $2,000,000 2022 Selected prior to policy (in 2019-2022 STIP)
64 US 75 Medium overlay from Lac Qui Parle/Big Stone County line to Hwy 7 $200,000 2021 Selected prior to policy (in 2019-2022 STIP)
64 MN 78 Thin mill and overlay from Summit St in Battle Lake to Wagon Trail $1,100,000 Not selected  
64 MN 55 Reclaim and overlay from North Dakota/Minnesota State line to Grant County Road 11 in Wendell  $6,200,000 2022  
63 MN 87 Reclaim and overlay from River Dr in Frazee to Becker/Wadena County Line $7,100,000 2021 Selected prior to policy (in 2019-2022 STIP)
61 MN 78 Reclaim and overlay from Wagon Trail to County Road 54 $4,000,000 Not selected  
60 US 75 Medium mill and overlay from 5th Ave in Wheaton to Mustinka River in Wheaton $200,000 2021 Selected prior to policy (in 2019-2022 STIP)
60 US 75 Medium mill and overlay from Clay County Road 12 entrance to Clay County Road 12 roundabout exit. $100,000 Not selected  
55 MN 27 Reclaim and overlay from Hwy 28 (Browns Valley) to Traverse County Road 6 $4,900,000 Not selected  
51 MN 329 Medium mill and overlay from Hwy59 to U of M Experiment Station $300,000 Not selected  
50 MN 32 Thin mill and overlay from Hwy 10 to Clay/Norman County line $3,200,000 Not selected  
45 MN 108 Thin mill and overlay from I-94 to 9th St NW in Pelican Rapids $1,500,000 2023 Selected prior to policy (in 2019-2022 STIP)
42 MN 28 Thin mill and overlay from South Dakota/Minnesota State line to Hwy 7 $1,600,000 Not selected  
36 MN 7 Reclaim and overlay from Big Stone County Road 53 to 1.6 miles south of Big Stone County Road 68 $4,700,000 Not selected  
13 US 75 Thin mill and overlay from Hwy 12 to Hwy 28 in  Graceville $3,100,000 2029 Selected prior to policy (in 2019-2028 CHIP)
5 MN 7 Thin mill and overlay from Hwy 28 in Beardsley to Big Stone County Road 53 $1,900,000 Not selected  
3 MN 7 Thin mill and overlay from 1.6 miles south of Big Stone County Road 68 to Pacific Ave in Ortonville $300,000 Not selected  