The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2020

Score Route  Description  High Level Cost Estimate for Planning Purposes  Year Planned (FY) Comments
100 I94 Mill and overlay from east of Melrose to east of Freeport $8,400,000 2029  
94 I94 Mill and overlay from Hwy 71/Sauk Centre to East of Melrose $9,900,000 2029  
92 MN15 Mill and overlay from Stearns County Road 47 to Stearns County Road 33 entrance Ramp $12,000,000 2030  
91 MN23 Mill and overlay from bypass to Jct Hwy 15 $10,000,000 2026  
90 I94 Mill and and overlay from east of Freeport to eastern limits of Albany $6,200,000 2027  
88 MN23 Mill and overlay from Hwy 15 to west of 4th ave South $5,600,000 2027  
87 US 12 Mill and overlay from Howard Lake to 72nd st in Delano $2,800,000 2022  
86 US 10 Mill and overlay from west of Hwy 371 to Morrison County Road 35 $5,800,000 2025  
86 US 10 Mill and overlay from Morrison County Road 35 to Benton County Road 40 $15,200,000 2027  
85 MN25 Mill and overlay from I-94 bridge to Jct Hwy10 $4,300,000 2028  
85 MN210 Reconstruction from end of River bridge in Brainerd to east of Hwy 25 $18,400,000 2025  
84 US 169 Mill and overlay from Ojibwe Dr to Garrison $4,500,000 2024  
83 US 10 Mill and overlay from County Road 11 to 3 miles west of Hwy 371 $12,400,000 2029  
83 US 10 Mill and overlay from 4.4 miles west of Clear Lake to 2.2 miles west of Clear Lake $1,200,000 Not Selected Not a district priority. Will continue to monitor pavement performance.
83 US 169 Mill and overlay from north of Mille Lacs County Road 29 to 2.3 miles south of Milaca $9,400,000 2025  
80 MN25 Mill and overlay from north of 14th St to the southern limits of Monticello $5,400,000 2025  
80 MN210 Mill and overlay from Hwy 10 to Pillager $5,000,000 2026  
79 US 10 Mill and overlay from west of Oink Joint Rd to Staples City Limits $13,000,000 2029  
78 MN23 Mill and overlay from east of Stearns County Road 12 to end of bypass $15,100,000 2027  
78 MN101 Mill and overlay from Hennepin/Wright County Line to south of Wright County Road 42 $2,500,000 2025  
77 US 10 Mill and overlay from Main st in Elk River to Hwy 101 in Elk River $400,000 Not Selected Not a district priority. Will continue to monitor pavement performance.
77 US 71 Mill and overlay from 4th St in Sauk Centre to 230th in Long Prairie $13,700,000 2027  
77 US 71 Mill and overlay from Todd/Wadena County line to Franklin Ave in Wadena $3,000,000 2027  
76 US 10 Mill and overlay from Long Prairie River to 50th Ave $17,800,000 2028  
76 MN23 Mill and overlay from District 3/8 border to Hwy 23B $200,000 Not Selected Conditions on the ground are not deteriorating as fast as the model is predicting
76 MN55 Mill and overlay from Hwy 25 to east of Wright County Road 134 $4,200,000 2026  
76 US 71 Mill and overlay from Elm Ave in Wadena to 5th St in Sebeka $10,200,000 2026  
74 US 169 Mill and overlay from south of Hwy 23 in Milaca to North of Mile Drew Brook $8,100,000 2028  
74 MN371 Mill and overlay from Cass County Road 5 in Hackensack to North of Hwy 200 $4,000,000 2025  
71 US 2 Mill and overlay from Cass County Road 206 in Cass Lake to east end of Bridge 5760 $3,200,000 2022  
71 MN23 Mill and overlay from Hwy 25 to Benton County Road 53 $1,400,000 2030  
71 US 169 Mill and overlay from South of Rum River bridge to Reference Pt 204 $700,000 Not Selected Not a district priority. Will continue to monitor pavement performance.
71 MN210 Thick overlay from Pillager to Baxter City Limits $6,500,000 2030  
70 US 71 Mill and overlay from 5th St in Sebeka to Wadena/ Hubbard County line $7,700,000 2027  
70 MN101 Minor rehabilitation from Wright County Road 42 to bridge over Hwy10 $2,100,000 2030  
70 US 169 Mill and overlay from Aitkin County Line to Aitkin County Road 76 $8,500,000 2029  
70 US 169 Milll and overlay from Mill Lacs County Road 103 to Vineland $4,500,000 Not Selected Not a district priority. Will continue to monitor pavement performance.
59 US 2 Thin mill and overlay from Hubbard/Cass County Line to Cass County Road 206 in Cass Lake $2,900,000 2025  
69 MN24 Reclaim and overlay from I-94 ramps to east of Sherburne County Road 8 $600,000 Not Selected Not a district priority. Will continue to monitor pavement performance.
69 MN371 Reclaim and overlay from Steamboat River Bridge to Reference point 112 $8,000,000 2030  
68 MN210 Mill and overlay from east end of Hospital Parking lot to Hwy 6 in Deerwood $4,200,000 2027  
68 MN371 Mill and overlay from Hwy 200  to north of Highland Ave $7,000,000 2027  
65 I94 Mill and overlay from Hwy 24 in Clearwater to North of Albertville $7,600,000 Not Selected Recently resurfaced in 2019
65 MN210 Mill and overlay from Wisconsin ave in Hewitt to Hwy10 $11,200,000 2027  
63 I94 Minor rehabilitation from Douglass/Todd County line to Hwy 71 in Sauk Centre $11,600,000 2030  
63 US 169 Mill and overlay from North end of Mississippi River Bridge to Aitkin County Road 18 $4,800,000 2024 Coordinated with D1 project
63 US 169 Mill and overlay from Aitkin County Road 18 to Hwy 200 in Hill City  $5,000,000 2025 Coordinated with D1 project
61 MN28 Reclaim and overlay from Pope/Stearns County Line to Hwy71 $3,400,000 Not Selected  
60 MN210 Mill and overlay from Ottertail/Todd County Line to Wisconsin Ave in Hewitt $1,400,000 2025  
59 I94 Reclaim and overlay from east limits of Albany to Stearns County Road 159 $14,000,000 2030  
58 MN34 Mill and overlay from Hubbard/Cass County Line to Hwy 371 $3,400,000 2026  
53 MN371 Thick overlay from Hwy 210 to North of Crow Wing County Road 13 $12,100,000 2029  
42 MN23 Mill and overlay from County Road 53 to South end of bridge 48030 $3,200,000 2022 Selected prior to policy (in 2019-2022 STIP)
40 MN15 Mill and overlay from Railroad crossing in Kimball to Hwy 55 $100,000 2021 Selected prior to policy (in 2019-2022 STIP)
40 MN371 Mill and overlay from Hwy 10 to Morrison County Road 48 $9,100,000 2030  
39 MN65 Diamond Grinding from Cambridge to Isanti County Road 30 $800,000 Not Selected  
37 US 10 Mill and overlay from Becker County Road 40 to Railroad crossing in Saint Cloud $10,200,000 2029  
37 US 71 Reclaim and overlay from North of Hwy 55 in Belgrade to bridge over I-94 $5,900,000 Not Selected  
32 US 169 Unbonded overlay from Hwy 210 to North end of Mississippi River Bridge  $1,900,000 2022 Selected prior to policy (in 2019-2022 STIP)
20 MN23 Medium mill and overlay from Hwy 23B to 1.1 miles east of County Road 12 $2,000,000 2022 Part of D8 project in 2022