The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2020

Score Route  Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
84 US 2 Resurface eastbound lanes of Hwy 2 from East Grand Forks Fisher $5,400,000 2028  
81 US 2 Resurface westbound lanes of Hwy 2 from Fosston to Bagley $7,400,000 2028  
81 US 71 Resurface Hwy 71 from Beltrami County Road 22 to Hwy 72 $3,100,000 2026  
78 US 59 Resurface Hwy 59 from Hwy 2 to Brooks $2,800,000 2030  
75 US 2 Resurface westbound lanes of Hwy 2 from Hwy 59 to Fosston  $5,000,000 2027  
61 MN 11 Resurface Hwy 11 from Roseau to Hwy 313 $6,100,000 2025  
74 US 2 Resurface westbound lanes of Hwy 2 from East Grand Forks to Fisher $9,200,000 2021  
74 US 59 Resurface Hwy 59 from Brooks to Thief River Falls $4,300,000 2023  
74 US 71 Resurface Hwy 71 from Beltrami County Road 15 to Beltrami County Road 22 $1,900,000 2028  
73 US 2 Resurface westbound lanes of Hwy 2 from Fisher to Hwy 75 $2,000,000 2021  
73 US 2 Resurface Hwy 2 from the south Beltrami County line to Midge Lake $5,000,000 Not selected District does not expect pavement segments to deteriorate as fast as the model predicts
73 US 71 Resurface Hwy 71 from Hwy 197 to Beltrami County Road 15 $5,500,000 2022  
72 MN 34 Resurface Hwy 34 from the west Hubbard County line to Park Rapids $1,100,000 2024  
72 US 71 Resurface Hwy 71 from Menahga to the north Wadena County line $1,500,000 Not selected Coordinating funding with another district 
71 US 2 Resurface the eastbound lanes of Hwy 2 from Fosston to Bagley $6,100,000 2028  
69 US 2 Resurface Hwy 2 from Wilton to Beltrami County Road 11 $3,000,000 2028  
69 US 2 Resurface Hwy 2 from Cass Lake to Cass County Road 10 $1,000,000 2021  
69 MN 11 Resurface Hwy 11 from Warroad to east Roseau County line $2,900,000 2027  
69 MN 371 Resurface Hwy 371 from th Steamboat River Bridge to Cass Lake $2,100,000 2030  
66 US 2 Resurface eastbound lanes of Hwy 2 from Hwy 9 to Hwy 32 $5,800,000 2022  
66 US 2 Resurface Hwy 2 from the Mississippi River Bridge to Itasca County Road 18 $500,000 2021  
66 MN 11 Resurface Hwy 11 from Karlstad to east Kittson County line $2,200,000 Not selected Not a district priority, will continue to monitor pavement performance 
66 MN 34 Resurface Hwy 34 from Akeley to the west Cass County line $1,200,000 Not selected Waiting to coordinate with another project
66 US 71 Resurface Hwy 71 from the north Itasca County line to the north junction of Hwy 1 $1,800,000 Not selected Coordinating funding with another district 
65 MN 11 Resurface Hwy 11 from the North Dakota border to 1-mile to the east $300,000 Not selected Waiting to coordinate with another project
67 US 2 Resurface Hwy 2 from Cass Lake to Hubbard County Road 25 $2,400,000 2025 Majority of this project is in District 3
58 MN 11 Resurface Hwy 11 from Williams to Lake of the Woods County Road 66 $2,400,000 Not selected Not a district priority, will continue to monitor pavement performance 
57 US 59 Resurface Hwy 59 from Winger to Hwy 2 $1,500,000 2021  
53 MN 32 Resurface Hwy 32 from Middle River to Hwy 11 $5,200,000 2024  
53 MN 34 Resurface Hwy 34 from the west Cass County line to Hwy 371 $2,700,000 Not selected Coordinating funding with another district 
41 US 2 Reconstruct eastbound lanes of Hwy 2 from Hwy 32 to Erskine $48,700,000 2021  
36 US 2 Reconstruct eastbound lanes of Hwy 2 from Hwy 59 to Fosston $28,300,000 2022  
28 US 71 Resurface Hwy 71 from Lake George to Hwy 71 $1,700,000 2030 RQI forecast doesn't reflect on the ground conditions
18 US 2 Resurface the eastbound lanes of Hwy 2 from Fisher to Crookston $6,400,000 2030 RQI forecast doesn't reflect on the ground conditions
11 US 71 Resurface Hwy 71 from the north Wadena County line to Park Rapids $1,300,000 Not selected  