Non-National Highway System pavement projects

MnDOT District 7

How the projects scored in 2019

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2019

Score Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
92 MN19 Medium overlay from Highway 15 to the west city limits of Gaylord $7,800,000 Not selected District is focusing on pavements previously selected and those currently in worse condition
90 MN22 Medium overlay from 10th Street SW to 6th Avenue NE $14,000,000 2023
88 MN22 Reclaim and overlay from Highway 111 to north of Sibley County Road 67  $5,200,000 2020
88 MN91 Medium overlay from the northern city limits of Adrian to the Nobles/Murray county line $5,100,000 2020
88 MN111 Reclaim and overlay from Highway 99 to Highway 22 $4,900,000 2020
87 MN5 Medium overlay from 5th Street on north side of Green Isle to Highway 212 $2,300,000 2021
87 US75 Medium overlay from Veteran's Drive in Luverne to Highway 268/Trosky (D7/D8) $6,400,000 2025
86 US75 Medium mill and overlay from north end of the bridge over I-90 and the I-90 ramp $500,000 2025
86 MN22 Medium overlay from north of Highway 83 to Bassett Drive in Mankato $1,300,000 Not selected Removed from CHIP to include with a future larger Highway 22 project. 
85 MN99 Medium mill and overlay from Birch Street to Highway 169 $4,300,000 2021
85 MN15 Medium overlay from the Iowa/Minnesota State line to Johnson Street in Fairmont $4,500,000 2028
85 MN83 Reclaim and overlay from north of Blue Earth County Road 173 to east of Blue Earth County Road 41 (near Mankato) $7,200,000 Not selected Corridor needs more evaluation
84 MN99 Medium overlay from Le Center to west of Highway 13 $2,800,000 2027
84 MN22 Reconstruction from north of the Blue Earth County Road 90 to 0.5 miles north of Blue Earth County Road 90 $700,000 Not selected Smaller segment. Should be included in a future larger Highway 22 project
83 US75 Medium overlay from the Iowa/MN state line to north of 101st Street $4,600,000 2028
83 MN13 Reclaim and overlay from north of Highway 60 to Highway 99 $9,100,000 2028
83 MN270 Reclaim and overlay from the railroad overpass at Hills to Highway 75 $5,800,000 Not selected Potential turnback, coordination with local partners will be needed
82 MN4 Medium overlay from Watonwan County Road 26 to Highway 60 $21,000,000 2022
82 MN4 Reclaim and overlay from Watonwan County Road  12 to south side of Sleepy Eye $15,000,000 2023
82 MN13 Medium mill and overlay from Waseca County Road 30 to  South of Highway 60 $3,900,000 2026
82 MN13 Medium overlay from Highway 99 to Highway 21/south of Montgomery city limits $1,600,000 2028 Part of Waterville to Montgomery Project
82 MN5 Reclaim and overlay from Division Street in Gaylord to Sibley County Road 17 $4,100,000 Not selected Not a current district priority, but will continue to monitor for pavement performance
82 MN13 Medium overlay from 5th Street SE to Waseca County Road 13 $600,000 Not selected Waiting to coordinate with another project.
81 MN13 Medium mill and overlay from Highway 21 to southern Montgomery city limits $800,000 2028
81 MN19 Medium mill and overlay from the New Prague to east of Alton Avenue $500,000 2029
81 MN19 Medium mill and overlay from east of Red Wing Avenue to east of LeRoy Avenue South  $900,000 2029
81 MN264 Reclaim and overlay from Round Lake to north ramps at I-90 $5,600,000 Not selected Potential turnback, coordination with local partners will be needed
80 MN253 Reclaim and overlay from Faribault County Road 2 to I-90 $3,500,000 2020
80 MN254 Reclaim and overlay from 1st Street to I-90 $2,600,000 2020
80 MN19 Repair Concrete from Highway 4 to Highway 15  $21,000,000 Not selected Continue to monitor for pavement performance
80 MN68 Reclaim and overlay from Highway 15 south of New Ulm to Highway 169 $16,000,000 2029
80 MN93 Medium overlay from Bridge 72007 (near Le Sueur) to Highway 169 $400,000 Not selected Waiting to coordinate with another project.
79 MN22 Medium mill and overlay from north of Sibley County Road 67 to Gaylord city limits $200,000 2020
79 MN22 Medium mill and overlay from south of Highway 83 to north of Highway 83 $400,000 Not selected Smaller segment. Should be included in a future larger Highway 22 project
79 MN22 Medium mill and overlay from north of Blue Earth County Road 90 to north of Hungry Hollow Road $400,000 Not selected Should be included in a future larger Highway 22 project
79 MN22 Medium mill and overlay from north of Hungry Hollow Road to north of Maple Hill Road $200,000 Not selected Should be included in a future larger Highway 22 project
78 MN4 Medium mill and overlay from the Iowa/Minnesota state line to Martin County Road 26 $3,700,000 2020
78 MN30 Medium overlay from Highway 22 to Highway 83 $3,800,000 2020
78 MN99 Medium overlay from Highway 13 to Highway 21 $2,800,000 2020
78 MN30 Medium mill and overlay from Cottonwood County Road 7 to Highway 71 $6,200,000 2021
78 MN13 Thick overlay from Montgomery city limits to New Prague $5,500,000 Not selected Waiting to coordinate with another project.
78 MN30 Medium mill and overlay from East of Highway 169 (Amboy eastern city limits) to east of Troendle Street SW $5,200,000 Not selected Not a current district priority, but will continue to monitor for pavement performance
78 MN109 Medium mill and overlay from Winnebago to east of 560th Avenue (west of Wells) $11,000,000 Not selected Not a current district priority, but will continue to monitor for pavement performance
77 MN93 Medium mill and overlay from Highway 169 to the southern city limits of Henderson $1,600,000 2022
77 MN22 Medium mill and overlay from the Iowa/Minnesota state line to  Faribault County Road 16 $10,000,000 2027  
77 MN257 Reclaim and overlay from southern city limits of Hanska to Highway 15 $2,900,000 2028
77 MN19 Medium mill and overlay from east of Highway 169 to east of Le Sueur County Road 143 $6,100,000 2029  
77 MN19 Medium mill and overlay from west of 11th Avenue SW to the New Prague $200,000 2029  
76 MN22 Reclaim and overlay from Faribault County Road 16 (where Highway 22 turns North) to 10th Street SW in Wells $3,800,000 2025  
76 MN83 Medium mill and overlay from west of Ichabod Lane to Highway 22/Victory Drive $200,000 Not selected
76 MN99 Medium mill and overlay from the railroad crossing on the East side of St. Peter to the Western city limits of Le Center $12,000,000 Not selected
75 MN13 Medium mill and overlay from MN30 to 1.5 miles South of Waseca $3,900,000 Not selected
74 MN4 Medium mill and overlay from Highway 68 to Highway 19  $6,600,000 Not selected
74 MN60 Major concrete rehabilitation from Highway 13 to east of TH13 $200,000 Not selected
73 MN91 Medium mill and overlay from the southern city limits of Adrian to 8th Street in Adrian $300,000 2020 Selected prior to policy (in 2019-2022 STIP)
73 MN19 Medium mill and overlay from west of Highway 169 to west of Highway 169 $700,000 2029 Small segment with bridge work that will be included with a project on Highways 13/19/169
73 MN4 Medium overlay from 3rd Avenue NW in Sleepy Eye to North side of Highway 68 intersection $1,300,000 Not selected
73 MN13 Medium overlay from Highway 30 in New Richland to 2.2 miles North of Highway 30 $1,100,000 Not selected
72 MN91 Reclaim and overlay from southern Ellsworth city limits to North Avenue in Ellsworth $1,300,000 Not selected
71 MN30 Thin overlay Blue Earth County Road 24 to west end of Bridge 07038  $4,600,000 2026 Selected prior to policy (in 2019-2028 CHIP)
71 MN19 Medium mill and overlay from east of Le Sueur County Road 143 to west of 11th Avenue SW $300,000 2029 Selected prior to policy (in 2019-2028 CHIP)
71 MN22 Medium mill and overlay from Linden Avenue to North Avenue in Gaylord $400,000 Not selected
71 MN86 Reclaim and overlay I-90 to Highway 60 $19,000,000 Not selected
70 MN263 Reclaim and overlay from Ceylon to I-90 $6,200,000 2021 Selected prior to policy (in 2019-2022 STIP)
70 MN22 Medium mill and overlay north Sunrise Drive in St. Peter to south of Nicollet Count Road 20 $300,000 2024 Small segment that will be included in larger Highway 22 project
70 MN19 Medium mill and overlay from railroad bridge east of Henderson to east of Henderson Station Road $200,000 2025 Segment part of larger Highway 19 project
70 MN30 Medium overlay from the Highway 169/Amboy city limit to east of the South Junction of Highway 169 $900,000 Not selected
70 MN19 Medium mill and overlay from East of Alton Avenue to Red Wing Avenue  $200,000 2029 Selected prior to policy (in 2019-2028 CHIP), previously selected because of bridge and highway work to the west
70 MN83 Medium mill and overlay from east of Blue Earth County Road 41 (near Mankato) to west of Blue Earth County Road 41 $200,000 Not selected
70 MN91 Reclaim and overlay from Iowa/Minnesota state line to Ellsworth $800,000 Not selected
69 MN30 Medium mill and overlay from Highway 83 to western city limits of New Richland $3,400,000 2020 Selected prior to policy (in 2019-2022 STIP)
69 MN22 Medium mill and overlay from Maple Hill Road to  south of the Junction of Highway 83 $400,000 2029 Smaller segment. Will likely be included in larger Highway 22 project
68 MN60 Reclaim and overlay Highway 14 to Waterville $18,500,000 2021 Selected prior to policy (in 2019-2022 STIP)
68 US59 Medium mill and overlay from Iowa/Minnesota state line to the South Junction of Highway 60 $2,300,000 Not selected
68 MN62 Medium mill and overlay from East Fulda city limits to Plum Avenue in Windom $12,000,000 Not selected
67 MN30 Medium mill and overlay from east of Troendle Street SW in Mapleton to western city limits of Mapleton $500,000 Not selected
67 MN60 Major concrete rehabilitation from east of 3rd Street in Waterville to Highway 13 $300,000 Not selected
66 MN83 Medium mill and overly from Highway 30 to Blue Earth County Road 173 $6,900,000 Not selected
65 MN19 Medium mill and overlay from Henderson to the Sibley/Le Sueur county line $600,000 2025 Selected prior to policy (in 2019-2028 CHIP)
65 MN19 Medium mill and overlay from east of LeRoy Avenue South to Highway 13 $200,000 2029 Selected prior to policy (in 2019-2028 CHIP)
65 MN4 Major Concrete rehabilitation/diamond grinding from Willow Street NW to 3rd Avenue NW  $800,000 2027 Selected prior to policy (in 2019-2028 CHIP)
65 MN30 Reclaim and overlay from Highway 71 to Highway 4 $26,000,000 Not selected
65 MN5 Medium mill and overlay from Sibley County Road 15 to South of 5th Street  $300,000 Not selected
65 MN13 Medium mill and overlay from Waseca County Road 103 to 5th Street SE in Waseca $800,000 Not selected
64 MN91 Reclaim and overlay from North Avenue in Ellsworth to NE of Chaney Avenue $3,500,000 Not selected
63 MN4 Thick overlay from Highway 60 near St. James to the west junction of Highway 60 $300,000 2022 Selected prior to policy (in 2019-2022 STIP)
63 MN22 Medium mill an overlay from Fairbault County Road 6 to the West Junction of Faribault County Road 16 $400,000 2027 Selected prior to policy (in 2019-2028 CHIP), Coordinating with another MnDOT project
63 MN30 Thin overlay from west end of Bridge 07038 to the Highway 169 $800,000 2026 Selected prior to policy (in 2019-2028 CHIP)
62 MN4 Major Concrete rehabilitation/diamond grinding from the bridge over Highway 60 to Watonwan County Road 12  $400,000 Not selected
61 MN13 Medium overlay Waseca City limits to Waseca County Road 103 (South of Waseca) $400,000 Not selected
61 MN91 Reclaim and overlay from Dayton Avenue to the southern city limits of Adrian $2,500,000 Not selected
59 MN99 Medium mill and overlay city limits of Nicollet to Heideman Avenue in Nicollet $500,000 Not selected
58 MN60 Reclaim and overlay  from Highway 14 to north of Highway 14  $200,000 2021 Selected prior to policy (in 2019-2022 STIP)
58 MN91 Reclaim and overlay from NE of Chaney Avenue to Dayton Avenue $1,500,000 Not selected  
54 MN30 Medium mill and overlay from Murray/Cottonwood County line to Cottonwood County Road 7  $400,000 2021 Selected prior to policy (in 2019-2022 STIP)
54 MN22 Medium mill and overlay from south of the West Junction of Highway 212 to Highway 212 $200,000 Not selected  
53 MN30 Thin  overlay from Highway 15 to Blue Earth County Road 24 $1,600,000 2026 Selected prior to policy (in 2019-2028 CHIP)
50 MN19 Medium mill and overlay from Highway 5 to Henderson $6,600,000 2025 Selected prior to policy (in 2019-2028 CHIP)
46 US75 Thick mill and overlay from James Street to Veteran's Drive $1,300,000 2025 Selected prior to policy (in 2019-2028 CHIP)
45 MN21 Medium mill and overlay from Highway 99 to Highway 13 (South of Montgomery) $4,400,000 2027 Selected prior to policy (in 2019-2028 CHIP)
43 MN22 Medium mill and overlay from south of Nicollet County Road 20 to Highway 111 $5,300,000 2024 Selected prior to policy (in 2019-2028 CHIP)
43 US75 Medium overlay from north of 101st Street to the north end of the Bridge over I-90 $200,000 2028 Selected prior to policy (in 2019-2028 CHIP)
43 MN68 Reclaim and overlay from Morgan to the North Junction of Highway 4 $9,000,000 Not selected
42 MN4 Minor concrete rehabilitation from Sleepy Eye to Elsworth Street in Sleepy Eye $200,000 2023 Selected prior to policy (in 2019-2028 CHIP)
41 MN19 Medium mill and overlay from East of Henderson Station Road to west of Highway 169 $800,000 2025 Selected prior to policy (in 2019-2028 CHIP)
39 MN22 Medium overlay from North Avenue to south of Highway 212 $11,500,000 Not selected
39 MN86 Reclaim and overlay from Iowa/Minnesota state line to Bridge 32084 (ramps North of I90) $7,400,000 Not selected
35 MN83 Medium overlay from west of Blue Earth County Road 41 (near Mankato) to west of Ichabod Lane $200,000 Not selected  
34 MN91 Reclaim and overlay from 0.3 miles north of North Avenue in Ellsworth to 1 mile north of North Avenue $700,000 Not selected
31 MN109 Medium overlay from east of 560th Avenue (west of Wells) to the western city limits of Wells $400,000 Not selected  
30 MN19 Medium mill and overlay from the Sibley/Le Sueur county line to railroad bridge east of Henderson $400,000 2025 Selected prior to policy (in 2019-2028 CHIP)
25 MN5 Medium mill and overlay from 4th Avenue East to Sibley County Road 15  $2,900,000 Not selected
23 MN22 Reconstruction from Blue Earth County Road 15 to County Road 90 $11,500,000 Not selected
16 MN13 Minor concrete rehabilitation from 0.2 miles south of Highway 60 to 0.2 miles north of Highway 60 $100,000 Not selected