The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated December 2019

Score Bridge number Route Key intersection or closest landmark Work type Year planned (FY)  High level construction cost estimate for planning purposes  Comments
90 9507 Mower County Highway 13 I-90 Redeck  2024 $800,000
90 85002 MN 74 Beaver Creek Replace Not selected $100,000 Not a current district priority, continue to monitor for performance issues
80 50004 MN 16 Deer Creek Overlay deck surface Not selected $500,000 Bridge still in relatively good condition, continue to monitor condition
80 85818 I 90 EB Highway 74 Re-overlay deck surface Not selected $200,000 Not a current district priority, continue to monitor for performance issues
70 28009 MN 16 Root River Overlay deck surface Not selected $200,000 Not a current district priority, continue to monitor for performance issues
70 9105 MN 76 Money Creek Overlay deck surface Not selected $300,000 Not a current district priority, continue to monitor for performance issues
70 85843 I-90 WB County Road 7 Re-overlay deck surface Not selected $100,000 Not a current district priority, continue to monitor for performance issues
65 9183 MN 105 I-90 Replace 2023 $3,000,000 Coordinated with a pavement project
65 9062 US 61 NB Cedar Creek Replace 2024 $1,800,000 Selected prior to scoring policy (in 2020-2029 CHIP)
55 6862 MN 57 Zumbro River Replace Not selected $600,000
40 25007 MN 19 Prairie Creek Re-overlay deck surface Not selected $100,000
20 9505 MN 56 I-90 Redeck 2024 $800,000 Selected prior to scoring policy (in 2020-2029 CHIP)
20 9662 MN 60 Highway 2 Replace 2025 $1,800,000 Selected prior to scoring policy (in 2020-2029 CHIP)
20 9848 MN 16 Crystal Creek Replace 2029 $2,000,000 Selected prior to scoring policy (in 2020-2029 CHIP)
10 6468 MN 56 Rose Creek Replace 2024 $1,000,000 Selected prior to scoring policy (in 2020-2029 CHIP)
0 9856 Mower County Highway 6 I-90 Redeck 2024 $700,000 Selected prior to scoring policy (in 2020-2029 CHIP)