The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).
Last updated December 2019
| Score | Culvert number | Route | Key intersection or closest landmark | Work type | Year Planned (FY) | High level construction cost estimate for planning purposes | Comments |
|---|---|---|---|---|---|---|---|
| 66 | 6292 | MN 210 | Island Lake Outlet | Replace | 2029 | $400,000 | Being delivered with culverts 4560 and 6290 |
| 66 | 6290 | MN 210 | Otter Creek | Replace | 2029 | $400,000 | Being delivered with culverts 4560 and 6292 |
| 64 | 4650 | MN 210 | Stony Brook | Replace | 2029 | $400,000 | Being delivered with culverts 6292 and 6290 |
| 63 | 6293 | MN 210 | Tamarack River | Replace | 2026 | $350,000 | Being delivered with culverts 4321 6293,6295, 8448 and 8449 |
| 63 | 8448 | MN 210 | Sandy River | Replace | 2026 | $350,000 | Being delivered with culverts 6293, 6295, 4321 and 8449 |
| 61 | 89395 | MN 73 | Stream near Janette Lake in Hibbing | Replace | 2023 | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
| 46 | 8792 | MN 135 | West Two Rivers | Replace | 2025 | $200,000 | Selected prior to policy (in 2019-2028 CHIP) |
| 28 | 6295 | MN 210 | Sandy River | Replace | 2026 | $350,000 | Being delivered with culverts 6293, 4321, 8448 and 8449 |
| 13 | 4321 | MN 210 | County Ditch #42 | Replace | 2026 | $350,000 | Being delivered with culverts 6293, 6295, 8448 and 8449 |
| 13 | 8449 | MN 210 | Sandy River | Replace | 2026 | $350,000 | Being delivered with 6293,6295, 8448 and 4321 |