Interstate Access Requests/Interstate Modification Requests flowcharts

The following flowcharts summarize the IAR/IAMR process and its interactions with NEPA. The flowcharts illustrate interrelationships between steps, including which steps occur in parallel versus in series. Each step referenced in the flowcharts is described in detail in the step-by-step process in TPDP

Figure 1: IAR/IAMR process overview
Figure 2: IAR/IAMR process