We'd love your feedback! Your experience on our website matters to us. If you have suggestions, comments, or notice anything that could be improved, please take a moment to share your thoughts using our feedback form. Thank you for helping us make our site better for everyone.

Minnesota Department of Transportation

511 Travel Info

Project development

Engineering process | Scoping | Interstate Access Requests/Interstate Access Modification Requests

Interstate Access Requests/Interstate Modification Requests flowcharts

The following flowcharts summarize the IAR/IAMR process and its interactions with NEPA. The flowcharts illustrate interrelationships between steps, including which steps occur in parallel versus in series. Each step referenced in the flowcharts is described in detail in the step-by-step process in TPDP

Figure 1: IAR/IAMR process overview
Figure 2: IAR/IAMR process