Minnesota Department of Transportation

511 Travel Info

Hwy 59 Concrete Repair

South of Marshall

Project work zones and detours

Map of Hwy 59 work south of  Marshall from the intersection of Hwy 23 to the intersection of County Road 6.
Map of Hwy 59 project from intersection of Hwy 14 to intersection of Hwy 30 near Currie.

Summary of work

Originally, MnDOT planned to repair and diamond grind sections of the concrete pavement on Hwy 59 in two locations (see below). Diamond grinding is a process that makes the pavement smoother.

  • Hwy 59 from the intersection of Hwy 23 in Marshall to the intersection of Lyon County Road 6 (south of Marshall).
  • Hwy 59 from the intersection of Hwy 14 (near Garvin) to just north of the intersection of Hwy 30.

However, the project is being scaled back as crews encountered more repairs than were originally estimated. The roadway had deteriorated from the bottom up in many places and the full extent of repair work wasn't known until crews began removing the old concrete pavement.

MnDOT looked for additional funding options, but not enough funding was available to repair the entire stretch of roadway as originally planned. A future project will be introduced to allocate the funding required to repair the remaining segments. The project has been updated as follows.

Road sections to be fully or partially completed

  • Hwy 59 from Hwy 14 to Lyon County Road 14 through Garvin
  • Hwy 59 from Lyon County Road 14 to 241st St
  • Hwy 59 from Hwy 30 to 201st St

Road sections to be postponed

  • Hwy 59 from Hwy 23 in Marshall to Lyon County Road 6
  • Hwy 59 from 241st St to 201st St

Traffic impacts

  • Hwy 59 is closed to through traffic from Hwy 14 to Hwy 30; follow the detour for that route - see map above.
  • Homes and businesses along Hwy 59 will always have access to/from the nearest intersection.
  • Reach Lake Shetek using County Road 48 from the detour route.
  • Allow extra travel time and expect delays.

Project updates

September 17, 2021: work is taking place between Hwy 14 and Hwy 30

  • Diamond grinding work continues
  • Crews are working on some of the repairs that require additional work
  • Repairs at RR crossing are scheduled for next week

Crews are replacing sections of concrete on US 59