Hwy 10, 75 - 11th Street Underpass Project

Moorhead

Current traffic impacts

Detour map for the 11th Street underpass project.
Detour map for Stage 1A closures
  • First Avenue closed between 10th Street and 12th Street, portion of Eighth Street closed north of First Avenue, and 11th Street closed between Second Ave North and Main Avenue, with Center Avenue remaining open to traffic.
    • Detour to/from North Moorhead: 14th Street North, Fourth Avenue North and Ninth Street North.
    • East/west detour: Eighth Street North, Center Avenue and 14th Street.
    • Heading south? Use Eighth Street or 14th Street N to Main Avenue to 11th Street
  • Residents/travelers can expect loud noises and vibrations throughout the area during piling operations.

Have questions? Join us at an upcoming open house:

  • May 2, 9:30 to 10:30 a.m.,  at the Hjemkomst Center, 202 1st Ave N, Moorhead

Construction schedule

Construction will be completed in phases, starting in spring 2024 through fall 2026.

  • 2024: Bridge construction and Stage 1 (portions of First Avenue & 11th Street at railroad crossings up to 2nd Ave N)
  • 2025: Portion of Stage 1 (First Avenue) and Stage 2 (Center Avenue & 11th Street under bridges from Main to First)
  • 2026: Stage 3 (Main Avenue and 11th Street from 2nd to Main)

Construction staging map for the 11th Street underpass project

Stay informed

You can sign up for project email updates, or submit questions or comments at any time by either using the comment form on the project home page, or by contacting a MnDOT representative directly by email or phone.

Join us at upcoming public open houses. Depending on attendance, these could become regularly scheduled meetings:

  • May 2, 9:30 to 10:30 a.m., at the Hjemkomst Center, 202 1st Ave N, Moorhead