Truck haulers plan ahead: Detour Aug. 25 to late October
Current impacts
2025 bridge work
MnDOT will replace the Hwy 200 bridge over the Willow River, just southeast of Hwy 6 in Remer, Cass County. A truck and through traffic detour is necessary to complete work.

Select project location map to enlarge (PNG)
Summary of work
- Replace Hwy 200 bridge with a double-box structure
- Resurface road approaches
- Update shoulder barriers/railing and ditch slope
- Install fresh road marks
Prep-work
Aug. 4-24
- The current Hwy 200 bridge will remain open to all travelers the first two weeks
- Motorists to encounter flaggers, slower speeds or sudden stops at the bridge as crews:
- Set-up work area along bridge
- Set-up the Hwy 200 detour
- Install a temporary one-lane bypass bridge for emergencies east of Hwy 200, includes temporary portable signals